Challenges of Continuous Parallel
Free Powerpoint Templates
Challenges of Continuous Parallel Operation of GTG Units in DPS A case study & Simulation
Presented By: Sri Rajib Kumar Sarmah Dy.SEE(Gen)
Date: 05-Dec-2014 Venue: Elect Conf Room
Challenges of Continuous Parallel Challenges of Continuous Parallel - - PowerPoint PPT Presentation
Challenges of Continuous Parallel Challenges of Continuous Parallel Operation of GTG Units in DPS A case study & Simulation Presented By: Date: 05-Dec-2014 Sri Rajib Kumar Sarmah Venue: Elect Conf Room Free Powerpoint Templates
Free Powerpoint Templates
Presented By: Sri Rajib Kumar Sarmah Dy.SEE(Gen)
Date: 05-Dec-2014 Venue: Elect Conf Room
Duliajan Power Station Present Scenario with 2 x 14.45 MW Gas Turbine Units
B/C 1 B/C 2 11 KV Unit 1 Inter. Unit 2 Inter. Unit 2 Gen. Unit 1 Gen. Bus A Bus B Bus C
OFF OFF ON ON ON ON
Gen. Bkr Gen. Bkr GT Unit 1 GT Unit 2 NGR Unit 1 NGR Unit 2
Duliajan Power Station Operating Condition with only One Unit Running
B/C 1 B/C 2 Unit 1 Inter. Unit 2 Inter. Unit 2 Gen. Unit 1 Gen. Bus A Bus B Bus C
ON ON ON ON ON OFF
11 KV Gen. Bkr Gen. Bkr GT Unit 1 GT Unit 2 NGR Unit 1 NGR Unit 2
Duliajan Power Station Operating Condition With Unit Running in Parallel
B/C 1 B/C 2 Unit 1 Inter. Unit 2 Inter. Unit 2 Gen. Bkr Unit 1 Gen. Bkr Bus A Bus B Bus C
ON ON ON ON ON ON
11 KV Bkr Bkr GT Unit 1 GT Unit 2 NGR Unit 1 NGR Unit 2
Circulating Zero Sequence Current
Eliminating Circulating Zero Sequence Current in Grid Connected Units
High Impedance Neutral Grounding System
Unit 1 Inter. Unit 2 Interrupter Bkr Bus A
ON ON Unit 1Interrupter Bkr
30 MVA, 11/ 132 KV Tr 2 22.6 MVA, 11/ 132 KV Tr 1 132 KV Unit 2 Gen. Bkr Unit 1 Gen. Bkr GT Unit 1, 15 MW GT Unit 2 , 20 MW NGT Unit 1
ON ON
NGT Unit 2 R R No circulating current between parallel running units
Option 1: IDEAL Solution: Scheme for DPS for Eliminating Circulating Zero
Sequence Current Using Unity Ratio Transformer & High Impedance Neutral Grounding System B/C 1 B/C 2 Unit 1 Inter. Unit 2 Interrupter Bkr Bus A Bus B Bus C
ON ON ON ON Unit 1Interrupter Bkr
20 MVA, 11/ 11 KV Tr 1 11 KV 20 MVA, 11/ 11 KV Tr 2 Unit 2 Gen. Bkr Unit 1 Gen. Bkr GT Unit 1 GT Unit 2 NGT Unit 1
ON ON
NGT Unit 2 R R NGT to be designed for Gen Stator Earth Fault < 20 A) There will not be any circulating current between parallel running units
switching is required and the scheme has to be fail safe design; so that if
unit does not remain ungrounded.
connected to ground automatically to prevent ungrounded operation of any unit.
units is required so that only one unit remains in Isoch mode and all
required so that if one of the parallel running unit trips on fault, some non-priority feeders can be segregated automatically & quickly to prevent under frequency trip of the healthy unit. (If the 20 MW unit trips then more load to be segregate corresponding to tripping of any one of 14.45 MW units).
Option 2: Practicable Solution: Eliminating Circulating Zero Sequence Current Using Neutral Switching Breakers B/C 1 B/C 2 Unit 1 Inter. Unit 2 Inter. Unit 2 Gen. Unit 1 Gen. Bus A Bus B Bus C
ON ON ON ON ON ON
11 KV Gen. Bkr Gen. Bkr GT Unit 1 GT Unit 2 NGR Unit 1 NGR Unit 2
No Circulating Zero Sequence Current ON OFF
New GT- Old GT Inter Connection 1- 3 B/C 1 B/C 2 Unit 1 Inter. Unit 2 Inter. Unit 2 Gen. Unit 1 Gen.
Unit 3
N B/C 1
Bus A Bus B Bus C
New Bus 3
Tie 3 Bkr Tie 1 Bkr Tie 4 Bkr Tie 2 Bkr 11 KV 11 KV
Duliajan Power Station Switchgear Arrangement with Three Units
New Bus 1 N B/C 2 New Bus 2
Gen. Bkr Gen. Bkr GT Unit 1 GT Unit 2 NGR Unit 1
URT, 31.5 MVA 11/ 11.5 KV
GT Unit 3 NGTr. Unit 3 High Imp Grnd. NGR URT 3 NGR Bkr 1 NGR Bkr 2 NGR Bkr 3 NGR Unit 2
Path of Zero Sequence Currents with Any Combination of two units or Three Units Running Parallel
B/C 1 B/C 2 Unit 1 Inter. Unit 2 Inter. Unit 2 Gen. Unit 1 Gen.
Unit 3
N B/C 2
Bus A Bus B Bus C
NBus 2 NBus 3
Tie 3 Bkr Tie 1 Bkr Tie 4 Bkr Tie 2 Bkr
ON ON ON ON ON ON ON ON ON ON ON ON
11 KV 11 KV
ON NBus 1 N B/C 1
Path 1 Path 3 Gen. Bkr Gen. Bkr GT Unit 1 GT Unit 2 NGR Unit 1 URT Unit 3 GT Unit 3 NGTr. Unit 3 High Imp Grnd. NGR URT 3 Path 2
ON
NGR Unit 2
Operation with Unit #3 Running Alone
B/C 1 B/C 2 Unit 1 Inter. Unit 2 Inter. Unit 2 Gen. Unit 1 Gen.
Unit 3
N B/C 2
Bus A Bus B Bus C
NBus 2 NBus 3
Tie 3 Bkr Tie 1 Bkr Tie 4 Bkr Tie 2 Bkr New GT- Old GT Inter Connection 1-3
ON ON ON ON ON ON ON ON ON ON
11 KV 11 KV
ON NBus 1 N B/C 1
OFF OFF
Gen. Bkr Gen. Bkr NGR Unit 1 NGR Unit 2 URT Unit 3 GT Unit 3 NGTr. Unit 3 High Imp Grnd. NGR URT 3
ON
NGR Bkr 1 NGR Bkr 2 Unit 2 Not Running Unit 1 Not Running
ON ON
Operation with Unit #3 & Unit #1 Running In Parallel and Unit #3 is Selected as Master
B/C 1 B/C 2 Unit 1 Inter. Unit 2 Inter. Unit 2 Unit 1
Unit 3
N B/C 2
Bus A Bus B Bus C
NBus 2 NBus 3
Tie 3 Bkr Tie 1 Bkr Tie 4 Bkr Tie 2 Bkr
ON ON ON ON ON ON ON ON ON ON
11 KV 11 KV
ON NBus 1 N B/C 1
OFF
ON
Unit 2 Gen. Bkr Unit 1 Gen. Bkr
NGR Unit 1 NGR Unit 2 URT Unit 3 GT Unit 3 NGTr. Unit 3 High Imp Grnd. NGR URT 3
ON
NGR Bkr 1 NGR Bkr 2 Unit 2 Not Running Unit 1 Running
ON
OFF
ON
OFF
Operation with Unit #3 & Unit #1 Running In Parallel and Unit #1 is Selected as Master B/C 1 B/C 2 Unit 1 Inter. Unit 2 Inter. Unit 2 Unit 1
Unit 3
N B/C 2
Bus A Bus B Bus C
NBus 2 NBus 3
Tie 3 Bkr Tie 1 Bkr Tie 4 Bkr Tie 2 Bkr
ON ON ON ON ON ON ON ON ON ON
11 KV 11 KV
ON NBus 1 N B/C 1
OFF
ON
Unit 2 Gen. Bkr Unit 1 Gen. Bkr
NGR Unit 1 NGR Unit 2 URT Unit 3 GT Unit 3 NGTr. Unit 3 High Imp Grnd. NGR URT 3 NGR Bkr 1 NGR Bkr 2 Unit 2 Not Running Unit 1 Running
ON
OFF
ON ON
OFF