a1307 cambridge south
play

A1307 Cambridge South East Transport Study Local Liaison Forum 12 th - PowerPoint PPT Presentation

A1307 Cambridge South East Transport Study Local Liaison Forum 12 th September 2018 Greater Cambridge Partnership General Progress Phase 1 scheme design development Current work on scheme design Review of previous work 2018


  1. A1307 Cambridge South East Transport Study Local Liaison Forum 12 th September 2018 Greater Cambridge Partnership

  2. General Progress – Phase 1 scheme design development • Current work on scheme design − Review of previous work − 2018 consultation comments − Value Engineering workshop − Discussions with key stakeholders • Surveys • Programming of works Image source: https://www.greatercambridge.org.uk/transport/transport- projects/cambridge_south_east_study/ Mott MacDonald | Presentation 2 12 September 2018

  3. Scheme 1 – Granham’s Road junction Linton Greenway Proposed right turn lane 30mph speed Remove existing island limit to be extended south Mott MacDonald | Presentation 3 12 September 2018

  4. Scheme 2 – Babraham P&R Additional Cycle Parking Location of proposed cycle parking Mott MacDonald | Presentation 4 12 September 2018

  5. Scheme 3 – Linton Greenway Widen existing Widen existing Existing route Signal crossing Options being On road route reassessed here Widen existing Widen existing Cross via new signals Mott MacDonald | Presentation 5 12 September 2018

  6. Scheme 4/5 – Haverhill Road/ Wandlebury Underpass Realigned Haverhill Road Proposed underpass with pedestrian/ cycle route connection Mott MacDonald | Presentation 6 12 September 2018

  7. Scheme 6 – Babraham Research Campus Roundabout Proposed signalised crossing Mott MacDonald | Presentation 7 12 September 2018

  8. Scheme 7 – Eastbound Bus Lane near A11/ High Street, Babraham Proposed bus lane Proposed signal crossing Proposed bus lane End of bus lane Mott MacDonald | Presentation 8 12 September 2018

  9. Scheme 8 – A11 Multi-user Crossing Existing footbridge amendments Connection to former A11 and Granta Park Equestrian route via underpass Mott MacDonald | Presentation 9 12 September 2018

  10. Scheme 9 – Hildersham Crossroads Proposed signal crossing Mott MacDonald | Presentation 10 12 September 2018

  11. Scheme 10/11 (Interim) – Dalehead Foods Access Mott MacDonald | Presentation 11 12 September 2018

  12. Scheme 10/11 – Dalehead Foods to Linton Village College Mott MacDonald | Presentation 12 12 September 2018

  13. Scheme 12 – Linton High Street Signalise junction Proposed right turn ban being reviewed following 2018 consultation Mott MacDonald | Presentation 13 12 September 2018

  14. Scheme 13/14 – Linton Bus Improvements/ Westbound Bus Lane Proposed bus lane Proposed bus lane Proposed bus lane Mott MacDonald | Presentation 14 12 September 2018

  15. Scheme 15 – Linton Rural Hub Proposed parking Alternative layouts/ alignments being considered at present Realigned arm Mott MacDonald | Presentation 15 12 September 2018

  16. Scheme 16/17 – Dean Road Crossroads/ Linton to Horseheath Central reservation gap to be closed Mott MacDonald | Presentation 16 12 September 2018

  17. Next stages • Scheme design development • Refining overall programme to develop scheme-specific programmes • Tranche 1 schemes delivery • Tranche 2 and Tranche 3 scheme development • Phase 2 development, including interface with Phase 1 and other schemes/ emerging development proposals Mott MacDonald | Presentation 17 12 September 2018

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.