Citizens Transportation Advisory Committee Maritime Subcommittee - - PowerPoint PPT Presentation

citizens transportation advisory committee maritime
SMART_READER_LITE
LIVE PREVIEW

Citizens Transportation Advisory Committee Maritime Subcommittee - - PowerPoint PPT Presentation

Citizens Transportation Advisory Committee Maritime Subcommittee Meeting May 11, 2011 Port of Miami Tunnel Benefits The Port of Miami Tunnel will: Provide a second access between the mainland the Port of Miami for the safeguard of cruise and


slide-1
SLIDE 1

Citizens’ Transportation Advisory Committee Maritime Subcommittee Meeting

May 11, 2011

slide-2
SLIDE 2

Port of Miami Tunnel Benefits

The Port of Miami Tunnel will:

  • Provide a second access between the mainland the

Port of Miami for the safeguard of cruise and cargo industries

  • Increase competitiveness at the POM by alleviating

traffic congestion and reducing travel times

  • Provide direct expressway access to I‐395, I‐95, and

SR‐836

  • Offer a direct connection between MIA and the

Seaport

  • Relieve congestion and improve safety on

Downtown Miami streets by diverting the Seaport’s commercial traffic

slide-3
SLIDE 3

Potential Construction Impacts

Analysis of Potential Impacts to Cruise and Cargo Business Report prepared for Board of County Commissioners and presented on December 20, 2010

  • Analyzed potential impact to

industry at the Port of Miami related to construction of the Port of Miami Tunnel

  • Addressed measures established

to mitigate and minimize such potential impacts

slide-4
SLIDE 4

Potential Construction Impacts

Impacts identified include:

  • Lane Closures
  • Maintenance of Traffic
  • Construction Work on Main Channel
slide-5
SLIDE 5

Lane Closures

  • Temporary Lane Closures may be required during

short periods

  • Closure requests must be submitted two weeks in

advance for review, approval, and notification

  • Lane Closure Advisory issued through Port’s Public

Information Manager as Port Bulletin to Port tenants and users

  • VMS required a week in advance as public notification
  • No closures are approved on the cruise roadway

network during cruise days

  • Lane closure requests on Port Boulevard only

approved during non‐peak cargo and cruise times

slide-6
SLIDE 6

Lane Closure Mitigation Strategy

  • Weekly Meetings held to discuss and plan future

closures

  • No closures approved for hours other than those

specified in the Concession Agreement

  • Pre‐activity Meetings held for any closure involving a

traffic shift, detour, or closure of more than one lane

  • Detailed Action Plan required describing means and

methods, and phasing of activities during closure

  • Contingency Plan required addressing provisions for

Contractor to follow FDOT directive to implement plan

  • Performance Points assessed for failure to adhere to

Action Plan

slide-7
SLIDE 7

Maintenance of Traffic Restrictions

  • MOT must ensure no reductions in existing lanes in
  • rder to maintain levels of service on roadways
  • Contractual Obligations to Maintain Dodge Island

Traffic during Construction

  • Heavy construction must not interfere with the peak traffic periods.
  • No construction traffic hauling operations from 6am to 6pm

between Friday and Monday (inclusive).

  • With the exception of one‐time movements, no operations allowed
  • n roads adjacent to Cruise Terminals.
  • One‐time movements may only occur during non‐peak days and they

need to be coordinated and approved by the Port in advance.

  • Access to parking facilities for cruise passengers must be maintained

at all times during construction.

slide-8
SLIDE 8

Construction Work on Channel

  • Most tunneling activities will

be underground with no impacts to channel or Port

  • perations
  • Ground treatment may be

required from the surface within limited construction windows

slide-9
SLIDE 9

Construction Work on Port

  • Work along cruise ship berths will not be performed

when vessels are on port

  • Access along the Cruise Terminals waterfront is to be

maintained at all times

  • Vessel provisioning operations cannot be interrupted
slide-10
SLIDE 10

Port of Miami Partners

  • The Port of Miami Tunnel Management Team has

maintained close communication with Port Partners

  • Two separate Project kick‐off meetings were held in

April 2010 with the Cruise and Cargo Stakeholders

  • Industry Stakeholder Meetings were held on

December 2010 and April 2011 to report Project progress and notify stakeholders of upcoming Dodge Island roadway traffic shifts

  • Follow‐up meetings will be held in May 2011 to address

specific issues related to MOT

slide-11
SLIDE 11

Looking Ahead

  • Top priority is to minimize impacts to

businesses at the Port during construction

  • Active and ongoing coordination between

Concessionaire, FDOT and Port staff

  • Ongoing bi‐monthly follow‐up with

partners (or as needed)