ANACOSTIA RECREATION CENTER AT KETCHAM ANC 8A UPDATE July 7, 2020 ANACOSTIA / KETCHAM REC CENTER 1 PROJECT OVERVIEW ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 PROJECT OVERVIEW 2 PROJECT OVERVIEW ANACOSTIA / KETCHAM REC CENTER


  1. ANACOSTIA RECREATION CENTER AT KETCHAM ANC 8A UPDATE July 7, 2020 ANACOSTIA / KETCHAM REC CENTER 1

  2. PROJECT OVERVIEW ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 PROJECT OVERVIEW 2

  3. PROJECT OVERVIEW ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 PROJECT OVERVIEW 3

  4. PROJECT GOALS • Communication • Safety and Staffing • Connection to Community • Positive Addition to Neighborhood • Improved Outdoor Spaces • Improved Traffic / Parking • Flexibility & Durability ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 PROJECT GOALS 4

  5. PROJECT INTRODUCTION • PROJECT BUDGET : • $15M • PROJECT SCOPE : • New Stand Alone Facility (10-12,000 SF) • Gymnasium • Fitness Center • Demonstration Kitchen • Technology Lounge • Classrooms • Spaces for Multigenerational Programming / Workforce Development • Exterior Upgrades • Multi-functional playing field equipped with a new irrigation system • New running / walking track • Basketball court • Playground and Splash Pad • Parking for both school and new facility • Lighting and Security ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 PROJECT INTRODUCTION 5

  6. MILESTONE SCHEDULE • ANC8A Update July 7, 2020 • Online Survey Aug – Sep 2020 • Community Meeting to Introduce Architect Sep – Oct 2020 • Project Design Phase Fall 2020 – Summer 2021 • Construction Documents, Permitting Summer – Fall 2021 • Construction Kickoff Winter 2021 • Construction Completion Winter 2022 * Schedule subject to change pending weather, unforeseen conditions, etc. ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 MILESTONE SCHEDULE 6

  7. NEXT STEPS • This presentation will be placed on the project website for reference: www.dgs.dc.gov/page/anacostia-recreation-center-new-construction (or simply do a web search for “DGS Ketcham Recreation Center”). • DPR will be issuing community survey to collect programming information. • To be included on our distribution list, please send an email to Brent Sisco at brent.sisco@dc.gov ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 NEXT STEPS 7

  8. POINTS OF CONTACT Brent Sisco Capital Projects Officer DC Department of Parks and Recreation brent.sisco@dc.gov 202.615.9824 David Wooden Landscape Architect DC Department of Parks and Recreation david.wooden1@dc.gov Project Website: https://dgs.dc.gov/page/anacostia-recreation-center-new-construction ANACOSTIA / KETCHAM REC CENTER | ANC Update | July 7, 2020 POINTS OF CONTACT 8

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.