an experiment in takt time
play

An Experiment in Takt Time 16 th LCI Congress | San Francisco, CA | - PowerPoint PPT Presentation

An Experiment in Takt Time 16 th LCI Congress | San Francisco, CA | October 7-10, 2014 Introduction to Project 7,500 SF Gut and Remodel Downtown San Mateo, CA OSHPD Project Occupied Building/ Operational Hospital IFOA-IPD


  1. An Experiment in Takt Time 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  2. Introduction to Project • 7,500 SF Gut and Remodel • Downtown San Mateo, CA • OSHPD Project • Occupied Building/ Operational Hospital • IFOA-IPD Contract with Trade Partners • Last Planner • Pull Scheduling • BIM Modeling 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  3. Why Takt Time? • P2SL looking for small project • James Pease of Sutter Health recommended P2SL for Pankow 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  4. What is Takt time? • German word for beat • Match production rate to demand rate Takt time Cycle time Duration Operation 1 Operation 2 Operation 3 Operation 4 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  5. Takt Time 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  6. Takt-time planning process Data Collection Fine Zone / Work balancing definition Team Rough agreements balancing Adapted from Ballard and Tommelein (1998) white paper • on continuous flow 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  7. Flow Summary Fire sprinkler Duct Piping Drywall Electrical 4 3 Are these work flows compatible? 2 1 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  8. Takt-time planning process Data Collection Average Activity Durations Updated Durations Sequence Details: 10 10 - Rough in electrical before top of 9 9 8 8 wall drywall 7 7 Fine Zone / Work 6 6 5 5 balancing definition 4 4 - “I can install prefab walls in 4 3 3 2 2 days, but only if entire space is 1 1 0 0 clear.” Operation Operation Operation Operation Operation Operation Operation Operation 1 2 3 4 1 2 3 4 Team Rough agreements balancing Adapted from Ballard and Tommelein (1998) white paper • on continuous flow 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  9. Line of Balance Scheduling • What is Line of Balance? • What does it have to do with Takt Time? 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  10. Line of balance scheduling • Optimize the schedule Zone 4 • Used it for pull planning Zone 3 • Did not use the full BIM, still improved the schedule significantly Zone 2 • Line of balance scheduling IS NOT Zone 1 takt-time planning Time 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  11. Dreams to Field • How did we implement Takt Time and Line of Balance in the field? 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  12. Overhead Phase LOB • Begins with Layout on the floor, ends with duct insulation, plumbing chlorinated and all overhead conduit installed. • 44 days total 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  13. 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  14. Individual Trade Workflows Piping Sequence: Duct Sequence: Electrical Sequence: 2,1,3,6,5,4 2,1,3,6,5,4 5,4,1,2,3,6 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  15. Overhead LOB 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  16. Controlling the schedule • Last Planner system • Visual plan system in the field • Goal: Communicate where people are actually working, how fast they are, and if they need to speed up or slow down 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  17. Communicating and controlling the space schedule Daily progress reports and space schedule displayed via whiteboard 16 th LCI Congress | San Francisco, CA | October 7-10, 2014 10/4/2014 17

  18. Interactive Daily Reports and Color Up 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  19. Continuous Improvement of the Plan • Initially structured with 4-day takt time, but this needed to be adapted. 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  20. Continuous Improvement of the Plan • Printed out 11x17 of the LOB schedule and worked with the trades to reschedule w/ a pencil and ruler • Took out 8 days in the schedule due to changing the sequence and crews 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  21. Current Inwall Phase LOB • Now: 29 day sequence. (initially 37 with 4-day takt). 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  22. Overhead Phase Summary Takt Time Planning Results • 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible moment to speed up or slow down • “9/10 when we accelerate, this costs us money. We’ve gone so much faster on this job and it hasn’t cost us a dime”- PM Jeff Stewart of Southland 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  23. Trade Partners Panel • Thoughts when first introduced to Takt Time and Line of Balance • Benefits and Draw Backs? • Opinion of Daily Color Ups and Reports • Effect on working conditions • Ownership of space/ cooperation • Crew Sizes/ Hours Spent compared to original estimate • Material Management 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  24. 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  25. Final Thoughts and Lessons Learned • Data of Findings (PPC) • Success of Project • Calculated Risk • Final Perspective of Takt Time • Incorporating Owner Change Order and saving time 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  26. Questions? P 2 SL 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend