Building the Future Todays Presentation Design-Build Team hired to - - PowerPoint PPT Presentation

building the future today s presentation
SMART_READER_LITE
LIVE PREVIEW

Building the Future Todays Presentation Design-Build Team hired to - - PowerPoint PPT Presentation

Building the Future Todays Presentation Design-Build Team hired to construct Business 40 Timeline to complete project Schedule for Construction Segments A-D Other off-site improvements Bridge designs Transportation


slide-1
SLIDE 1

Building the Future

slide-2
SLIDE 2
  • Design-Build Team hired to construct Business 40
  • Timeline to complete project
  • Schedule for Construction Segments A-D
  • Other off-site improvements
  • Bridge designs
  • Transportation Management Plan
  • Incident Management
  • Other mobility options
  • Communication and contact information

Building the Future

Today’s Presentation

slide-3
SLIDE 3

Building the Future

Business 40 Visualization

Visualization

slide-4
SLIDE 4

Building the Future Flatiron Constructors, Inc./Blythe Development Company Joint Venture and HDR Engineering Inc.

  • Rebuild the 1.2-mile section of Business 40, which includes

reconstruction of the roadway, 9 vehicular bridges and 2 pedestrian bridges.

  • Build a major section of the Multi-Use Path from Peters

Creek Parkway to Liberty Street (remaining section from Peters Creek to Lockland will be built afterwards)

  • Increase speed limit to 55mph.

Design-Build Team Hired

slide-5
SLIDE 5

Timeline

Project Completed Late 2020

9

NCDOT hires Design-Build Team of Flatiron/Blythe/HDR Preliminary Soil Testing Construction Segment A begins – 4th St. Bridge, Peters Creek Parkway and other local improvements All of Business 40 Reopens

Fall

2017

4 3

Dec 2016 Jan 2017

NCDOT announces that Business 40 will be renamed Salem Parkway in 2020

2

October 21

2016

September

2016

Business 40 closes while construction Segments B and C begin

6

2017

Fall

2018

ONLY the section

  • f Business 40

from Main St. east to U.S. 52 reopens

7

2017

Fall

2019

Construction Segment D begins – MLK Jr. Blvd. and Academy St. Improvements

5

Summer

2018

8

Summer

2020

1

PUBLIC MEETING AUG/SEP 2017

slide-6
SLIDE 6

Building the Future

Construction Segments A-D

Fall 2019 – Summer 2020

slide-7
SLIDE 7

Building the Future

Construction Segment A

Fall 2017 to Fall 2018

PETERS CREEK PKWY. FOURTH STREET BUSINESS 40 APPLE & GREGORY STREETS

slide-8
SLIDE 8

Building the Future

Construction Segment D*

Summer 2018 to Fall 2018

MLK, Jr. Blvd./Eighth St.

slide-9
SLIDE 9

Peter’s Creek Pkwy. and Silas Creek Pkwy.

Off-Site Improvements

slide-10
SLIDE 10
  • Peters Creek Parkway/Second Street at First Street

Provide a second left turn lane eastbound and a third left turn lane westbound

  • Broad Street at Second Street

Convert the left most eastbound through lane to a shared left/through lane

  • Broad Street at Fifth Street

Provide a separate left turn lane westbound

  • Broad Street at Sixth Street

Provide a separate left turn lane westbound

  • Marshall Street at Academy Street

Provide a separate left turn lane southbound

  • Third Street at Liberty Street

Provide a separate left turn lane westbound

Off-Site Improvements

slide-11
SLIDE 11
  • Martin Luther King Jr. Drive at Marshall Street & Cherry Street

Provide a second left turn lane southbound

  • First Street at Northwest Boulevard

Provide a separate right turn lane westbound

  • First Street at Hawthorne Road

Provide a separate right turn lane northbound

  • Northwest Boulevard at Broad Street/Thurmond Road

Provide a separate left turn lane eastbound

  • Peters Creek Parkway at Silas Creek Parkway

Provide a second left turn lane southbound; convert the right most eastbound left turn lane to a through lane and convert the right most eastbound through lane to a second right turn lane.

Off-Site Improvements

slide-12
SLIDE 12

Building the Future

Construction Segment C

Fall 2018 to Fall 2019

THE STROLLWAY LIBERTY ST. MAIN ST. CHURCH ST.

slide-13
SLIDE 13

Building the Future

Construction Segment B

Fall 2019 – Summer 2020

BROOKSTOWN AVE. BROAD STREET GREEN ST. PED BRIDGE BUSINESS 40 MARSHALL & CHERRY STREETS

Fall 2019 – Summer 2020

slide-14
SLIDE 14

Building the Future

Business 40 Closure Period

Business 40 Closure Period

Segment C Bridges* Bridges will be closed while under Construction: Fall 2018 – Fall 2019 *OTHER NOTES Section of Business 40 from Main Street to U.S. 52 will Re-Open: Fall 2019

BUSINESS 40 CLOSED

Segment B Bridges* Bridges will be closed while under Construction: Fall 2019 – Summer 2020

FALL

2018

FALL

2019

SUMMER

2020

  • When a bridge is completed, it will re-open to traffic.
  • When Segment C is completed in Fall 2019, ONLY the section of

Business 40 between Main Street and U.S. 52 will re-open to traffic.

  • The remaining sections of Business 40 will open in Summer 2020.

Bus 40 (pavement and ramps) under construction during both Bridge Segment B & Segment C: Fall 2018 – Summer 2020

Green Street Pedestrian Bridge Broad Street Business 40 Brookstown Ave. Marshall Street Cherry Street Liberty Street The Strollway Main Street Church Street

slide-15
SLIDE 15
  • Initial construction work DOES NOT mean closure.
  • Peters Creek Parkway interchange and local road work

will begin in Fall 2017 and finish in Fall 2018.

  • Business 40 will be closed beginning in Fall 2018 and

ending in Summer 2020.

  • Liberty/Main and Cherry/Marshall one-way pairs WILL

NOT be closed at the same time.

  • Detours and bridge closures must be noticed 30 days in

advance.

  • Incident Management Plan is underway to better manage

and clear accidents.

Building the Future

A Few Reminders

slide-16
SLIDE 16

Building the Future

A Transportation Management Plan (TMP) is currently being reviewed by the City and NCDOT.

The TMP includes detours for vehicles and pedestrians.

slide-17
SLIDE 17

Building the Future

  • Currently, NO vehicular detours are planned on First or

Second Streets between Broad and Marshall Streets.

  • Pedestrian detours are planned for First Street between

Broad and Marshall Streets.

  • A capacity analysis is being conducted on the proposed

detours - results are anticipated this summer.

What we can Share with you NOW

slide-18
SLIDE 18

Building the Future

Downtown Roads that provide “through” access during Closure

Bridges to reopen once complete – detours for each bridge closure. First and Second streets in Holly Avenue Neighborhood will NOT be signed as detour routes.

slide-19
SLIDE 19

Building the Future

Area roads providing access to Downtown

slide-20
SLIDE 20

Building the Future

  • Incorporate new design features; visually attractive.
  • Created through the combined efforts of:
  • NCDOT
  • Business 40 Bridge & Design Working Group
  • City of Winston-Salem
  • Creative Corridors Coalition

New Bridge Designs

slide-21
SLIDE 21

Building the Future

Peters Creek Pkwy. Bridge

slide-22
SLIDE 22

Building the Future

Church Street Bridge

slide-23
SLIDE 23

Building the Future

Marshall Street Bridge

slide-24
SLIDE 24

Building the Future

Green St. Pedestrian Bridge

slide-25
SLIDE 25

Building the Future

Green St. Pedestrian Bridge

(lighted at night)

slide-26
SLIDE 26

Building the Future

Strollway Land Bridge

slide-27
SLIDE 27
  • Managing accidents will be critical during closure.
  • NCDOT is coordinating with City and County services,

including Police, Fire, EMS, to remove/clear accidents quickly.

  • Will install mobile message boards to alert drivers.
  • Will contract with towing company to ensure quick

removal of vehicles.

  • Will add one more driver to IMAP routes, add routes and

mobilize equipment at specific locations.

Building the Future

Managing Accidents during Closure

(Incident Management)

slide-28
SLIDE 28

Building the Future

  • Free Park and Ride/Shuttle locations
  • Employer-based incentives for FREE RIDES
  • Additional cameras and signage for

Incident Management

  • Centralized Regional Call Center
  • Interactive transit maps for real time info.
  • “Dynamic” carpool and vanpool rides
  • Expanded marketing and outreach program to

provide citizens alternative mobility options

www.partnc.org

A Plan to Enhance Mobility Options

Piedmont Authority for Regional Transportation (PART)

slide-29
SLIDE 29
  • Telecommuting
  • 4-day, 10-hour/day work week
  • Flextime, staggered work hours
  • Vanpool/carpool incentives
  • Webinars, conference calls, on-line sharing in lieu of

meetings

Building the Future

Employer’s Can Help:

slide-30
SLIDE 30

Building the Future

  • Name was announced on October 21 at Groundbreaking

Ceremony.

  • New name for all of US 421/Business 40 (from I-40/US 421

split near Clemmons to I-40 in Guilford County).

In case you didn’t know: Business 40 got a new name!

slide-31
SLIDE 31

Building the Future

Outreach and Communication

  • Social media:
  • Web site: www.business40nc.com
  • Twitter: @NCDOT_Triad #Biz40NC
  • Email:
  • business40@business40nc.com
  • Mail:
  • Business 40 Project, NCDOT - Division 9

375 Silas Creek Pkwy., Winston-Salem, NC 27127

PUBLIC MEETINGS – AUGUST/SEPTEMBER 2017

slide-32
SLIDE 32

Building the Future

  • Mobile Navigational Apps.
  • NCDOT communicates with all navigational companies to provide

traffic/travel information.

  • Currently reviewing an agreement with WAZE about “HOW” to share

data.

  • Presentations like the one today.
  • Newsletters – next one is this Summer.
  • Small Business Liaison, SPECIFICALLY for this project.
  • Downtown Partnership, Chamber and City - marketing

campaign to let people know that: DOWNTOWN IS OPEN FOR BUSINESS!

Outreach and Communication

slide-33
SLIDE 33

Building the Future

Miracle King, NCDOT Communications Ofdicer, Div. 7 & 9 336-487-0157 miracleking@ncdot.gov Cassandra Herndon, NCDOT Small Business Liaison 336-747-7833 ceherndon@ncdot.gov Connie James, P.E., City of Winston-Salem Deputy Dir. of Transportation 336-747-6872 conniel@cityofws.org Karen Simon, Pres., Simon Resources Stakeholder Presentations 336-749-1411 simonresrc@gmail.com Pat Ivey, P.E., NCDOT Division 9 Engineer 336-747-7800 pivey@ncdot.gov Michael Penney, NCDOT Design-Build Engineer 919-707-6619 mpenney@ncdot.gov Jamille Robbins, NCDOT Project Manager 919-707-6085 jarobbins@ncdot.gov Jason Mroz, Flatiron Construction Design-Build Contractor jmroz@dlatironcorp.com

Your Business 40 Team

NCDOT, Design-Build Contractor, Consultant

slide-34
SLIDE 34

Building the Future

Concerns, Questions and Comments