Aitik presentation at CMD 2019
Hans Jönsson, General Manager
Aitik presentation at CMD 2019 Hans Jnsson, General Manager Welcome - - PowerPoint PPT Presentation
Aitik presentation at CMD 2019 Hans Jnsson, General Manager Welcome to Aitik Agenda March 14, 2019 08.15 Hans Jnsson, General Manager Boliden Aitik 09.00 Pause and change of clothes 09.30 Guided tour (2 groups) 11.30 Pause and
Hans Jönsson, General Manager
08.15 Hans Jönsson, General Manager Boliden Aitik 09.00 Pause and change of clothes 09.30 Guided tour (2 groups) 11.30 Pause and change of clothes 12.00 Lunch including final Q& A session with Group Management 13.15 Departure Aitik mine 14.30 Departure Gällivare Airport 16.00 Arrival Arlanda Airport
Boliden CMD 2019 2 2019-03-14
Boliden CMD 2019 3 2019-03-14
Boliden CMD 2019 4
1932 The Aitik deposit discovered
Aitik ore profile
Boliden CMD 2019 4 2019-03-14
Boliden CMD 2019 5 2019-03-14
7,000 ha
Boliden CMD 2019 6 2019-03-14
2019-03-14 7 Boliden CMD 2019 Aitik 5 10 15 20 25 30 35 20 40 60 80 100 120 140
Milled ore tonnes/manhour Million tonnes of ore milled
Copper mine productivity 2018 Open pit mines with concentrator
Source: Wood Mackenzie
New Haul trucks
2008 despite the fact that yearly throughput has increased 100%.
save 830 m3 diesel per year.
reductions.
Remote controlled/autonomous drill rigs Truck trolley
New Aitik electric trolley
New Komatsu 830E-5 intended for Kevitsa and Komatsu 930E-5 intended for Aitik
Boliden CMD 2019 8 2019-03-14
500 1 000 1 500 2 000 2 500 3 000 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Aitik- EBIT (MSEK)
10 000 20 000 30 000 40 000 50 000 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Aitik - Milled production (Ktonnes)
Boliden CMD 2019 9 2019-03-14
2019-03-14
10 20 30 40 50 60 70 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Aitik - Operating costs (excl. depr.), SEK/milled tonne
Boliden CMD 2019 10
Boliden CMD 2019 11
Boliden CMD 2019 11 2019-03-14
500 1 000 1 500 2 000 2 500 Apr May Jun Jul Aug Sep Oct Nov Dec Ktonnes
KiD2 production from start
*KiD2 = Surface crusher 2
Boliden CMD 2019 12 2019-03-14
Boliden CMD 2019 2019-03-14 13
Short facts
Cu
Status
‒ Satellite to Aitik pit ‒ Hauling ore and acid forming waste rock to Aitik ‒ Processing in Aitik
inspectorate
court Risks
2019-03-14
NE SW
Boliden CMD 2019 14
Short facts
surface, still open
‒ Indicated: 8.2 Mtonnes at 1.7% Cu, 0.9 g/tonnes Au, 5 g/tonnes Ag ‒ Inferred: 7.5 Mtonnes at 1.5% Cu, 0.6 g/tonnes Au, 7 g/tonnes Ag
Status
‒ Underground mine, open stoping ‒ Transport to Aitik and processing in Aitik ‒ Application for mining concession ‒ Water treatment ‒ More drilling
Risks
Boliden CMD 2019 2019-03-14 15
2019-03-14
1000 2000 3000 4000 5000
1979 1984 1989 1994 1999 2004 2009 2014 Kg/year
Aitik mine - Emissions of copper per year
Boliden CMD 2019 16
Boliden CMD 2019 17 2019-03-14
2019-03-14
undertake any obligation to correct or update the information or any statements made therein. Certain statements in this presentation are forward-looking and are subject to risks and uncertainties.
any independent verification of the information obtained from third parties.
from engaging in any transaction.
18 Boliden CMD 2019