canada us separation event
play

Canada/US Separation Event Tim Reynolds W E C C E S T E R - PowerPoint PPT Presentation

Canada/US Separation Event Tim Reynolds W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L 2 Presentation Outline Event Overview Existing Conditions Effects of the


  1. Canada/US Separation Event Tim Reynolds W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  2. 2 Presentation Outline • Event Overview • Existing Conditions • Effects of the Fault/Separation • Lessons Learned W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  3. 3 Event Overview • The Western Interconnection separated between Canada and the US on 10/16/2017 and 10/26/2017 • Last occurrence around 20 years ago W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  4. 4 Path Overview W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  5. 5 Impacted Paths - Bubble Map Path 3 Path 83 MATL Ingledow - ING Nelway - NLY (AESO) (BCHA) (BCHA) Montana Alberta Tie - MATL 2L277/71L 2L112 5L51 5L52 AESO NWMT BCHA BPA Haylake Rimrock (NWMT) (WWA) Boundary - Custer - CUS BDY (BPA) (BPA) W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  6. 6 Existing Conditions Path 3 • 5L51 was out of service – Maintenance scheduled between Oct Ingledow - ING Nelway - NLY (BCHA) (BCHA) 16-27, 2017 • Path Flows 2L277/71L 2L112 5L51 5L52 – 10/16 flow was ~1,400 MW from BCHA to BPA BCHA – 10/26 flow was ~530 MW from BCHA to BPA BPA Boundary - Custer - CUS BDY (BPA) (BPA) W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  7. 7 Existing Conditions Path 83 • In-service MATL • Path flows (AESO) – 10/16 flow was ~120 MW into Montana Alberta Tie - MATL AESO AESO – 10/26 flow was ~145 MW into NWMT NWMT Haylake Rimrock (NWMT) (WWA) W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  8. 8 The Fault Path 3 Fault Occurred on 5L52 • 10/16/2017, 1545 PDT – 10/26/2017, 0817 PDT – Ingledow - ING Nelway - NLY (BCHA) (BCHA) Both events were single pole to ground faults • 2L277/71L Cause likely due to insulator contamination • 2L112 5L51 5L52 Triggered RAS and trips 2L112 • BCHA BPA Path 3 now open • Boundary - Custer - CUS BDY (BPA) (BPA) W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  9. 9 The Fault (cont.) Path 83 • MATL RAS Action MATL – Path 83 open (AESO) Montana Alberta Tie - MATL • Western Interconnection AESO separated into Northern and NWMT Southern islands Haylake Rimrock (NWMT) (WWA) W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  10. 10 After the Fault (10/16) Frequency Deviation (10/16) • – Northern Island 60.32 Hz – Southern Island 59.84 Hz • 1552 PT – Still inadequate generation in southern island. – Peak RC sends RMT stating for all entities to bring generation up as necessary and align schedules to stabilize system frequency. 1610 PT • – Ingeldow-Custer (5L52) put in-service – BCHA re-synced with BPA – Path 83 then restored W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  11. 11 After the Fault (10/26) Frequency Deviation (10/26) • – Northern Island 60.30 Hz – Southern Island 59.90 Hz • 0841 PT – Ingeldow-Custer (5L52) put in- service – BCHA re-synced with BPA – Path 83 then restored W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  12. 12 Lessons Learned • Suppressed Frequency Response – Better coordination/procedures • Additional tools/alarms to help operators recognize islanding • Adding single pole tripping • Scenario is being added to future training schedules W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  13. 13 Lessons Learned: Suppressed Response 10/ 16/ 2017 10/ 26/ 2017 1000 1000 500 500 0 0 ACE (MW) ACE (MW) -500 -500 -1000 -1000 -1500 -1500 16:38 16:43 16:48 16:53 16:58 17:03 17:08 09:12 09:17 09:22 09:27 09:32 09:37 09:42 Time (MST) Time (MST) Southern Northern WI ACE Island ACE Island ACE W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

  14. 14 Lessons Learned: Additional Tools W E C C E S T E R N L E C T R I C I T Y O O R D I N A T I N G O U N C I L

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend