Faculty of Business and Economics, Chair of Energy Economics, Prof. Dr. Möst
Changing Electricity System Fabian Hinz 15th IAEE European - - PowerPoint PPT Presentation
Changing Electricity System Fabian Hinz 15th IAEE European - - PowerPoint PPT Presentation
Faculty of Business and Economics , Chair of Energy Economics, Prof. Dr. Mst The Influence of Voltage Stability on Congestion Management Cost in a www.ee2.biz Changing Electricity System Fabian Hinz 15th IAEE European Conference Vienna,
TU Dresden, Chair of Energy Economics, Fabian Hinz 2 06.09.2017
Future scenario 2025 4 Staus Quo 2014 3 Model Development 2 Motivation 1
TU Dresden, Chair of Energy Economics, Fabian Hinz 3 06.09.2017
Congestion management causes high cost
Development of congestion mgmt. cost, causes Congestion mgmt. cost [mio. EUR] 198 159 2013 2015 269 750 2014 2012 45 2006 2011 2008 164 32 30 2009 2007 58 2010 Redispatch & Countertrading Curtailment Loop flows
Loop flow via PL, CZ and AT Direct flow from North to South
Load vs. generation Load distribution Wind distribution
- Load concentrated in the South and West
- Wind concentrated in the North
- Power flows from
North to South cause loop flows via Eastern Europe
- Phase shifting
transformers being installed
Source: BNetzA Monitoring Reports 2007 - 2016
Challenge Current / Real power
TU Dresden, Chair of Energy Economics, Fabian Hinz 4 06.09.2017
Future supply Conventional supply Electricity feed-in 110 kV grid Medium / low voltage grid Transmission grid
Availability of reactive power in the transmission grid declines
Reactive power supply: conventional and future scenario
Source: Kraftwerksliste BNetA 2015, Netzentwicklungsplan 2015
Reactive power supply
- Conventional supply through
large power plants
- Availability in the
transmission grid decreases
- Supply can be replaced by
RES in the distribution grid Reactive power consumption Reactive power consumption
38% 51% 59% 62% 42% 28% 13% 2035 2025 2014 8%
DSO Offshore TSO Controllable reactive power
Challenge Voltage / Reactive power
TU Dresden, Chair of Energy Economics, Fabian Hinz 5 06.09.2017
Redispatch measures conducted in order to solve current and voltage problems
Current- and voltage-induced redispatch
Voltage-induced redispatch Current-induced redispatch Real power Reactive power
Redispatch Situation Power plant 1 not dispatched Power plant 2 fully dispatched Current too high Power plant 1 ramped up Power plant 2 ramped down Current okay Power plant 1 not dispatched Power plant 2 Reactive power Voltage too low Voltage okay Power plant 1 Reactive power Power plant 2 Reactive power Voltage okay Voltage okay
expan- sive cheap expan- sive cheap expan- sive cheap
Q
expan- sive cheap
Q Q
More expansive power plant ramped up in
- rder to alleviate transmission line
More expansive power plant ramped up in
- rder to provide reactive power
Redispatch cost
TU Dresden, Chair of Energy Economics, Fabian Hinz 7 06.09.2017
Future scenario 2025 4 Staus Quo 2014 3 Model Development 2 Motivation 1
TU Dresden, Chair of Energy Economics, Fabian Hinz 8 06.09.2017
Redispatch cost calculated in a 3-step approach
Model approach
Step 1 Market model Step 3 Reactive power: voltage-induced redispatch Step 2 Real power: current-induced redispatch
- Electricity market model (copper plate) for
Germany and neighboring countries to generate power plant dispatch
- NTC-based trade between market zones
- Only real power (P) dispatch
Reactive power behavior of 380 KV line
- 100
100 200 300 400 500 600 500 1000 1500
Reactive power [Mvar] Line load [MVA]
Q_cap Q_ind Q_tot
Iterative calculation of quadratic inductive reactive power behavior
- Estimation of current-induced redispatch based on
a transmission & 110 kV distribution grid model
- Usage of ELMOD to calculate load flows, overloads
and least-cost redispatch
- Penalty cost for international redispatch
- Estimation of reactive power dispatch and voltage-
induced redispatch
- Usage of ELMOD LinAC, a linearized AC model to
account for voltage stability and reactive power flows
- Iterative approach to account for quadratic
reactive power behavior of electricity lines
TU Dresden, Chair of Energy Economics, Fabian Hinz 9 06.09.2017
Redispatch models use linearized real and reactive power flow calculations
Simplified model formulation of redispatch models
1) Un / Um... Voltage magnitude at node n / m Θn / Θm... Voltage angle at node n / m gn,m / bn,m... Conductance / susceptance between node n and m
Target function Market model
Voltage-induced Redispatch Current-induced Redispatch
Restrictions 𝐍𝐣𝐨
𝒐∈𝑶
𝒅𝒑𝒕𝒖𝒐
𝒏𝒃𝒔𝒉 ∙ 𝑯𝒇𝒐𝒐 𝑸 − 𝒉𝒇𝒐𝒐 𝑸,𝒏𝒃𝒔𝒍𝒇𝒖
Thermal limit: 𝑴𝒋𝒐𝒇𝑫𝒗𝒔𝒔𝒇𝒐𝒖𝒎 ≤ 𝑼𝒊𝒇𝒔𝒏𝒃𝒎𝒎𝒋𝒏𝒋𝒖𝒎 Voltage TS: 𝟏, 𝟘𝟖 𝒒. 𝒗. ≤ 𝑽𝒐 ≤ 𝟐, 𝟏𝟒 𝒒. 𝒗. Voltage DS: 𝟏, 𝟘𝟓 𝒒. 𝒗. ≤ 𝑽𝒐 ≤ 𝟐, 𝟏𝟕 𝒒. 𝒗 𝑯𝒇𝒐𝒐
𝑸,
𝑯𝒇𝒐𝒐
𝑹
∈
GenP GenQ
Grid balance Real power: 𝑯𝒇𝒐𝒐
𝑸 − 𝑬𝒇𝒏𝒐 𝑸 = σ𝒏∈𝑶 𝒉𝒐,𝒏 𝑽𝒐 − 𝑽𝒏 − 𝒄𝒐,𝒏(𝜾𝒐−𝜾𝒏)
Reactive power: 𝑯𝒇𝒐𝒐
𝑹 − 𝑬𝒇𝒏𝒐 𝑹 − 𝑴𝒑𝒕𝒕𝒐 𝑹 =
σ𝒏∈𝑶 −𝒄𝒐,𝒏 𝑽𝒐 − 𝑽𝒏 − 𝒉𝒐,𝒏(𝜾𝒐−𝜾𝒏)
Iterative calculation
TU Dresden, Chair of Energy Economics, Fabian Hinz 10 06.09.2017
Current and voltage are represented reasonably well by the redispatch model
Model quality of ELMOD AC and ELMOD LinAC
Current [A]
Comparison between redispatch model (ELMOD LinAC) and AC load flow model (ELMOD AC), Germany, 16 grid situations
1) Adjusted Mean Absolute Percentage Error: adjusted in relation to nominal voltage / thermal limit 2) On 380 kV level
Voltage [p.u.]
LinAC MAE RSME aMAPE1) I [A] 22.9 39.6 0.69% LinAC MAE RSME aMAPE1) U [kV]2) 2.0 2.5 0.53%
Good fit for current Reasonable fit for voltage
TU Dresden, Chair of Energy Economics, Fabian Hinz 11 06.09.2017
110 kV grid set developed based on OSM data and other public sources
Data set for grid model Power plants / RES
Attribution to nodes
- Plants: based on
addresses and coordinates
- RES: based on OSM
data / RES database
Load
- Attribution based on
GDP and population of surrounding area Nodes: ~5700 Lines: ~6500 Substations: ~370
380 kV 220 kV 110 kV
OSM data
- Substations
380 / 220 / 110 kV
- Electricity lines
380 / 220 / 110 kV
- Nodes with
generation and demand
- Auxiliary nodes
- Lines start / end,
technical parameters updated with TSO static grid models
- Transformers
380 / 110 kV 220 / 110 kV
TU Dresden, Chair of Energy Economics, Fabian Hinz 12 06.09.2017
Future scenario 2025 4 Staus Quo 2014 3 Model Development 2 Motivation 1
TU Dresden, Chair of Energy Economics, Fabian Hinz 13 06.09.2017
Good fit between congestions in model and reality
Congested grid elements: Model results vs. reality Model results 2014 Monitoring report 2014
Frequency of congested grid elements
- Good fit between for
border areas to Poland, Czech Republic and Denmark
- Fit for Remptendorf-
Redwitz line
- Congestions in the
North West and Center not reliably recognized
- Distribution grid
congestions in the North fit local curtailment compensation
Source: BNetzA Monitoring Report 2015
TU Dresden, Chair of Energy Economics, Fabian Hinz 14 06.09.2017
Current-induced Current- and voltage induced
Taking into account voltage stability, redispatch patterns change
Results
- Ramp-down of power plants in the North
- Curtailment mainly in Schleswig-Holstein
- Ramp-up in the South and Austria
- Additional redispatch in the South to cover
reactive power requirements
- Additional ramp-downs in the North
High load and high wind feed-in situation: current- and voltage-induced redispatch
TU Dresden, Chair of Energy Economics, Fabian Hinz 15 06.09.2017
Reactive power from the 110 kV grid decreases voltage-induced redispatch cost
Redispatch costs 2014 in Germany
20 40 60 80 100 120 140 160 180 161.3 34.6 13.3 78.1 Cost p.a. [mio. EUR] with 110 kV sources
- 13.4
(-8%) Current-induced Current- / Voltage-induced 35.3 78.1 35.4 113.4 174.7 17.1 35.4 78.1 44.1 Curtailment U Redispatch I Curtailment I Redispatch U
- Redispatch and curtailment
cost is mainly current- induced
- 8% reduction possible
through reactive power from the distribution grid Redispatch cost Germany 2014
- Comparison of voltage- /
current- induced redispatch
- Cost reduction potential
from 110 kV grid reactive power sources
TU Dresden, Chair of Energy Economics, Fabian Hinz 16 06.09.2017
Future scenario 2025 4 Staus Quo 2014 3 Model Development 2 Motivation 1
TU Dresden, Chair of Energy Economics, Fabian Hinz 17 06.09.2017
Market zone split decreases redispatch cost more than 110 kV reactive power
Redispatch costs 2025 under full grid extension, combined and split DE/AT market zone
106 105 103 102 244 241 347 293 278 322 346 307 304 308
- 18
956
- 23
- 179
With 110kV sources 777 933 4 759 4 Status Quo With 110kV sources 4 4 Status Quo Int. redispatch AT DE PL CZ
Com- bined zone Zone split
- Cost reduction potential through 110 kV sources increases
- Overall reduction of redispatch cost through splitting of DE/AT market zone
Only redispatch cost! Additionally welfare effects on wholesale markets have to be considered! Redispatch cost 2025
- Comparison of DE/AT market zone and split
- Cost reduction potential from 110 kV grid reactive power sources
TU Dresden, Chair of Energy Economics, Fabian Hinz 18 06.09.2017
Considerably higher cost under grid extension delay – savings potential increases
Redispatch costs 2025 under full and delayed grid extension
293 278 14 14 703 703 4 4 178 179 249 260 241 244 445 443 304 308 105 1,930 1,894 With 110kV sources 2,825 Status Quo
- 23
1,659
- 46
Status Quo 106 +1,166 1,636 With 110kV sources 2,779 Grid extension PL Int. redispatch AT DE CZ
Full grid extension 5 year grid extension delay
- Considerably higher cost under grid extension delay
- Under grid extension delay , the cost reduction potential from 110 kV sources increases
Redispatch cost 2025
- Comparison of full and delayed grid extension
- Cost reduction potential from 110 kV grid reactive power sources
Annuity @ 4% WACC + 2% O&M cost
TU Dresden, Chair of Energy Economics, Fabian Hinz 19 06.09.2017
0.0 2.8 1.2 1.8 2.2 1.6 2.4 0.2 2.6 0.6 1.4 0.8 1.0 2.0 0.4 8 HVDC 1.65 7 HVDC 1.79 1.86 0.19 2.46 2.09 1.87 0 HVDC Delayed 0.34 0.43 1.37 1.61 1.55 0.70 4 HVDC 1.49 1.44 5 HVDC Full 0.79 1.31 6 HVDC 1.29 0.61 1.31 2 HVDC 3 HVDC 0.53 1.56 1.50 2.70 1 HVDC 1.60 1.68 Total cost [bn. EUR] 0.89 1.03 1.53 Grid extension cost Total cost - Market zone split Total cost - Market zone combined
Which degree of grid extension is economically reasonable?
Relationship between grid extension and redispatch cost Redispatch cost 2025
- Alteration of grid extension level (# of HVDC links)
- Comparison of total grid extension cost
TU Dresden, Chair of Energy Economics, Fabian Hinz 20 06.09.2017
Conclusions
Key take-aways
- Current- and voltage induced redispatch will play an
important role in future electricity systems
- Usage of 110 kV reactive power sources can slightly
limit redispatch costs
- Market zone layout has a much higher impact
- Grid extensions required to impede extreme cost
increases – number of HVDC links in grid development plan seems reasonable
Faculty of Business and Economics, Chair of Energy Economics, Prof. Dr. Möst
www.ee2.biz
Thank you for your attention!
- Dipl. Wi.-Ing. Fabian Hinz