IH-35W Business Owner Task Force Meeting December 11, 2013 Fossil Creek 11 6100 North Freeway Fort Worth, TX 76137 2 Meeting Agenda Safety Minute Construction Look Ahead IH -35W north of IH-820 IH-35W south of IH-820


slide-1
SLIDE 1

IH-35W Business Owner Task Force Meeting

December 11, 2013 Fossil Creek 11 6100 North Freeway Fort Worth, TX 76137

slide-2
SLIDE 2

Meeting Agenda

  • Safety Minute
  • Construction Look Ahead

▫ IH -35W north of IH-820 ▫ IH-35W south of IH-820 ▫ IH-820 ▫ SH 183/SH 121

  • Questions
  • Adjourn

2

slide-3
SLIDE 3
slide-4
SLIDE 4

Safety Minute: Winter Driving

  • Reduce speed. Speed limits are

based on normal road and weather conditions, not winter road conditions

  • Maintain at least three times the

normal following distance on snow

  • r ice
  • Watch carefully for snow removal

equipment and stay at least 200 feet back if you are behind a snow plow

  • Use extra caution on bridges,

ramps, overpasses and shaded areas as they tend to freeze first

  • If you start to slide, ease off the gas

pedal or brakes. Steer into the direction of the skid until you feel you have regained traction then straighten your vehicle

  • Check highway conditions at

DriveTexas.

4

slide-5
SLIDE 5

North Tarrant Express Facility Map

5

slide-6
SLIDE 6

IH-35W North of IH-820

6

slide-7
SLIDE 7

Quick Facts

  • Length: 3.6 miles
  • Cross-section
  • Expected Completion: 2016

7

Existing (each direction) Phase 1 (each direction) Main Lanes 2 2 Frontage Road 2 2 Managed Lanes (toll) None 2

 Discontinuous

slide-8
SLIDE 8

South of Western Center Blvd

8 April 2013 October 2013

slide-9
SLIDE 9

South of Western Center Blvd

9 December 2013: Southbound pavement and ditch. December 2013: Underground drainage pipe installed and parking lot removed to new right-of-way.

slide-10
SLIDE 10

Western Center Blvd

10 April 2013 October 2013

slide-11
SLIDE 11

Western Center Blvd

11 December 2013: Southbound frontage road

  • Beginning underground drainage

December 2013: Northbound frontage road

  • Trees removed
  • Continuing franchise and

city utility relocation

  • Upcoming frontage road

construction

slide-12
SLIDE 12

Western Center Blvd

12 December 2013: Bridge drill shafts.

slide-13
SLIDE 13

Western Center Construction Phasing

13 Phase 2 Step 1 Phase 2 Step 1B Phase 2 Step 1C

slide-14
SLIDE 14

Western Center Construction Phasing

14 Phase 2 Step 2 Phase 2 Step 2B Phase 2 Step 3

slide-15
SLIDE 15

Basswood Blvd

15 April 2013 October 2013

slide-16
SLIDE 16

Basswood Blvd

16 November 2013: U-turn bridge decks poured & preparing for bridge rails. December 2013: Southbound managed lane entrance.

slide-17
SLIDE 17

Basswood Blvd

17 November 2013: Looking south from Basswood Blvd at wall construction, future southbound lanes, and managed lane entrance. November 2013: Looking north from Basswood Blvd at future southbound lanes being constructed.

slide-18
SLIDE 18

IH-35W/US 287 Interchange

18 April 2013 October 2013

slide-19
SLIDE 19

IH-35W/US 287 Interchange

19 November 2013: Hanging beams for new northbound connection to US 287. November 2013: Structure construction for new northbound Connection to US 287.

slide-20
SLIDE 20

IH-35W/US 287 Interchange

20 December 2013: Curb and gutter for new southbound frontage road north of Basswood Blvd. December 2013: New ramp from southbound I-35W to northbound US 287. December 2013: New northbound I-35W main lanes south of North Tarrant Pkwy.

slide-21
SLIDE 21

IH-35W South of IH-820

21

slide-22
SLIDE 22

Quick Facts

  • Length: 6.5 miles
  • Cross-section
  • Expected Completion: 2018

22

Existing (each direction) Phase 1 (each direction) Main Lanes 2 – 3 2 – 3 Frontage Road 2 2 Managed Lanes (toll) None 2

 Discontinuous

slide-23
SLIDE 23
slide-24
SLIDE 24

Project Timeline

24

Financial Close Achieved September 2013 Design Optimization / Right of Way Acquisition Construction Starts 2014 Completed 2018

slide-25
SLIDE 25

Primary Contacts

  • Robert Hinkle

NTE Mobility Partners, LLC (817) 710-0511

  • Scott Hall, P.E.

TxDOT (817) 341-9254

25

slide-26
SLIDE 26

IH-820

26

slide-27
SLIDE 27

Quick Facts

  • Length: 6.4 miles
  • Cross-section
  • Expected Completion: 2015

27

Existing (each direction) Phase 1 (each direction) Main Lanes 2 2 Frontage Road 2 2 Managed Lanes (toll) None 2

 Discontinuous

slide-28
SLIDE 28

Project Impact

www.northtarrantexpress.com 1-888-NTE-2015 Companies that have worked directly on the project:

142

People working in the corridor:

2,354

Amount of excavation moved

3.91M CY

Amount of pavement laid

0.36M CY

Constr nstruc ucti tion

  • n Compl

plete

74%

slide-29
SLIDE 29

No lane closures during these times

Sunday, Dec 22 at 12 p.m.-10 p.m. Friday, Dec 27

Sunday, Dec 29 at 12 p.m.-10 p.m. Thursday, Jan 2

Blackout Periods

slide-30
SLIDE 30

Upcoming: Riverside Drive

Construction Activities: Continued construction of the bridge approaches from the north and south sides of the Riverside bridge Traffic Impacts: Currently anticipate reopening the bridge end of February 2014 www.northtarrantexpress.com 1-888-NTE-2015

slide-31
SLIDE 31

Upcoming: Haltom Road

Construction Activities: Continued expansion of Haltom Rd.

  • ver IH 820

Traffic Impacts: Currently anticipate all lanes northbound and southbound to be

  • pen early 2014

www.northtarrantexpress.com 1-888-NTE-2015

slide-32
SLIDE 32

Upcoming: Denton Hwy 377

Construction Activities: Continued expansion of Denton Hwy.

  • ver IH 820

Traffic Impacts: All lanes, including east to west u-turn, open first quarter 2014 www.northtarrantexpress.com 1-888-NTE-2015

slide-33
SLIDE 33

Upcoming: Iron Horse Blvd

Construction Activities: Continued expansion of Iron Horse

  • Blvd. over IH 820

Traffic Impacts: Open off-ramp from westbound IH 820 January 2014 www.northtarrantexpress.com 1-888-NTE-2015

slide-34
SLIDE 34

SH 183/SH 121

34

slide-35
SLIDE 35

Quick Facts

  • Length: 6.9 miles
  • Cross-section
  • Expected Completion: 2015

35

Existing (each direction) Phase 1 (each direction) Main Lanes 3 3 Frontage Road 2 2 Managed Lanes (toll) None 2

 Discontinuous

slide-36
SLIDE 36

Upcoming: Precinct Line

Construction Activities: Continued expansion SH 121/183

  • ver Precinct Line Rd.

Traffic Impacts: Alternating lanes of northbound and southbound Precinct Line Rd. at SH 121/183 www.northtarrantexpress.com 1-888-NTE-2015

slide-37
SLIDE 37

Upcoming: Brown Trail

Construction Activities: Continued expansion of Brown Trail

  • ver SH 121/183

Traffic Impacts: All lanes anticipated to be open first quarter 2014 www.northtarrantexpress.com 1-888-NTE-2015

slide-38
SLIDE 38

Information rmation Hotl

  • tline

ine 1-888 888-NTE TE-20 2015 Information rmation Center 8713 Airpo rport t Freeway, , Suite 100 North Richland land Hills, s, Texas 76180 180 Project ct Website www.N .NorthT thTarr arrant antExp xpress ress.co .com Fan us on Facebook

  • k

Follow w us @NTExpress ress

Keeping You Informed

www.northtarrantexpress.com 1-888-NTE-2015

slide-39
SLIDE 39

Public Information

  • Public Outreach

▫ Mobility Coordinator: Jason Crawford, P.E.

▫ jcrawford@tamu.edu ▫ (817) 462-0534

  • Lane Closures

▫ Coordination with NTE Mobility Partners

▫ northtarrantexpress.com ▫ E-alerts ▫ Hotline: 1-888-NTE-2015

39