Building the Future Todays Presentation Design-Build Team hired to construct Business 40 Timeline to complete project Schedule for Construction Segments A-D Other off-site improvements Bridge designs Transportation
- Design-Build Team hired to construct Business 40
- Timeline to complete project
- Schedule for Construction Segments A-D
- Other off-site improvements
- Bridge designs
- Transportation Management Plan
- Incident Management
- Other mobility options
- Communication and contact information
Building the Future
Today’s Presentation
Building the Future
Business 40 Visualization
Visualization
Building the Future Flatiron Constructors, Inc./Blythe Development Company Joint Venture and HDR Engineering Inc.
- Rebuild the 1.2-mile section of Business 40, which includes
reconstruction of the roadway, 9 vehicular bridges and 2 pedestrian bridges.
- Build a major section of the Multi-Use Path from Peters
Creek Parkway to Liberty Street (remaining section from Peters Creek to Lockland will be built afterwards)
- Increase speed limit to 55mph.
Design-Build Team Hired
Timeline
Project Completed Late 2020
9
NCDOT hires Design-Build Team of Flatiron/Blythe/HDR Preliminary Soil Testing Construction Segment A begins – 4th St. Bridge, Peters Creek Parkway and other local improvements All of Business 40 Reopens
Fall
2017
4 3
Dec 2016 Jan 2017
NCDOT announces that Business 40 will be renamed Salem Parkway in 2020
2
October 21
2016
September
2016
Business 40 closes while construction Segments B and C begin
6
2017
Fall
2018
ONLY the section
- f Business 40
from Main St. east to U.S. 52 reopens
7
2017
Fall
2019
Construction Segment D begins – MLK Jr. Blvd. and Academy St. Improvements
5
Summer
2018
8
Summer
2020
1
PUBLIC MEETING AUG/SEP 2017
Building the Future
Construction Segments A-D
Fall 2019 – Summer 2020
Building the Future
Construction Segment A
Fall 2017 to Fall 2018
PETERS CREEK PKWY. FOURTH STREET BUSINESS 40 APPLE & GREGORY STREETS
Building the Future
Construction Segment D*
Summer 2018 to Fall 2018
MLK, Jr. Blvd./Eighth St.
Peter’s Creek Pkwy. and Silas Creek Pkwy.
Off-Site Improvements
- Peters Creek Parkway/Second Street at First Street
Provide a second left turn lane eastbound and a third left turn lane westbound
- Broad Street at Second Street
Convert the left most eastbound through lane to a shared left/through lane
- Broad Street at Fifth Street
Provide a separate left turn lane westbound
- Broad Street at Sixth Street
Provide a separate left turn lane westbound
- Marshall Street at Academy Street
Provide a separate left turn lane southbound
- Third Street at Liberty Street
Provide a separate left turn lane westbound
Off-Site Improvements
- Martin Luther King Jr. Drive at Marshall Street & Cherry Street
Provide a second left turn lane southbound
- First Street at Northwest Boulevard
Provide a separate right turn lane westbound
- First Street at Hawthorne Road
Provide a separate right turn lane northbound
- Northwest Boulevard at Broad Street/Thurmond Road
Provide a separate left turn lane eastbound
- Peters Creek Parkway at Silas Creek Parkway
Provide a second left turn lane southbound; convert the right most eastbound left turn lane to a through lane and convert the right most eastbound through lane to a second right turn lane.
Off-Site Improvements
Building the Future
Construction Segment C
Fall 2018 to Fall 2019
THE STROLLWAY LIBERTY ST. MAIN ST. CHURCH ST.
Building the Future
Construction Segment B
Fall 2019 – Summer 2020
BROOKSTOWN AVE. BROAD STREET GREEN ST. PED BRIDGE BUSINESS 40 MARSHALL & CHERRY STREETS
Fall 2019 – Summer 2020
Building the Future
Business 40 Closure Period
Business 40 Closure Period
Segment C Bridges* Bridges will be closed while under Construction: Fall 2018 – Fall 2019 *OTHER NOTES Section of Business 40 from Main Street to U.S. 52 will Re-Open: Fall 2019
BUSINESS 40 CLOSED
Segment B Bridges* Bridges will be closed while under Construction: Fall 2019 – Summer 2020
FALL
2018
FALL
2019
SUMMER
2020
- When a bridge is completed, it will re-open to traffic.
- When Segment C is completed in Fall 2019, ONLY the section of
Business 40 between Main Street and U.S. 52 will re-open to traffic.
- The remaining sections of Business 40 will open in Summer 2020.
Bus 40 (pavement and ramps) under construction during both Bridge Segment B & Segment C: Fall 2018 – Summer 2020
Green Street Pedestrian Bridge Broad Street Business 40 Brookstown Ave. Marshall Street Cherry Street Liberty Street The Strollway Main Street Church Street
- Initial construction work DOES NOT mean closure.
- Peters Creek Parkway interchange and local road work
will begin in Fall 2017 and finish in Fall 2018.
- Business 40 will be closed beginning in Fall 2018 and
ending in Summer 2020.
- Liberty/Main and Cherry/Marshall one-way pairs WILL
NOT be closed at the same time.
- Detours and bridge closures must be noticed 30 days in
advance.
- Incident Management Plan is underway to better manage
and clear accidents.
Building the Future
A Few Reminders
Building the Future
A Transportation Management Plan (TMP) is currently being reviewed by the City and NCDOT.
The TMP includes detours for vehicles and pedestrians.
Building the Future
- Currently, NO vehicular detours are planned on First or
Second Streets between Broad and Marshall Streets.
- Pedestrian detours are planned for First Street between
Broad and Marshall Streets.
- A capacity analysis is being conducted on the proposed
detours - results are anticipated this summer.
What we can Share with you NOW
Building the Future
Downtown Roads that provide “through” access during Closure
Bridges to reopen once complete – detours for each bridge closure. First and Second streets in Holly Avenue Neighborhood will NOT be signed as detour routes.
Building the Future
Area roads providing access to Downtown
Building the Future
- Incorporate new design features; visually attractive.
- Created through the combined efforts of:
- NCDOT
- Business 40 Bridge & Design Working Group
- City of Winston-Salem
- Creative Corridors Coalition
New Bridge Designs
Building the Future
Peters Creek Pkwy. Bridge
Building the Future
Church Street Bridge
Building the Future
Marshall Street Bridge
Building the Future
Green St. Pedestrian Bridge
Building the Future
Green St. Pedestrian Bridge
(lighted at night)
Building the Future
Strollway Land Bridge
- Managing accidents will be critical during closure.
- NCDOT is coordinating with City and County services,
including Police, Fire, EMS, to remove/clear accidents quickly.
- Will install mobile message boards to alert drivers.
- Will contract with towing company to ensure quick
removal of vehicles.
- Will add one more driver to IMAP routes, add routes and
mobilize equipment at specific locations.
Building the Future
Managing Accidents during Closure
(Incident Management)
Building the Future
- Free Park and Ride/Shuttle locations
- Employer-based incentives for FREE RIDES
- Additional cameras and signage for
Incident Management
- Centralized Regional Call Center
- Interactive transit maps for real time info.
- “Dynamic” carpool and vanpool rides
- Expanded marketing and outreach program to
provide citizens alternative mobility options
www.partnc.org
A Plan to Enhance Mobility Options
Piedmont Authority for Regional Transportation (PART)
- Telecommuting
- 4-day, 10-hour/day work week
- Flextime, staggered work hours
- Vanpool/carpool incentives
- Webinars, conference calls, on-line sharing in lieu of
meetings
Building the Future
Employer’s Can Help:
Building the Future
- Name was announced on October 21 at Groundbreaking
Ceremony.
- New name for all of US 421/Business 40 (from I-40/US 421
split near Clemmons to I-40 in Guilford County).
In case you didn’t know: Business 40 got a new name!
Building the Future
Outreach and Communication
- Social media:
- Web site: www.business40nc.com
- Twitter: @NCDOT_Triad #Biz40NC
- Email:
- business40@business40nc.com
- Mail:
- Business 40 Project, NCDOT - Division 9
375 Silas Creek Pkwy., Winston-Salem, NC 27127
PUBLIC MEETINGS – AUGUST/SEPTEMBER 2017
Building the Future
- Mobile Navigational Apps.
- NCDOT communicates with all navigational companies to provide
traffic/travel information.
- Currently reviewing an agreement with WAZE about “HOW” to share
data.
- Presentations like the one today.
- Newsletters – next one is this Summer.
- Small Business Liaison, SPECIFICALLY for this project.
- Downtown Partnership, Chamber and City - marketing
campaign to let people know that: DOWNTOWN IS OPEN FOR BUSINESS!
Outreach and Communication
Building the Future
Miracle King, NCDOT Communications Ofdicer, Div. 7 & 9 336-487-0157 miracleking@ncdot.gov Cassandra Herndon, NCDOT Small Business Liaison 336-747-7833 ceherndon@ncdot.gov Connie James, P.E., City of Winston-Salem Deputy Dir. of Transportation 336-747-6872 conniel@cityofws.org Karen Simon, Pres., Simon Resources Stakeholder Presentations 336-749-1411 simonresrc@gmail.com Pat Ivey, P.E., NCDOT Division 9 Engineer 336-747-7800 pivey@ncdot.gov Michael Penney, NCDOT Design-Build Engineer 919-707-6619 mpenney@ncdot.gov Jamille Robbins, NCDOT Project Manager 919-707-6085 jarobbins@ncdot.gov Jason Mroz, Flatiron Construction Design-Build Contractor jmroz@dlatironcorp.com