and synchronization project phase 3
play

and Synchronization Project Phase 3 Planning, Analysis & Design - PowerPoint PPT Presentation

Banner/EAS Chart of Accounts (CoA) Clean-Up and Synchronization Project Phase 3 Planning, Analysis & Design (PAD) Phase PMLC Gate Review February 7, 2018 CoA Phase 3 PAD Phase Gate Review Agenda Project Overview Project Team


  1. Banner/EAS Chart of Accounts (CoA) Clean-Up and Synchronization Project Phase 3 Planning, Analysis & Design (PAD) Phase PMLC Gate Review February 7, 2018

  2. CoA – Phase 3 – PAD Phase Gate Review Agenda Project Overview • Project Team – – Business Needs Business Requirements – PAD Deliverables • Project Definition Document – Business Requirements Review/Functional Specifications (IT) – Project Schedule – Next Steps • 2

  3. CoA – Phase 3 – PAD Phase Gate Review Project Overview Banner/EAS Chart of Accounts (CoA) Clean-Up and Synchronization Project Phase Description Delivery Phase 1 CoA Clean-Up (CoA Structure As-Is) May 2015 Phase 2 Banner CoA Field Use Redesign July 2017 Phase 3 Maintenance of CoA between EAS and Banner September 2018 Today’s Focus: Phase 3 PAD Phase Gate Review 3

  4. CoA – Phase 3 – PAD Phase Gate Review Project Team Executive Sponsors Ann McCorvey Dale McLeod Frank Azuola Project Owners Project Manager Sharon Heinle Melissa Weicker Mike Gardner Comptroller DIT-EIS SAIG DIT-BIS HRIS Anna de Lapparent Aileen Miller Mike Wolf Neena Ali Albert Mojica Michelle Hall Joyce Cage-Ford Sulé Williams Manisha Wadhwani Joseph Francis 4

  5. CoA – Phase 3 – PAD Phase Gate Review Project Overview- Business Needs Phase 3 was originally intended to provide automated synchronization of the • CoA between EAS and Banner. Focus of Phase 3 has changed due to uncertainty around the future state of the • University’s ERP systems. Phase 3 will now consist of stop-gap measures including periodic reports and • processes to ensure that the CoA in Banner and EAS remain synchronized until a decision is made on the new ERP system. 5

  6. CoA – Phase 3 – PAD Phase Gate Review Project Overview - Business Requirements No. Goal/Objective Category Priority System Description Stakeholder (H, M, L) (Banner, EAS, Both, Mapping) 1. Process-Oriented Support H Banner Stop-gap program in Banner that Multiple would automate the shutdown process to reduce manual entry. 2. Reporting H Both Report showing changes to CoA since SAIG/BI/CO a specific date. 3. Reporting H Both Report showing differences in CoA SAIG/BI/CO between EAS and Banner. 4. Reporting H Both Dependency report that would SAIG/BI/CO provide details for departments that need to take action if a Banner code is still in use in Banner, but already end dated/inactivated in EAS. 6

  7. CoA – Phase 3 – PAD Phase Gate Review PAD Phase Deliverables PAD Phase Deliverables Status Project Definition Document - Complete Business Requirements Review& Functional Specifications (IT) Complete Project Schedule Complete PAD Gate Review February 7 Planning, Solution Testing & Proposal Analysis & Deployment Closing Development Readiness Design Nov 2017- Feb 2018 7

  8. CoA – Phase 3 – PAD Phase Gate Review PAD Phase Deliverables Project Definition Document Provided a comprehensive overview of the project consistent with the proposal • content and addressed project management approach, including PMLC process and artifacts Business Requirements Review & Functional Specifications (IT) Reviewed stop gap program requirements • Documented 4 functional specifications for technical solutions for • FTVORGN – – FTVFUND FTVACTV – FTVACCI – • Met with BI to develop Data Warehouse tool to use for reporting 8

  9. CoA – Phase 3 – PAD Phase Gate Review PAD Phase Deliverables - Estimated Timeline Nov. Dec. Jan. Feb. Mar. Apr. May June July Aug. Sept. 2017 2017 2018 2018 2018 2018 2018 2018 2018 2018 2018 Planning, Analysis & Design Phase Gate Review Stop Gap Programs Mid- Phase • FTVORGN Deploy Development Testing -ment Review • FTVFUND Deploy Development Testing -ment • FTVACTV Develop- Deploy Testing ment -ment • FTVACCI Develop- Deploy Testing ment -ment Data Warehouse Reports Deploy Development Testing -ment Closing Closing Gate Review 9

  10. CoA – Phase 3 – PAD Phase Gate Review Next Steps Approval to proceed into Development & Testing Phase for CoA Phase 3 • Phase 3 Development and Testing Phase • – Development/Analyst Testing – Deployment Plan Development • Mid-Phase Briefing – June 2018 Gate Review – September 2018 • 10

  11. Banner/EAS CoA Clean-Up and Synchronization Project For More Information, Contact: Melissa Weicker, Associate, BMAG 571-213-4988 | mweicker@gwu.edu 11

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.