BEX IV Planning Board Work Session March 28, 2012 Agenda 1. - PowerPoint PPT Presentation

Photos by Susie Fitzhugh BEX IV Planning Board Work Session March 28, 2012 Agenda 1. BEX/BTA Spending History 2. BEX IV Planning Assumptions and Variables 3. BEX IV Schedule 4. Enrollment and Capacity Surplus/Shortfall Review 5. Review


  1. Photos by Susie Fitzhugh BEX IV Planning Board Work Session March 28, 2012

  2. Agenda 1. BEX/BTA Spending History 2. BEX IV Planning Assumptions and Variables 3. BEX IV Schedule 4. Enrollment and Capacity Surplus/Shortfall Review 5. Review of Stakeholder Feedback (FACMAC, BEX Oversight, Staff) 6. Review of Scenarios by Middle School Service Area 7. Scenario Summary of Costs and Added Capacity – Goal: Reduce to Three Scenarios (one at low, medium, and higher cost levels) 8. BEX IV Other Projects 9. Preliminary Tax Rate Implications 2

  3. History of Capital Spending in SPS North Region % of Total BEX & BTA I , II & III 37% Central Region % of Total BEX & BTA I, II & III 18% South West Region % South East Region % of Total of Total BEX & BTA I, II & III BEX & BTA I, II & III 22% 23% 3

  4. Long Term Planning • Capacity Units = students / percentages 6 + Years • Geographic Unit = service areas • Capital Levies (BEX IV) Intermediate Planning • Capacity Units = students / percentages • Geographic Unit = service areas 4 Years Short Term Planning • Capacity Units = home rooms 1 Year • Geographic Unit = school attendance / service areas 4

  5. 5

  6. How will Building Projects be Chosen for BEX IV? The SPS 2012 Facilities Master Plan will serve as the platform for project selection. The Board has developed policies and guidelines that direct capital planning staff to prioritize potential projects: • Health, Safety and Security • Capacity • Building Condition 6

  7. Overview of BEX IV Levels 1,2,3 Level 1: assumes that all portable classrooms currently in use as of Aug 2012 will remain (approx. 156 in open schools of which 42 are not homerooms). Level 2: assumes that portable general classrooms will be reduced to approximately 5% of K-8 general classrooms (1,482 x 5% = 74). Level 3: assumes that almost all portable classrooms are eliminated in grades K-8 (not including non- homeroom portables). 7

  8. Summary of Portables as of 2012 • General Classroom Portables @ Active Schools: 114 • Portables @ Closed Buildings: 14 • Non Homeroom Classroom Portables: 42 – PCP: 12 – Resource: 10 – OT/PT: 5 – Head Start: 2 – Childcare: 7 – Partnership: 2 – Other: 4 • Total of all Portables: 170 8

  9. 2020-21 K-5 Cumulative Capacity Shortfall By MS Service Area (Without Portables) 9 Note: Negative numbers indicate excess capacity

  10. 2020-21 6-8 Cumulative Capacity Shortfall By MS Service Area (Without Portables) 10 Note: Negative numbers indicate excess capacity

  11. 9-12 Projection (Without Portables) 11

  12. 12

  13. Review of Stakeholder Feedback ( Based on March Meetings with Principals, FACMAC, BEX Oversight, SPS Departmental Staff ) • Decision on APP configuration integral to planning process • Get maximum capacity for investment in building additions • Decision on permanent STEM in West Seattle (Genessee Hill often suggested) • Support for combining Roxhill and Arbor Heights • Support for repurposing Jane Addams as a comprehensive middle school • Support for maintaining a small percentage of homeroom portables • K-8 Mushroom concept – discussions around several factors of concern 13

  14. Comprehensive Middle School / K-8 Mushroom School – Feedback Threads • Instructional staff, principals, FACMAC, generally supportive of comprehensive middle school concept • Current K-8 schools are often under-enrolled in grades 6-8, even in neighborhoods with overcrowded 6-8 schools • Concern about limitations in program offerings in grades 6-8 in a K-8 school • We currently lack clarity of definition, including educational specifications, operating model (staffing and cost), and instructional program framework for the K-8 mushroom model  FACMAC Recommendation: Scenario 2B be removed – no support  Staff Recommendation: Scenario 2B be removed 14

  15. Scenario Review Goal: Reduce to Three Scenarios: Scenario 1: w/current level of portables (estimated @ $525M) Scenario 2: w/portable use reduced to 5% (estimated @ $745M) Scenario 3: w/portables removed @ elem level (estimated @ $855M) 15

  16. Level 2A Comprehensive MS (5%Portables) - $749m Eckstein Elementary • Thornton Creek – New K-8 (retain Whitman K-5) Elementary • Rogers – Replace • Bagley - Addition/Modernize • North Beach – Replace Middle • Olympic Hills – Build Adjacent Middle • Wilson Pacific – New / Replace Interim • John Marshall - interim Hamilton High School • Lincoln – Update McClure Elementary Interim • Magnolia – Modernize • Lincoln - interim • Queen Anne - Addition City Planning • South Lake Union - New Washington Elementary • TT Minor - Open Middle • Meany – Replace Madison High School Elementary • Meany – Replace • Schmitz Park at Genesse Hill – • Mann - Modernize Replace • Fairmount Park – Open / Modernize Mercer Middle • Mercer – Addition Interim Denny • Old Van Asselt - interim Elementary • Roxhill/Arbor Heights @ Arbor Heights - New Aki Kurose • Hughes - Open Interim • Boren - interim 16

  17. Level 2B K- 8 “Mushroom” (5% Portables) - $743m Eckstein K-8 • Thornton Creek – New K-8 Whitman (retain K-5)) Elementary • Olympic Hills K-8 – Replace • Bagley – Addition / Modernize • North Beach – Replace Interim • John Marshall - interim K-8 • Wilson Pacific K-8 – New Hamilton High School McClure • Lincoln – Modernize Elementary Interim • Magnolia - Modernize • Lincoln - interim City Planning • South Lake Union - New Washington Elementary • McGilvra – Addition / Modernize Madison Middle Elementary • Meany – Replace • Schmitz Park @ Genesse Hill - Replace High School • Fairmount Park – Open / Update • Meany – Replace • Mann - Modernize Mercer Denny Middle Elementary • Mercer – Addition • Hughes – Open Interim • West Seattle Elementary – Addition • Old Van Asselt - interim Interim • Boren - interim Aki Kurose 17

  18. Level 3 (Minimal Portables) - $857m Eckstein Elementary • Sand Point – Addition / Modernize • Rogers – Replace Whitman • Thornton Creek – New K-8 (retain K- Elementary 5) • Viewlands – Addition Middle • North Beach – Replace • Olympic Hills – Build Adjacent • Bagley - Addition / Modernize Interim • Northgate - Replace • John Marshall - interim Middle • Wilson Pacific – Replace Hamilton High School McClure • Lincoln – Modernize Elementary Interim • Queen Anne - Addition • Lincoln - interim City Planning • South Lake Union - New Washington Elementary • TT Minor – Modernize Middle • Meany – Replace Madison • Washington – Addition Elementary • Schmitz Park @ Genesse Hill - Replace High School • Fairmount Park - Modernize • Mann – Modernize • Meany – Replace Mercer Middle • Mercer – Addition Denny Interim Elementary • Old Van Asselt - interim • Roxhill/Arbor Heights @ Arbor Heights - New Aki Kurose • Hughes – Open Elementary • West Seattle Elementary – Addition • Wing Luke – Replace Interim • Boren - interim 18

  19. Level 1 (Keep Current Portables) - $524m Eckstein Elementary • Rogers - Replace Whitman • Thornton Creek – New K-8 Elementary • Viewlands - Addition (retain K-5) • North Beach – Replace Interim • John Marshall - interim Middle School • Wilson Pacific – New Hamilton High School • Lincoln – Modernize Interim McClure • Lincoln - interim Elementary City Planning • South Lake Union - New Washington Elementary • TT Minor – Modernize Middle • Meany – Replace High School • Meany – Replace • Mann - Modernize Madison Elementary • Fairmount Park – Open / Modernize Mercer Middle • Mercer – Addition Denny Interim Elementary • Old Van Asselt - interim • Hughes – Open • West Seattle Elementary – Addition Interim • Boren - interim Aki Kurose 19

  20. Other Projects Part of BEX IV Projects will be selected using School Board guiding principles and stakeholder input: • Technology • Classroom/business/network infrastructure • Infrastructure • Seismic, roofs, security, fields, water lines, cafeterias, Memorial Stadium renovation, program placement • Operations • Capital major preventative maintenance 20

  21. Total Tax Levy – Financial Impacts Four variables that will affect our overall tax rate: 1. Operations (M&O) Levy (Feb 2013) • Higher enrollment = increased levy = higher tax rate 2. Size of BEX IV Capital Levy (Feb 2013) 3. Size of BTA IV Capital Levy (Feb 2016) • Need to take its future size into account; currently assuming a similar level in 2016/beyond ($45M/yr) 4. Assessed Valuation • Higher A/V = lower tax rate; lower A/V = higher rate 21

  22. Summary of BEX IV Tax Rate Impacts Note: figures below are estimated based on preliminary data; for illustration purposes only Current BEX III Tax Rates per $1,000/AV: • 2012 BEX III ($490M over 6 years/$81.7M per year) = $ .70 (current level) • 2013 BEX III ($490M over 6 years/$81.7M per year) = $ .70 (current level) Comparison of 2014 to 2019 Tax Rates per $1,000/AV @ $600M and $750M: 2014 2015 2016 2017 2018 2019 BEX IV @ Current $ .70 $ .70 $ .70 $ .70 $ .70 $ .70 BEX IV @ $600M $ .86 $ .85 $ .84 $ .82 $ .81 $ .79 $1.08 BEX IV @ $750M $1.06 $1.05 $1.03 $1.01 $ .99 22

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.