DIgSILENT Pacific
Power system engineering and software
Two hot topics
System strength and the 5.3.9 process Jennifer Crisp DIgSILENT Pacific February 2020
c i f i c a DIgSILENT Pacific P Power system engineering and - - PowerPoint PPT Presentation
c i f i c a DIgSILENT Pacific P Power system engineering and software T N Two hot topics System strength and the 5.3.9 process E Jennifer Crisp L DIgSILENT Pacific February 2020 I S g I D c i f i c a System strength
Power system engineering and software
System strength and the 5.3.9 process Jennifer Crisp DIgSILENT Pacific February 2020
2
7
Synchronous generators contribute 3 x fault level of same sized inverter-based generators Fault level also varies by
8
Minimum System Strength Generators pay NSPs pay
9
Minimum System Strength Generators pay NSPs pay
must mitigate their adverse system strength impact
arrangement Minimum system strength bar becomes the baseline for studies
10
10.0 8.00 6.00 4.00 2.00 0.00 [s] 1.09 1.07 1.05 1.03 1.01 0.99 [p.u.]
POC: Strong Grid, SCR = 10, connection point voltage POC: Medium Grid, SCR = 5, connection point voltage POC: Weak Grid, SCR = 3, connection point voltage 0.936 s 1.045 p.u. Y = 1.045 p.u. X = 0.500 s 1.988 s 1.045 p.u. 3.496 s 1.045 p.u.
10.0 8.00 6.00 4.00 2.00 0.00 [s] 0.60 0.40 0.20 0.00
Reactive Power: Strong Grid, SCR = 10, reactive power in pu Reactive Power: Medium Grid, SCR = 5, reactive power in pu Reactive Power: Weak Grid, SCR = 3, reactive power in pu
Less reactive power power required as fault level decreases for same voltage change Slower response as fault level Increases Less stable as fault level decreases
11
Damping is lower as fault level reduces
13
4 Hz oscillation on a wind farm 7 Hz oscillation on a solar farm
Source: Lingling Fan SETO Modelling conference 2019, USF
unstable if fault level reduces for a network outage
existing plant, and new plant are at risk
14
September 2019
in 2018 ($10.7 billion)
being MLFs and congestion)
15
plant (first step)
models
16
work for Victoria’s West Murray region
shortfall
17
18
19
connected generating plant
previously accepted
technical requirements of S5.2.5, S5.2.6, S5.2.7, S5.2.8 or
use of network by another Network User
20
Plan, Design & construct Commission Operate compliantly Upgrade Decom- mission
strength impact assessment for each proposed alteration to a generating system to which clause 5.3.9 applies (5.3.4B)
generator’s cost or
scheme or
21
response to disturbances, voltage/reactive control systems)
technical standards
requirement that is affected by the alteration to the generating system
22
requirements)
23
measurement with PSS/e models
slower/more onerous (NSP dependent)
24
25
26
performance of plant less than current minimum standard
in previous rules
farms for not riding through multiple faults in 2016 SA blackout
difficult for old plant – requires mechanical design to be assessed
27
“On 6 August 2019 the AER commenced proceedings against four wind farm
and Tilt Renewables) concerning the Black System Event in South Australia on 28 September 2016…. The AER is alleging that certain wind turbine generators ceased supplying power in response to voltage disturbances that occurred on 28 September 2016. By not maintaining continuous uninterrupted operation to ride-through low voltage disturbances, as required by their Generator Performance Standards, we allege the generating units at the wind farms contravened the National Electricity
pecuniary penalties and costs.”
Source AER
changed since GPSs were first written, where performance requirement was in previous GPS.
requirement for continuous uninterrupted operation in range 0.8 pu to 1.1 pu for 10 seconds was NOT interpreted previously to mean generator had to operate at 0.8 pu for 10 seconds.
28
29
NSP devices
performance standards/compliance)
In line with this:
fault level and frequency behaviour of the power system changes over time
30
accepted, where its impact is not materially detrimental to:
31
32
Power system engineering and software