Cargill
North Vancouver Grain Terminal Power System Upgrade
Cargill North Vancouver Grain Terminal Power System Upgrade Project - - PowerPoint PPT Presentation
Cargill North Vancouver Grain Terminal Power System Upgrade Project Overview Construction of new 69kV/12.47kV indoor substation c/w environmental safeguards Construction of one new electrical room and modifications to three existing
North Vancouver Grain Terminal Power System Upgrade
Slide 2 of 10
▪ Construction of new 69kV/12.47kV indoor substation c/w environmental safeguards ▪ Construction of one new electrical room and modifications to three existing electrical rooms in the existing plant to house 12.47kV/600V Unit Substations ▪ New cable feed to Ship Loader ▪ New cable feeds to plant’s existing Motor Control Centres (MCC) from new Unit Substations ▪ Demolition of existing 69kV switchyard
LEX ENGINEERING LTD. JANUARY 2017
Slide 3 of 10
Ship Dock Neptune Bulk Terminals Unit Sub 2 Unit Sub 1 Existing Switchyard Unit Sub 3/4 Substation
LEX ENGINEERING LTD. JANUARY 2017
69kV Tap
Slide 4 of 10
Covered Power Transformers Incoming 69kV Pole Building to house indoor 69kV Gas-Insulated Switchgear & 12.47kV Arc-Resistant Switchgear
LEX ENGINEERING LTD. JANUARY 2017
Slide 5 of 10
LEX ENGINEERING LTD. JANUARY 2017
Slide 6 of 10
Substation Construction Unit Substation Construction Existing Substation Demolition
(tentative)
MCC Cable Installation Engineering
LEX ENGINEERING LTD. JANUARY 2017
Benefits of Proposed Project
▪ Safe working environment for High Voltage
▪ Substation building structure designed to meet current seismic and building code guidelines ▪ Modern equipment designed to be more environmentally conscious (e.g. PCB-free vegetable-oil-insulated power transformers) ▪ Improved efficiency due to reduced electrical losses
Potential Impacts of Project
▪ Virtually no impacts on everyday life of the surrounding residential and industrial community
LEX ENGINEERING LTD. JANUARY 2017 7
Slide 8 of 10
▪ Additional noise due to construction activities such as soil densification, concrete formwork and steel erection – during normal working hours ▪ Traffic will increase as equipment, concrete and building supplies are trucked in and later as rubble from the demolition is removed
LEX ENGINEERING LTD. JANUARY 2017
Slide 9 of 10
▪ Construction Environmental Management Plan:
▪ Site environmental inspections ▪ Construction waste management plan ▪ Environmental incident reporting ▪ Spill response plan ▪ Procedures to store, transfer and dispose of hazardous waste
▪ Soil Management Plan:
▪ Soil testing and monitoring ▪ Isolation and removal of contaminated soil
▪ Hazardous Materials Assessments for Demolition Works
LEX ENGINEERING LTD. JANUARY 2017
Darrell Mauthe, P.Eng Darrell_Mauthe@cargill.com
LEX ENGINEERING LTD. JANUARY 2017 10