Andover BF 0132(14) Alternatives Presentation Meeting FAS Route 132 - - PowerPoint PPT Presentation
Andover BF 0132(14) Alternatives Presentation Meeting FAS Route 132 - - PowerPoint PPT Presentation
Andover BF 0132(14) Alternatives Presentation Meeting FAS Route 132 Bridge #9 over Trout Brook October 22, 2018 Introductions Laura Stone, P.E. VTrans Scoping Engineer Gary Laroche, P.E. VTrans Project Engineer Carolyn Carlson, P.E.
Introductions
Laura Stone, P.E.
VTrans Scoping Engineer
Gary Laroche, P.E.
VTrans Project Engineer
Carolyn Carlson, P.E.
VTrans Design Project Manager
Purpose of Meeting
- Provide an understanding of our approach to the
project
- Provide an overview of project constraints
- Discuss alternatives that were considered
- Discuss our recommended alternative
- Provide an opportunity to ask questions and voice
concerns
Location Map
Bridge 9 Project Location
Meeting Overview
- VTrans Project Development Process
- Project Overview
– Existing Conditions – Alternatives Considered – Recommended Alternative
- Maintenance of Traffic
- Schedule
- Summary
- Next Steps
- Questions
VTrans Project Development Process
Project Definition Project Design Construction Project Funded Project Defined Contract Award
- Quantify areas of
impact
- Environmental
permits
- Develop plans,
estimate and specifications
- Right-of-Way
process if necessary
Initiated
- Identify resources &
constraints
- Evaluate alternatives
- Public participation
- Build Consensus
Project Overview
- Existing Conditions
- Alternatives Considered
- Recommended Alternative
Description of Terms Used
Existing Conditions – Bridge #9
- Roadway Classification – Major Collector (Class 2 TH/FAS Route)
- Bridge Type – 84’ Long Rolled Beam Bridge
- Ownership – Town of Andover
- Constructed in 1939
Looking East over Bridge
Existing Conditions – Bridge #9
- Bridge 9 is Structurally Deficient due to the deck rating
– localized spots with heavy deterioration, concrete spalling and large sections of exposed reinforcing steel. – Potential for full depth pop-outs
- The rolled beams are in satisfactory condition, but have
areas of heavy rust scaling, especially in the areas where deck spalling is present, and have minor section loss.
- Both backwalls are failing with most of the concrete
spalled with exposed reinforcing steel throughout. There is a potential for holes forming in the approaches due to the loss of roadbed material
Existing Conditions - Bridge #9
- Deck Rating
4 (Poor)
- Superstructure Rating
6 (Satisfactory)
- Substructure Rating
5 (Fair) Deck Deterioration
Existing Conditions - Bridge #9
- Skeletal Abutments
- Failing Backwalls
- Poor Condition bridge seats
Substructure
Existing Conditions - Bridge #9
- Class II Wetlands in Southeast Quadrant
- Wildlife Corridor
- Clear span meets required bankfull width
Hydraulics and Environmental Resources
Existing Conditions
- ADT of 830
- DHV of 120
- % Trucks: 19.6
- Design Speed of 40 mph
- Aerial Utilities
Design Criteria and Considerations
- No Action
– Additional maintenance required within 10 years
- Deck Replacement
– Structural deficiencies would be addressed – Widen to match the corridor – 30 year design life – Meets all ANR and hydraulic standards
- Superstructure Replacement
– Widen to match the corridor – 30 year design life – Meets all ANR and hydraulic standards
- Full Bridge Replacement On Alignment
– Widen to match the corridor – 75 year design life
- Full Bridge Replacement Off Alignment
– Widen to match the corridor – 75 year design life
Alternatives Considered – Bridge #9
Recommended Alternative - Bridge #9
- Full Bridge Replacement
– Widen to match the corridor – New integral abutments – 80’ span with skew similar to existing – 75 year design life
Proposed Typical Section
Proposed Layout Full Replacement On Alignment - Bridge #9
- 10’/3’ typical, 75 year design life
Proposed Profile
Maintenance of Traffic Options Considered
- Offsite Detour
- Phased Construction
- Not an option for full bridge replacement
- Temporary Bridge
Road Closure
- Detour chosen and signed by Town
- Shortest route is 6.4 miles end-to-end
- 8 week closure
- The shortest local detour
route, has an End-to-End distance of 6.4 miles
- Truck route available with
end-to-end distance of 23.4 miles
Traffic Control – Offsite Detour
What would be the maximum acceptable length of closure for Bridge #9? RAISE OF HAND
- A. 2 weeks
- B. 4 weeks
- C. 6 weeks
- D. 8 weeks
- E. 10 weeks
- F. 12 weeks
- G. No Preference
Temporary Bridge
- One Lane Upstream Temporary Bridge with Traffic Signal
‐ Would require hillside cut
Temporary Bridge Layout
Recommended Scope
- Full Bridge Replacement with Traffic Maintained on an
Offsite Detour
– Widen to match the corridor – New integral abutments – 80’ span with skew similar to existing – 75 year design life – 8 week closure – No/Minimal Right of Way – No Utility Relocation – Construction Year: 2023
Andover BF 0132(14) Alternative 1 Alternative 2 Alternative 3 Alternative 4 Deck Replacement Superstructure Replacement Full Bridge Replacement On‐ Alignment Full Bridge Replacement Off‐Alignment
- a. Offsite
Detour b. Temporary Bridge
- c. Phased
Construction
- a. Offsite
Detour b. Temporary Bridge
- c. Phased
Construction
- a. Offsite Detour
- b. Temporary
Bridge
- a. Existing
Bridge Total Project Costs $1,052,640 $1,454,335 $1,412,918 $1,449,294 $1,415,390 $1,248,928 $2,241,756 $2,044,398 $2,240,248
Annualized Costs
$35,090 $48,480 $47,100 $48,310 $47,180 $41,630 $29,890 $27,260 $29,870
TOWN SHARE
$26,316 $72,717 $70,646 $36,232 $70,770 $62,446 $112,088 $204,440 $224,025
TOWN %
2.50% 5% 5% 2.50% 5% 5% 5% 10% 10%
Project Development Duration
2 Years 4 Years 2 Years 2 Years 4 Years 2 Years 3 Years 4 Years 4 Years
Construction Duration
2 months 9 months 6 months 2 months 9 months 6 months 6 months 18 months 9 months
Closure Duration (If Applicable)
21 days n/a n/a 21 days n/a n/a 60 days n/a n/a
Typical Section ‐ Bridge (feet)
10'/3' (26')
Geometric Design Criteria
Substandard horizontal and vertical alignment at Approach
Utilities
No Relocation No No Relocation No No Relocation Relocation
ROW Acquisition
No Yes No No Yes No No Yes Yes
Design Life
30 30 75 75
Alternatives Matrix
Preliminary Project Schedule
- Construction Start – 2023
– Total Cost Estimate: $2,241,756
- Estimated Town Share: $112,000
This is a list of a few important activities expected in the near future and is not a complete list of activities.
Wait for Town response to recommendation on proposed project
- Develop Conceptual plans and distribute for comment
- Request a Public Information meeting
- Process local agreements
- Right-of-Way process (if needed)
- Town is responsible for any chosen detour route