An Experiment in Takt Time 16 th LCI Congress | San Francisco, CA | - - PowerPoint PPT Presentation

an experiment in takt time
SMART_READER_LITE
LIVE PREVIEW

An Experiment in Takt Time 16 th LCI Congress | San Francisco, CA | - - PowerPoint PPT Presentation

An Experiment in Takt Time 16 th LCI Congress | San Francisco, CA | October 7-10, 2014 Introduction to Project 7,500 SF Gut and Remodel Downtown San Mateo, CA OSHPD Project Occupied Building/ Operational Hospital IFOA-IPD


slide-1
SLIDE 1

16th LCI Congress | San Francisco, CA | October 7-10, 2014

An Experiment in Takt Time

slide-2
SLIDE 2

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Introduction to Project

  • 7,500 SF Gut and Remodel
  • Downtown San Mateo, CA
  • OSHPD Project
  • Occupied Building/ Operational Hospital
  • IFOA-IPD Contract with Trade Partners
  • Last Planner
  • Pull Scheduling
  • BIM Modeling
slide-3
SLIDE 3

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Why Takt Time?

  • P2SL looking for small project
  • James Pease of Sutter Health

recommended P2SL for Pankow

slide-4
SLIDE 4

16th LCI Congress | San Francisco, CA | October 7-10, 2014

What is Takt time?

  • German word for beat
  • Match production rate to

demand rate

Operation 1 Operation 2 Operation 3 Operation 4

Cycle time Takt time

Duration

slide-5
SLIDE 5

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Takt Time

slide-6
SLIDE 6

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Takt-time planning process

  • Adapted from Ballard and Tommelein (1998) white paper
  • n continuous flow

Data Collection Zone / Work definition Rough balancing Team agreements Fine balancing

slide-7
SLIDE 7

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Flow Summary

1 3 2 4 Fire sprinkler Duct Piping Drywall Electrical Are these work flows compatible?

slide-8
SLIDE 8

16th LCI Congress | San Francisco, CA | October 7-10, 2014

1 2 3 4 5 6 7 8 9 10 Operation 1 Operation 2 Operation 3 Operation 4

Average Activity Durations

1 2 3 4 5 6 7 8 9 10 Operation 1 Operation 2 Operation 3 Operation 4

Updated Durations

Takt-time planning process

  • Adapted from Ballard and Tommelein (1998) white paper
  • n continuous flow

Data Collection Zone / Work definition Rough balancing Team agreements Fine balancing

Sequence Details:

  • Rough in electrical before top of

wall drywall

  • “I can install prefab walls in 4

days, but only if entire space is clear.”

slide-9
SLIDE 9

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Line of Balance Scheduling

  • What is Line of Balance?
  • What does it have to do with Takt Time?
slide-10
SLIDE 10

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Line of balance scheduling

  • Optimize the schedule
  • Used it for pull planning
  • Did not use the full BIM, still improved

the schedule significantly

  • Line of balance scheduling IS NOT

takt-time planning

Zone 1 Zone 2 Zone 3 Zone 4 Time

slide-11
SLIDE 11

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Dreams to Field

  • How did we implement Takt Time and Line of Balance in the field?
slide-12
SLIDE 12

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Overhead Phase LOB

  • Begins with Layout on

the floor, ends with duct insulation, plumbing chlorinated and all

  • verhead conduit

installed.

  • 44 days total
slide-13
SLIDE 13

16th LCI Congress | San Francisco, CA | October 7-10, 2014

slide-14
SLIDE 14

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Individual Trade Workflows

Duct Sequence: 2,1,3,6,5,4 Piping Sequence: 2,1,3,6,5,4 Electrical Sequence: 5,4,1,2,3,6

slide-15
SLIDE 15

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Overhead LOB

slide-16
SLIDE 16

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Controlling the schedule

  • Last Planner system
  • Visual plan system in the field
  • Goal: Communicate where

people are actually working, how fast they are, and if they need to speed up or slow down

slide-17
SLIDE 17

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Communicating and controlling the space schedule

10/4/2014

17 Daily progress reports and space schedule displayed via whiteboard

slide-18
SLIDE 18

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Interactive Daily Reports and Color Up

slide-19
SLIDE 19

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Continuous Improvement of the Plan

  • Initially structured

with 4-day takt time, but this needed to be adapted.

slide-20
SLIDE 20

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Continuous Improvement of the Plan

  • Printed out 11x17 of the

LOB schedule and worked with the trades to reschedule w/ a pencil and ruler

  • Took out 8 days in the

schedule due to changing the sequence and crews

slide-21
SLIDE 21

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Current Inwall Phase LOB

  • Now: 29 day

sequence. (initially 37 with 4-day takt).

slide-22
SLIDE 22

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Overhead Phase Summary Takt Time Planning Results

  • 44 to 32 days
  • Slowed down some trades,

redirected some trades, sped up

  • thers, identified Last Responsible

moment to speed up or slow down

  • “9/10 when we accelerate, this costs

us money. We’ve gone so much faster on this job and it hasn’t cost us a dime”- PM Jeff Stewart of Southland

slide-23
SLIDE 23

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Trade Partners Panel

  • Thoughts when first introduced to Takt Time and Line of Balance
  • Benefits and Draw Backs?
  • Opinion of Daily Color Ups and Reports
  • Effect on working conditions
  • Ownership of space/ cooperation
  • Crew Sizes/ Hours Spent compared to original estimate
  • Material Management
slide-24
SLIDE 24

16th LCI Congress | San Francisco, CA | October 7-10, 2014

slide-25
SLIDE 25

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Final Thoughts and Lessons Learned

  • Data of Findings (PPC)
  • Success of Project
  • Calculated Risk
  • Final Perspective of Takt Time
  • Incorporating Owner Change Order and saving time
slide-26
SLIDE 26

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Questions?

P2SL