business briefing
play

Business Briefing Peter Flower Director:Water & Sanitation - PowerPoint PPT Presentation

The Current Water Supply Situation Business Briefing Peter Flower Director:Water & Sanitation Department 9 May 2017 Presentation Outline 1. Overview of Bulk Water supply system 2. Status of water resources and water use 3. Water demand


  1. The Current Water Supply Situation Business Briefing Peter Flower Director:Water & Sanitation Department 9 May 2017

  2. Presentation Outline 1. Overview of Bulk Water supply system 2. Status of water resources and water use 3. Water demand management 4. Assurance of Supply and Water Restrictions 5. Disaster declaration and contingency planning 6. Acceleration of water resource schemes 7. Business Sector engagement 8. Future outlook

  3. Bulk Water Infrastructure • Dams (DWA & City) 15 • Water Treatment Plants 12 – Production Capacity 1650 Ml/day – Current Capacity utilisation 45 % • Reservoirs 24 – Storage Capacity 2740 Ml – Average demand storage 3 days – Peak demand storage 2.5 days • Pipelines 655 km • Water Allocation and Demand – Allocation from System 400 Mm3 p.a. – 2014/15 Demand 345 Mm3 p.a. – 2015/16 Demand 330 Mm3 p.a. – Projected 2016/17 Demand 280 Mm3 p.a.

  4. Comparative Water Use from WCWSS (2014/2015) Agriculture: 158 Mm 3 (29%) Cape Town: Other 345 Mm 3 /a municipalities: (64%) 37 Mm 3 (7%)

  5. Estimated WCWSS Summer Water Use (1 November 2016 – 28 February 2017) Agriculture & Other COCT Municipalities 40% 45% Evaporation 15%

  6. Water Use in Cape Town (2015 / 16) Government, 2.5% CCT Departments & Other, 6.2% Council-owned premises, 5.2% Industry, 3.9% Retail & Offices, 11.0% Houses , 55.6% Informal Settlements, 70 % Residential 4.7% Flats & Domestic other, 1.8% complexes, 9.2%

  7. Dam Storage Change and WTP Production – 8 May 2017

  8. Recent Drought Events Drought Drought 75% 62% 30% 15-20%

  9. Rainfall Record

  10. Rainfall Forecasts (SAWS / GFCSA) Weather Outlook (March – May 2017) - Normal to below normal rainfall is expected over the Western-Cape for autumn and early winter. (PDMC Drought Monitoring Situation Report No.9) With the possibility of a moderate El Nino event becoming more likely in the summer of 2017/18, conservative planning is advised wherever possible (SAWS 2 May 2017)

  11. Voelvlei Dam (12 April 2017)

  12. Theewaterskloof Dam (28 April 2017)

  13. Steenbras Lower Dam (28 April 2017)

  14. Population Growth and Water Use Efficiency 700 6.0 Water Treated per year (million m 3 ) 600 5.0 Reducing per capita water consumption 500 Population (millions) 4.0 400 3.0 300 2.0 200 1.0 100 0 0.0 1950 1960 1970 1980 1990 2000 2010 2020 Water Treated Population Expon. (Population)

  15. Factors that influenced demand growth after 2000 Water business unusual Recognized need for WC and WDM Water restrictions in Water restrictions were implemented in 2000/01 and 2004/05, after periods of low winter rainfall. 2000/01 and 2004/05 The City commits to The raw water supply agreement between the City implementing WDM as and DWS was signed in 2003, for the construction of part of approval of the Berg River Scheme. One of the conditions of Berg River Scheme approval of the Scheme was that the City would implement water demand management. The City approves and The City approved its 10 year water demand implements a 10 year management strategy in 2007. A dedicated water WDM Strategy demand management section was established in the City’s water and sanitation department, responsible for implementing the strategy. Berg River Scheme The construction of the Berg River Scheme was completed completed in 2007. 15

  16. Water demand management interventions Technical interventions: Stepped tariffs • Pressure management • Treated effluent use • Water pipe replacement • Leak detection • Water management devices (WMDs) • Meter replacement • Zone metering • Building plumbing retrofit • Plumbing repairs in indigent houses • Springs investigation • Reducing response times to repair bursts and leaks • Education and awareness campaigns: Door to door community engagements • Schools interventions • Top water users engagements • 16

  17. Pressure management projects (coupled with pipe replacement) Khayelitsha pressure management project Other notable pressure management (2001) projects, with estimated savings: Mfuleni: 0.4 Mm 3 /a • Estimated Gugulethu: 2.6 Mm 3 /a • savings: Langa: 0.5 Mm 3 /a • 9 Mm 3 /a Eersteriver: 1.2 Mm 3 /a • Brentwood Park: 0.04 Mm 3 /a • Browns Farm: 0.6 Mm 3 /a • Wesbank: 0.3 Mm 3 /a • Delft: 0.6 Mm 3 /a • Grassy Park: 0.6 Mm 3 /a • Mitchells Plain pressure management Crossroads: 0.2 Mm 3 /a • project (2008) Plumstead & Retreat: 0.6 Mm 3 /a • Estimated Fisantekraal: 0.2 Mm 3 /a • savings: Marina de Gama: 0.6 Mm 3 /a • 2.4 Mm 3 /a 17

  18. Treated Effluent Re-use More than 250 users are connected • Mostly used for irrigation and industrial purposes • Golf courses – City Parks – Schools – Farmers – Refinery – Currently approximately 7% of potable water – treatment requirement is off-set by TE 18

  19. CITY OF CAPE TOWN WATER RETICULATION ASSETS 10 691.62km (03/17) Water Reticulation Pipeline 80 652 Valves 55 580 Hydrants (as at 03/17) Melbourne, Australia 652 783 (03/17) Service Connections. 19 Infrastructure Asset Management and Operations: Water Networks

  20. RETICULATION ASSET PERFORMANCE: WATER Water Mains - Relaid (m) Annual Totals 100 000 90 000 80 000 70 000 60 000 50 000 40 000 30 000 20 000 10 000 0 2007/08 2008/09 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 (as at March 2017) Repair to Burst Water Mains (No.) Note: Pressure Management 7 000 implementation was 6 000 intensified after 2010/11 5 000 4 000 3 000 2 000 1 000 0 2007/08 2008/09 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 (as at March 2017) 20 Infrastructure Asset Management and Operations: Water Networks

  21. RETICULATION WATER MAINS: PERFORMANCE Number of Bursts per Months 100 200 300 400 500 600 700 800 900 0 Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08 Oct-08 Jan-09 Apr-09 Jul-09 Oct-09 Jan-10 No. Burst Water Mains Apr-10 Jul-10 BURST WATER MAINS Oct-10 Jan-11 Apr-11 Jul-11 Oct-11 Jan-12 Water and Sanitation Department | Business Overview Apr-12 Jul-12 Oct-12 Jan-13 Burst/ 100km Apr-13 Jul-13 Oct-13 Jan-14 Apr-14 Jul-14 Oct-14 Jan-15 Apr-15 Jul-15 Oct-15 Jan-16 Apr-16 Jul-16 Oct-16 Jan-17 Apr-17 Jul-17 0 10 20 30 40 50 60 70 80 Bursts / 100km / year 21

  22. Active Leak Detection and Repair Subzone's statistics Description Highbury Highbury Park Wesbank Mfuleni Du noon Pella Totals Zone's Statistics 20.39 15.34 22.91 149.34 Length of watermains (km) 58.617 32.083 Fibre cement Fibre cement Fibre cement Fibre cement Fibre cement Fibre cement Pipeline Material 1259 943 3204 3025 16872 No. of properties 8441 located leaks statistics 413 Total No. leaks located 46 12 77 215 40 23 Dates in Months when leaks 2013 2013 2014 2014/15 2015 2015 1.8 yrs detection was done Leaks fixed except Dates in Months when leaks generally leaks Fixed Fixed leaking meters with Not fixed Not fixed Not fixed were repaired are not fixed WMD 22

  23. Water demand management interventions Technical interventions: Stepped tariffs • Pressure management • Treated effluent use • Water pipe replacement • Leak detection • Water management devices (WMDs) • Meter replacement • Zone metering • Building plumbing retrofit • Plumbing repairs in indigent houses • Springs investigation and utilization for non-potable uses • Reducing response times to repair bursts and leaks • Education and awareness campaigns: Door to door community engagements • Schools interventions • Top water users engagements • 23

  24. Billboards and print advert 24 Go to Insert > Header & Footer > Enter presentation name into footer field

  25. Social Media 25 Go to Insert > Header & Footer > Enter presentation name into footer field

  26. Promotional Material 26 Go to Insert > Header & Footer > Enter presentation name into footer field

  27. Education and Awareness Campaigns - Schools Intervention 27 Go to Insert > Header & Footer > Enter presentation name into footer field

  28. WATER AND SANITATION WEBSITE Developed and • improved W&S website (live April 2015) 58 Web pages • created Updated regularly • Branches can contact us to update information 28 Go to Insert > Header & Footer > Enter presentation name into footer field

  29. Water demand management programme 2011/12 to 2020/21: capital expenditure of R3.2b and water savings of 70 million m 3 per annum 29

  30. Cape Town Scoops C40 Cities Award at COP21 Conference in Paris

  31. Population Growth and Water Use Efficiency 700 6.0 Water Treated per year (million m 3 ) 600 5.0 Reducing per capita water consumption 500 Population (millions) 4.0 400 3.0 300 2.0 200 1.0 100 0 0.0 1950 1960 1970 1980 1990 2000 2010 2020 Water Treated Population Expon. (Population)

  32. Water Allocations and Actual Demand Proposed COCT Augmentation Schemes Accelerated Programme (Additional 15 Mm3) Allocation from Berg River Dam (84 Mm3) Fully Financed by COCT 20 % Saving 280- 260 Mm3 Combined allocations from Voelvlei, Wemmershoek, Theewaterskloof and Steenbras Dams plus Palmiet Transfer (320 Mm3)

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend