cashflow
play

Cashflow from the client and of delays is illustrated in the next - PDF document

The significance to the contractors cashflow of different patterns of payment Cashflow from the client and of delays is illustrated in the next figure showing a hypothetical contract of 2 years duration . 3.0 2.8 Total price 2.6


  1. • The significance to the contractor’s cashflow of different patterns of payment Cashflow from the client and of delays is illustrated in the next figure showing a hypothetical contract of 2 years’ duration . 3.0 2.8 Total price 2.6 • The predicted revenue (2) assumes monthly payments 2.4 Total cost for work completed and a 4-week delay between 2.2 certification and payment by client . The shaded area 2.0 Contract completion between the curves represents the funding to be 1.8 ) provided by the contractor. This would be considerably 1 1.6 ( t s o c reduced if the client agreed to a 10 % advance 1.4 d e t a 1.2 m mobilization payment (3), or increased if payments were i t s Predicted E 1.0 revenue (2) received late (4) as illustrated in the following figure. 0.8 0.6 0.4 0.2 0.0 0 20 40 60 80 100 120 140 Contract duration (weeks) 3.0 3.0 2.8 2.8 Total price Total price 2.6 2.6 2.4 2.4 Total cost Total cost 2.2 2.2 2.0 2.0 Contract completion Contract completion 1.8 1.8 ) ) 1.6 1 1.6 1 ( ( t t Revenue s s o o 1.4 c 1.4 c payment delayed d d e e t t a a 1.2 1.2 m m i i t t s Predicted s Predicted E E 1.0 1.0 revenue (2) revenue (2) 0.8 0.8 0.6 0.6 0.4 0.4 Revenue with Revenue with 0.2 0.2 mobilization fee (3) mobilization fee (3) 0.0 0.0 0 20 40 60 80 100 120 140 0 20 40 60 80 100 120 140 Contract duration (weeks) Contract duration (weeks) 1

  2. 3.0 2.8 Total price 2.6 • The effect of delay in completion is serious Predicted 2.4 revenue (2) Total cost as cost increases and payment for 2.2 2.0 Contract completion completed work is delayed. 1.8 Delay ) 1.6 1 ( t s o 1.4 c d e a t 1.2 m • If the delay is caused by factors outside t i s E 1.0 the contractor’s control, an extension of 0.8 0.6 time may be granted. 0.4 Delayed revenue 0.2 payment (6) 0.0 0 20 40 60 80 100 120 140 Contract duration (weeks) Programming techniques • The best form of plan for site use is the bar chart. • Each activity is shown in its schedule Cost Estimating position which results in efficient use of resources. • Estimates of cost and time are prepared and revised at many stages throughout the development of a project or contract. • There is inter-relationship of activities and movement of resource teams • The accuracy of successive estimates should improve as the project or contract develops. • Important constraints and key dates are marked to ensure that these are clearly communicated to all concerned with the project 2

  3. Cost Estimating Cost Estimating The requirements of an estimate are: These predictions will be influenced by factors specific for the project: • To predict the most probable cost of the works and also to define the range within which – location the final cost is likely to lie. – weather – availability and capacity of resources • To produce a forecast of expenditure: the cashflow based on the project programme . Cost Estimating techniques Cost Estimating techniques Additional work in a contract can be assessed and Additional work in a contract can be assessed and evaluated based on: evaluated based on: 1. Manhours: 2. Unit rates This is suitable for labour intensive construction For additional work, the unit rates in the bills of where reliable records of hourly productivity of different quantities is used. If unit rates for a similar work trades is available. The total manhours estimated for a does not exist in the bills of quantities, then given operation are then costed at the current labour rates and added to the costs of materials and equipment. Manhours are used. 1. Where a Contractor submits a programme which is approved or accepted by the • However, there are some contracts that do not permit the contractor to amend its architect/engineer, is he obliged to follow it or programme once accepted without approval . can he amend it at his own discretion (judgment)? • If a contract does not require approval by the engineer for a programme to be revised, the contractor can revise his programme as he • The programme is usually intended to be a wishes. flexible document. If the contractor gets behind (maybe due to delays by a subcontractor), he would normally expect to revise the programme • An architect/engineer who has not been asked to approve or accept an amended programme in an attempt to make up lost time. For this may feel under no obligation to issue drawings reason, programmes are rarely listed as in good time to enable the contractor to comply contract documents. with the revised programme. 3

  4. • The situation with subcontractors is similar to that of 2. Is a subcontractor obliged to follow a main a main contractor. contractor’s programme? • A court case between Pigott Foundations v. Shepherd Construction: Pigott was employed as a subcontractor to design and construct bored piling on a new fourteen storey office • Most standard forms of contract provide for the block. Shepherd Construction was the main contractor. contractor to produce a programme. A failure to do so, is a breach of contract. It is unusual however, for a programme to be classified as a contract document . If it were so, then contractors would be required to carry out work strictly in accordance with the programme. This could in many cases prove impossible. Pigott’s subcontract provided 8 weeks work. The work The court decision in this case, was that the started on 26 th June 1989. However, the majority of the subcontractor was not required to comply with the works were completed by 20 th October 1989. Pigott then main contractor’s programme. left the site and returned in April 1990 to complete the remaining 9 piles. The work continued slowly and If there exists an obligation for a subcontractor to carry out difficulties arose due to piling work which was alleged to work to suit a main contractor’s programme, it also be defective. It was not clear whether this was due to requires an obligation upon the main contractor to faulty design or bad workmanship and Pigott claimed provide access to enable the subcontractor to carry out that the difficulties arose as a result of ground conditions. the work in accordance to the main contractor’s A solution to the problem was reached which involved programme. installing additional piles. A subcontractor is not required to follow a main contractor’s programme unless provided in the terms of the subcontract. Equally, the main contractor is not obliged to grant access to enable the subcontractor to do so. 3. Who owns float time in the contractor’s programme, the architect/engineer or the contractor? • Most sensible/careful contractors, will allow some form of • Float time was the issue in a court case in 1999 contigency in their programme to accommodate for bad between Ascon Contracting Ltd v Alfred McAlpine ground, strikes, weather conditions, shortages of labour Construction . McAlpine was the main contractor and and materials etc. Ascon was the subcontractor for constructing the reinforced concrete floor slabs, basement walls and upright columns between floors. • If the contractor has clearly programmed an activity to take longer than is estimated to complete, can the employer take advantage of the float time? This • The subcontract period was 29 weeks commencing on 28 th August 1996 and completing works on 5 th March might be useful if the engineer is late issuing drawings or delays have been caused by the 1997. Completion of the subcontract was not achieved until 9 th May 1997, nine weeks late . employer . 4

  5. • No extension of time was granted . • Part of Mc Alpine’s case against Ascon was that if all subcontractors started and finished on time and Mc Alpine executed their work on time, completion of • Ascon submitted a claim for extension of time and works would have been 5 weeks early. payment of 337,918.00(UK pounds). • McAlpine’s agrument was that the 5 weeks float time • McAlpine counterclaimed 175,000.00(UK pounds) was for their benefit to absorb their own delays. liquidated damages paid to the employer plus its own Because these 5 weeks were used by Ascon, loss and expense. McAlpine claimed they were entitled to recover their lost benefit. • A dispute between Mc Alpine and the employer had been compromised by a final payment of 9,475.00 (uk • The judge rejected this argument. McAlpine could pounds) and no deduction was made for liquated not claim against the subcontractors. If float time is damages. available, it can be used on a first come first served basis. 5

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend