Canada/US Separation Event Tim Reynolds W E C C E S T E R - - PowerPoint PPT Presentation

canada us separation event
SMART_READER_LITE
LIVE PREVIEW

Canada/US Separation Event Tim Reynolds W E C C E S T E R - - PowerPoint PPT Presentation

Canada/US Separation Event Tim Reynolds W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L 2 Presentation Outline Event Overview Existing Conditions Effects of the


slide-1
SLIDE 1

Canada/US Separation Event

W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

Tim Reynolds

slide-2
SLIDE 2

Presentation Outline

  • Event Overview
  • Existing Conditions
  • Effects of the Fault/Separation
  • Lessons Learned

2 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

slide-3
SLIDE 3

Event Overview

  • The Western Interconnection separated

between Canada and the US on 10/16/2017 and 10/26/2017

  • Last occurrence around 20 years ago

3 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

slide-4
SLIDE 4

Path Overview

4 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

slide-5
SLIDE 5

Impacted Paths - Bubble Map

5 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

Path 3 Path 83

5L51 5L52 2L277/71L 2L112

BPA BCHA Boundary - BDY (BPA) Nelway - NLY (BCHA) Custer - CUS (BPA) Ingledow - ING (BCHA)

Haylake (NWMT) MATL (AESO) Rimrock (WWA)

Montana Alberta Tie - MATL

NWMT AESO

slide-6
SLIDE 6

Existing Conditions

6 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

Path 3

5L51 5L52 2L277/71L 2L112

BPA BCHA Boundary - BDY (BPA) Nelway - NLY (BCHA) Custer - CUS (BPA) Ingledow - ING (BCHA)

  • 5L51 was out of service

– Maintenance scheduled between Oct 16-27, 2017

  • Path Flows

– 10/16 flow was ~1,400 MW from BCHA to BPA – 10/26 flow was ~530 MW from BCHA to BPA

slide-7
SLIDE 7

Existing Conditions

7 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

Path 83

Haylake (NWMT) MATL (AESO) Rimrock (WWA)

Montana Alberta Tie - MATL

NWMT AESO

  • In-service
  • Path flows

– 10/16 flow was ~120 MW into AESO – 10/26 flow was ~145 MW into NWMT

slide-8
SLIDE 8

5L51 5L52 2L277/71L 2L112

BPA BCHA Boundary - BDY (BPA) Nelway - NLY (BCHA) Custer - CUS (BPA) Ingledow - ING (BCHA)

The Fault

8 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

Path 3

  • Fault Occurred on 5L52

– 10/16/2017, 1545 PDT – 10/26/2017, 0817 PDT

  • Both events were single pole to ground faults
  • Cause likely due to insulator contamination
  • Triggered RAS and trips 2L112
  • Path 3 now open
slide-9
SLIDE 9

The Fault (cont.)

9 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

  • MATL RAS Action

– Path 83 open

  • Western Interconnection

separated into Northern and Southern islands

Path 83

Haylake (NWMT) MATL (AESO) Rimrock (WWA)

Montana Alberta Tie - MATL

NWMT AESO

slide-10
SLIDE 10

After the Fault (10/16)

  • Frequency Deviation (10/16)

– Northern Island 60.32 Hz – Southern Island 59.84 Hz

  • 1552 PT

– Still inadequate generation in southern island. – Peak RC sends RMT stating for all entities to bring generation up as necessary and align schedules to stabilize system frequency.

  • 1610 PT

– Ingeldow-Custer (5L52) put in-service – BCHA re-synced with BPA – Path 83 then restored

10 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

slide-11
SLIDE 11

After the Fault (10/26)

  • Frequency Deviation (10/26)

– Northern Island 60.30 Hz – Southern Island 59.90 Hz

  • 0841 PT

– Ingeldow-Custer (5L52) put in- service – BCHA re-synced with BPA – Path 83 then restored

11 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

slide-12
SLIDE 12

Lessons Learned

  • Suppressed Frequency Response

– Better coordination/procedures

  • Additional tools/alarms to help operators

recognize islanding

  • Adding single pole tripping
  • Scenario is being added to future training

schedules

12 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

slide-13
SLIDE 13

Lessons Learned: Suppressed Response

13 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

  • 1500
  • 1000
  • 500

500 1000 16:38 16:43 16:48 16:53 16:58 17:03 17:08 ACE (MW) Time (MST)

10/ 16/ 2017

WI ACE Northern Island ACE Southern Island ACE

  • 1500
  • 1000
  • 500

500 1000 09:12 09:17 09:22 09:27 09:32 09:37 09:42 ACE (MW) Time (MST)

10/ 26/ 2017

slide-14
SLIDE 14

Lessons Learned: Additional Tools

14 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L