A1307 Cambridge South East Transport Study Local Liaison Forum 12 th September 2018 Greater Cambridge Partnership General Progress Phase 1 scheme design development Current work on scheme design Review of previous work 2018


slide-1
SLIDE 1

Local Liaison Forum 12th September 2018

A1307 Cambridge South East Transport Study

Greater Cambridge Partnership

slide-2
SLIDE 2

General Progress – Phase 1 scheme design development

  • Current work on scheme design

− Review of previous work − 2018 consultation comments − Value Engineering workshop − Discussions with key stakeholders

  • Surveys
  • Programming of works

12 September 2018 Mott MacDonald | Presentation 2

Image source: https://www.greatercambridge.org.uk/transport/transport- projects/cambridge_south_east_study/

slide-3
SLIDE 3

Mott MacDonald | Presentation 3

Scheme 1 – Granham’s Road junction

12 September 2018

Proposed right turn lane Linton Greenway Remove existing island 30mph speed limit to be extended south

slide-4
SLIDE 4

Mott MacDonald | Presentation 4

Scheme 2 – Babraham P&R Additional Cycle Parking

12 September 2018

Location of proposed cycle parking

slide-5
SLIDE 5

Mott MacDonald | Presentation 5

Scheme 3 – Linton Greenway

12 September 2018

Widen existing Widen existing Signal crossing Existing route Options being reassessed here On road route Widen existing Cross via new signals Widen existing

slide-6
SLIDE 6

Mott MacDonald | Presentation 6

Scheme 4/5 – Haverhill Road/ Wandlebury Underpass

12 September 2018

Realigned Haverhill Road Proposed underpass with pedestrian/ cycle route connection

slide-7
SLIDE 7

Mott MacDonald | Presentation 7

Scheme 6 – Babraham Research Campus Roundabout

12 September 2018

Proposed signalised crossing

slide-8
SLIDE 8

Mott MacDonald | Presentation 8

Scheme 7 – Eastbound Bus Lane near A11/ High Street, Babraham

12 September 2018

Proposed bus lane Proposed bus lane Proposed signal crossing End of bus lane

slide-9
SLIDE 9

Mott MacDonald | Presentation 9

Scheme 8 – A11 Multi-user Crossing

12 September 2018

Equestrian route via underpass Existing footbridge amendments Connection to former A11 and Granta Park

slide-10
SLIDE 10

Mott MacDonald | Presentation 10

Scheme 9 – Hildersham Crossroads

12 September 2018

Proposed signal crossing

slide-11
SLIDE 11

Mott MacDonald | Presentation 11

Scheme 10/11 (Interim) – Dalehead Foods Access

12 September 2018

slide-12
SLIDE 12

Mott MacDonald | Presentation 12

Scheme 10/11 – Dalehead Foods to Linton Village College

12 September 2018

slide-13
SLIDE 13

Mott MacDonald | Presentation 13

Scheme 12 – Linton High Street

12 September 2018

Signalise junction Proposed right turn ban being reviewed following 2018 consultation

slide-14
SLIDE 14

Mott MacDonald | Presentation 14

Scheme 13/14 – Linton Bus Improvements/ Westbound Bus Lane

12 September 2018

Proposed bus lane Proposed bus lane Proposed bus lane

slide-15
SLIDE 15

Mott MacDonald | Presentation 15

Scheme 15 – Linton Rural Hub

12 September 2018

Proposed parking Realigned arm Alternative layouts/ alignments being considered at present

slide-16
SLIDE 16

Mott MacDonald | Presentation 16

Scheme 16/17 – Dean Road Crossroads/ Linton to Horseheath

12 September 2018

Central reservation gap to be closed

slide-17
SLIDE 17

Next stages

  • Scheme design development
  • Refining overall programme to develop scheme-specific

programmes

  • Tranche 1 schemes delivery
  • Tranche 2 and Tranche 3 scheme development
  • Phase 2 development, including interface with Phase 1

and other schemes/ emerging development proposals

Mott MacDonald | Presentation 17 12 September 2018