A first choice September, 2016 Forward Looking Information - - PowerPoint PPT Presentation

a first choice
SMART_READER_LITE
LIVE PREVIEW

A first choice September, 2016 Forward Looking Information - - PowerPoint PPT Presentation

Goose Gold Project, Back River, Nunavut, Canada A Gold Miner in the Making A first choice September, 2016 Forward Looking Information Statements relating to our belief as to the timing of completion of the environmental assessment, the results


slide-1
SLIDE 1

A Gold Miner in the Making

September, 2016

Goose Gold Project, Back River, Nunavut, Canada

A first choice

slide-2
SLIDE 2

Forward Looking Information

Statements relating to our belief as to the timing of completion of the environmental assessment, the results of the final public hearings, the timing of receipt of a project certificate and permits and the timing of the start of construction and the first gold pour, and the results of further optimization studies to the feasibility study, the potential tonnage and grades and contents of deposits and the potential production from and viability of Sabina’s properties are forward looking information within the meaning of securities legislation of certain Provinces in Canada. Forward looking information are statements that are not historical facts and are generally, but not always identified by the words “expects,” “plans,” “anticipates,” “believes,” “intends,” “estimates,” “projects,” “potential,” “opportunities,” and similar expressions, or that events or conditions “will,” “would.” “may,” “could,” or should occur. The forward looking information is made of the date of this presentation. This forward looking information is subject to a variety of risks and uncertainties which could cause actual events or results to differ materially from those reflected in the forward looking information, including, without limitation: the effects of general economic conditions; changing foreign exchange rates; risks associated with exploration and project development; the calculation of mineral resources and reserves; risks related to fluctuations in metal prices; uncertainties related to raising sufficient financing to fund the planned work in a timely manner and on acceptable terms; changes in planned work arising from weather, logistical, technical or other factors; the possibility that results of work will not fulfill expectations and realize the perceived potential of the Company’s properties; risk of accidents, equipment breakdowns and labour disputes; access to project funding or other unanticipated difficulties or interruptions; the possibility of cost overruns or unanticipated expenses in the work program; title matters; government regulation; obtaining and receiving necessary licenses and permits; the risk of environmental contamination or damage resulting from Sabina’s operations and other risks and uncertainties including those described in Sabina’s annual information form for the year ended December 31, 2015 available at www.sedar.com Forward looking information is based on the beliefs, estimates and opinions of Sabina’s management on the date the statements are made. Sabina undertakes no obligation to update the forward looking information should management’s beliefs, estimates or opinions, or other factors, change, except as required by applicable law 2

slide-3
SLIDE 3

Key Investment Highlights

3

 Regional scale (80km belt)  Large high grade resource/reserve  Pro responsible development  Feasibility complete  Robust at US$1150 gold and C$0.80

A scarcity of gold and de-risked gold projects make Sabina

  • ne of the few highly leveraged undervalued opportunities

 Strong community support  Attractive to producers looking to replenish supply  Exceptional team  ~C$43 million in cash at June 30, 2016  Expect to end 2016 with ~C$38 million

slide-4
SLIDE 4

Environmental Assessment & Permitting

 Office in Cambridge Bay with Community Liaison  Letters of support from representatives from Kitikmeot hamlets to Minister  Years of engagement and relationship building  We have proven our commitment to the people of the Kitikmeot

4

Broad support for the Project from communities and agencies alike

“…the [NIRB] board wishes to recognize the considerable collaboration, data-sharing, and co-operation that was the hallmark

  • f this review.”
slide-5
SLIDE 5

Environmental Assessment & Permitting

5

Process Milestone Date

 Submitted Project Proposal To NIRB June 14, 2012  Minister directs NIRB to conduct a review of the project under Article 12, Part 5 NLCA December 17, 2012  NIRB issues Final Guidelines for the Review April 30, 2013  Submitted Draft Environmental Impact Statement January 20, 2014  Technical Meetings, Community Round-Table and Pre- Hearing Conference November 13-20, 2014  Pre-hearing Conference Decision released December 19, 2014  Final Environmental Impact Statement submitted November 23, 2015  Final Technical Review and Public Hearings April 25 – 30, 2016  NIRB Project Recommendation On Ministers Desk June 15, 2016 All information from all parties to Minister’s office for review September 30, 2016 Minister’s Decision Re: NIRB Recommendation TBD Water License and all other permits TBD

slide-6
SLIDE 6

NIRB Process

6

 Final public hearings April 25-30th, 2016  Many questions were raised and issues discussed during the hearings  At the end of the hearings, all regulatory agencies , the Government of Nunavut, the Kitikmeot Inuit Association and community members from all hamlets expressed support for the project

 On June 16, 2016, NIRB issued recommendation that project shouldn’t go ahead at this time.  Recommendations and suggestions on a number of issues, in particular caribou  NIRB recognized that the project does not interact with caribou calving and post calving grounds today, but are concerned about caribou changes in migration in the future

slide-7
SLIDE 7

Caribou Calving and Post-calving Core Areas

 No

  • verlap

with the Project  Bathurst herd - west of Project  Beverly herd - east of Project

Source data: GN, DOE 2003 - 2014 Green – calving grounds Purple – post calving grounds

No winter ice road throughout calving and post calving period

slide-8
SLIDE 8

What are we doing?

8

 We continue to receive broad based support for the project (letters posted to NIRB ftp site)  Kitikmeot Inuit Association (land owner) and the Government of Nunavut re-affirmed their support  We continue to engage with stakeholders in the communities and non-government agencies – community tour completed  Submitted comprehensive response to INAC in response to NIRB Report  We are working to incorporate updated measures and commitments made at the hearings into our proposals should

slide-9
SLIDE 9

Our Response to the NIRB Recommendation

 The extensive community and Inuit support for the project  The significant socio-economic benefits to the Kitikmeot  The evidence provided by all parties  the fact that Sabina has already agreed to more protective measures than other projects in the North in many areas  The mandates and responsibilities of federal and territorial agencies and the KIA tasked with oversight of environmental protection

9

We have asked the Minister to reject or send back the NIRB Recommendation

We believe the NIRB Report hasn’t fully considered

slide-10
SLIDE 10

Number of Meetings Number of Major Correspondences (as of April 1, 2016) TOTAL Cambridge Bay 55 8 63 Kugluktuk 52 10 62 Bathurst Inlet & Bay Chimo 9 7 16 Gjoa Haven 17 4 21 Taloyoak 20 3 23 Kugaaruk 17 3 20 Other (e.g. northern trade shows & conferences, SEMCs, newsletters) 33 13 46 Yellowknife / Other Locations in the NWT 14 25 39 TOTAL 217 73 290

10

Significant Community Consultation- We have listened

 We have worked closely with all communities, Hamlet Councils, HTO’s, Elders & Youth advisory Groups  Incorporated traditional knowledge with scientific data in all approaches

As of July, 2016

slide-11
SLIDE 11

Key support from Government and KIA

 “…As a result, KIA recommends that the Report be returned to the Board under paragraph 12.5.7.(e) with your [Minister of INAC] instructions to focus any further investigations on matters related to the Project’s impacts

  • n caribou and the best approaches to mitigation of such impacts.” -

Stanley Anablak, President, Kitikmeot Inuit Association

 “In the GN’s opinion, it is possible to develop terms and conditions to address the concerns expressed by the NIRB of the efficacy and adaptability of mitigation measure[s] for terrestrial wildlife, including

  • caribou. Accordingly, referring the Final Hearing Report back to the NIRB

for further review and public hearings may be the most responsible and expeditious way forward, and the one that provides the best opportunity to advance responsible development to provide economic opportunities for Nunavut’s communities while respecting Inuit societal values and protecting the integrity of our land, water and wildlife.” Government of

Nunavut

11

slide-12
SLIDE 12

Key Support from Communities

 “…I believe that Sabina has proven their case and the construction and operation

  • f this mine would not adversely affect Caribou and our Hamlet and others in the

region are asking you to right the wrong and dismiss the flawed NIRB decision.”

Stephen Inaksajak, Mayor, Hamlet of Kugaaruk

 “I would urge that you allow the Project to proceed now because it is of significant importance to our community. The Kugluktuk Hunters and Trappers have met many times with Sabina gold and Silver and have worked closely with them on a fisheries restoration project in the region. We believe that Sabina will provide jobs and benefits while ensuring they don’t harm the environment. We are confident in their approach to protect caribou.” Larry Adjun, Chairman, Kugluktuk Hunters and Trappers

Organization

 “Without the mining companies, we the Inuit will have no jobs and the Government of Nunavut cannot provide enough jobs for every Inuit, therefore the Inuit will continue to live in poverty if the mines are kept closed.” J. Nivingolak –

Manager, Kugluktk Hunters and Trapper Organization

12

slide-13
SLIDE 13

Key Support from Communities

 “This decision will affect more than just Sabina, as it also adversely affects young people through the Kitikmeot region who desperately require jobs…Please grant Sabina the necessary permits to allow them to commence construction and eventual flourishing operation of the mine…”

The Hamlet of Gjoa Haven

 “The Hamlet of Taloyoak strongly support this project and would like to request to the NIRB to reconsider their decision and grant a permit for exploring and construction of the mine.” Joe Ashevak, Mayor, Hamlet of Taloyoak.

13

Of the 25 letters received to date, 22 have been in support of Sabina and

  • nly 3 have supported the NIRB

recommendation

slide-14
SLIDE 14

What Happens Next?

14

Minister Decision options What do we do? Reject NIRB recommendation Proceed with water license application and detailed engineering Refer the report back to NIRB for further review Further engage with NIRB and intervening agencies to resolve NIRB’s concerns Accept NIRB recommendation Re-submit updated EIS to NIRB, new technical and public hearings

 Report is on Minister of INAC’s desk.  Ultimate decision rests with the Minister

Minister’s decision expected Q4, 2016

slide-15
SLIDE 15

1998 2002 2007 2009 2010 2012 2015

  • 2.0

4.0 6.0 8.0

Gold Resource in Millions of oz.

Back River - Deposits are Well Drilled and Well Understood

1980’s & 90s George & Goose deposit discoveries 1997-2009 Proj ect owned by Arauco, Kinross, Miramar & DPM 2010-2014 +325% resource growth under S abina June 2009 Proj ect acquired by S abina

15

Measured & Indicated

Inferred

*See mineral reserves and resources estimate slides 35 & 36 for details Mineral Resource Estimate Oct/14 Tonnes (kt) Au (g/t) Metal (koz Au) Measured 10,273 5.27 1,740 Indicated 17,969 6.22 3,593 Measured and Indicated 28,242 5.87 5,333 Inferred 7,750 7.43 1,851 Mineral Reserve Estimate Aug/15 Classification Tonnes (kt) Au (g/t) Au (koz) Total Open Pit Proven 6,983 5.97 1,340 Probable 1,885 5.52 335 Total Underground Proven 20 9.52 6 Probable 3,471 7.37 822 Total Back River Property Proven 7,003 5.98 1,346 Probable 5,356 6.72 1,157

80% of open pit reserve is in Proven Category

slide-16
SLIDE 16
slide-17
SLIDE 17

17

Back River Initial Project Feasibility Study Highlights

 Significant Gold Production – 244 koz/au in years 1-8, 198 koz/au LOM.  Simplified Mine Plan – 4 mining areas within 5 km  Primarily Open Pit – 3 open pits (Llama, Umwelt, Goose Main) and 1 underground(Umwelt)  3000 tonnes per day - 72% of ore from open pits. Payback with open pit mining.  Infrastructure – Higher proportion of pre-fab modules targeting less on site labour.  Credible Relevant Benchmarking against Northern projects.

slide-18
SLIDE 18

Back River – Initial Project Feasibility Study Sept 2015 Results

18

Summary Results @US$1,150/oz Gold/ C$0.80 Exchange Pre-Tax NPV(5%) & IRR C$M / % $699 / 28.2% After-Tax NPV(5%) & IRR C$M / % $480 / 24.2% Payback Years 2.9 Mill Throughput tpd 3,000

  • Avg. Grade Processed

diluted g/t Au 6.30g/t Gold Recovery % 93.0% Mine Life Years 11.8

  • Avg. Production (Y1-8)
  • z/year

250,000

  • Avg. LOM Production
  • z/year

198,000 On-Site Op. Costs C$/t milled $114.58 Total Cash Cost $US/oz $534 All-In Sustaining Cost $US/oz $620 LOM All-In Cash Cost* $US/oz $763 Pre-Production Capital C$M $415 Sustaining Capital C$M $185 Closure Capital C$M $64

*LOM All-In Cash Cost includes initial, sustaining and closure capital

QA/QP (see slide 37)

slide-19
SLIDE 19

Back River FS – Sensitivities & Optimizations

Operating Costs

NPV5% (C$M) IRR % Post-Tax

  • 20% -10%

Base Case +10% +20% Capital Costs

  • 20%

715 653 592 529 468 36.2 34.1 32.0 29.7 27.3

  • 10%

659 591 536 474 415 31.8 29.9 27.8 25.6 23.4 Base Case 603 542 480 418 356 28.1 26.2 24.2 22.1 20.0 +10% 547 486 425 362 300 24.8 23.3 21.1 19.1 17.0 +20% 492 430 369 306 245 21.9 20.2 18.3 16.4 14.4

Sensitivity to Capex & Opex

19

Sensitivity to Gold Price and Exchange Rate

Gold price (US$/oz)

NPV5% (C$M)

Exchange Rate: US$:C$

IRR % Post-Tax

0.70 0.725 0.75 0.80 0.85 0.90 $ 1,000 472 421 375 289 210 140 23.9 22.2 20.5 17.4 14.3 11.3 $ 1,150 687 630 577 480 394 317 30.9 29.1 27.4 24.2 21.2 18.4 $ 1,250 832 769 711 606 513 430 35.1 33.3 31.6 28.3 25.3 22.5 $ 1,350 977 910 846 732 631 542 39.1 37.3 35.5 32.2 29.1 26.3 $ 1,500 1,191 1,117 1,048 923 809 710 44.5 42.7 41.0 37.6 34.5 31.6

slide-20
SLIDE 20

Project Optimizations

 Flotation vs whole ore leach  Increased Recoveries  Positive impact on CAPEX and OPEX  Opportunities for satellite deposits (eg: George)  Increased Gold Price  US$1,200 gold price Echo, Llama UG & George are accretive to the project – increased mine life with existing resources  Imbedded growth – all existing deposits remain open, numerous exploration

  • pportunities

 Personnel and expertise availability (both for construction and operations)  Access to used equipment (mining, process and infrastructure)  Exploration opportunities for many years to come

20

slide-21
SLIDE 21

21

Economics – Credible Comparisons

Parameter Units Back River Meliadine1 Hope Bay2 Meadowbank3 Torex4 2015 FS 2015 FS 2015 PFS Producing 2012 FS Au Price US$/oz 1,150 1,300 1,250 400 (2005 FS) Avg $1,386 Post Tax IRR % 24.2 10.3 40.0 12.8% (2005 FS) 24.2% Post Tax NPV5% $M 480 307 626 155.2(2005 FS) $900 Payback years 2.9 5.0 1.7 N/A 3.6 OPEX $/t 114.58

(OP/UG)

135.27

(UG)

143.00

(UG)

73.00 (2015)

(OP)

30.00

(OP)

LOM Cash Costs US$/oz 534 531 638 613 (2015) 504 Pre-Production CAPEX $M 415 1,047 206 710 (2007) 1.5 B (2012) 663 Sustaining CAPEX $M 185 411 334 N/A 15 Total Reserve koz 2,503 3,350 3,507 1,165 4,090 ktonnes 12,359 14,012 14,194 11,795 48,800 g/t 6.30 7.44 7.70 3.08 2.61 LOM Payable Au koz 2,319 3,214 3,200 4,273* 4,090 Annual Production koz 198 350 160 381 (2015) 337

1. Information retrieved from “Agnico Eagle Updated Technical Report on the Meliadine Gold Project, Nunavut, Canada, February, 11, 2015” from www.sedar.com 2. Information retrieved from News Release “TMAC Resources Completes Robust Pre-feasibility Study on the Hope Bay Project”, April 24, 2015 retrieved from www.tmacresources.com 3. Information retrieved from financial results of website www.agnicoeagle.com. Various dates. *Cumulative production plus 2013 reserves and resources 4. Information retrieved from “Morelos Gold Project – 43-101 Technical Report Feasibility Study, Guerrero, Mexico October 1, 2012” from

www.sedar.com

 Comparisons to

  • ther projects

provide validity to quality of Back River FS  Comparable costs using a more conservative gold price

slide-22
SLIDE 22

Nunavut – Active Mining Region

22

 33,000 people live in coastal and inland communities in Nunavut  Mining has been ongoing for decades  Established routes and logistics for fuel delivery, construction equipment and resupply

Nunavut offers certainty of tenure and is pro responsible resource development

slide-23
SLIDE 23

23

Logistics and Transportation – Winter Roads

 Winter roads will be annually constructed beginning in Q4 Year -2  Construction will begin in December and take 6 weeks working on 2 fronts (starting at Goose and the MLA).  The road will then remain operational for 7-8 weeks.  During construction, up to 16 trucks will be used to move freight and fuel from the MLA to the Goose site.  During operations, 23-27 trucks are required annually for freight and fuel from the MLA to Goose (~45 days)

Winter Road Transport Truck

slide-24
SLIDE 24

24

Logistics and Transportation – Marine Routes

Equipment and material originating in western North America or in China will be consolidated at Vancouver, BC. Equipment and material originating in eastern North America or Europe will be consolidated at Becancour, QC.

Arctic Class Barge Arctic Class Transport Ship

slide-25
SLIDE 25

Back River Gold Belt – District Opportunity

25

80 Km

 Current ~12 year mine life with LOM gold production of 2.3Moz.  Significant extended production

  • pportunities exist through:

 Deposits not included in FS plan (at both Goose and George)  Low risk resource conversion

  • pportunities

 Direct extensional potential for all deposits  Numerous blue sky brownfield targets  Continued greenfield and generative exploration future

slide-26
SLIDE 26

Embedded Future Growth

26

George Property  Existing Mineral resources:

 Indicated: 1.1 m oz @ 5.6

g/t

 Inferred: 980k oz @ 6.32

g/t

 ~600k oz included in 6KFS

 Opportunities:

 stand alone second mine  Satellite with haulage via

winter road to Goose complex

 High value potential to

add resources

Significant existing resources at George on 20km of largely unexplored iron formation offering opportunity for another mining complex on the Back River district

slide-27
SLIDE 27

27

Growth Potential at George Property

slide-28
SLIDE 28

Other Opportunities in the District

28

 Two other widely mineralized BIF systems with little to no work  Large gold footprint at Del  Demonstrated opportunity for gold discoveries from field work, grab samples and limited drilling  Many years of exploration bluesky

slide-29
SLIDE 29

29

Attractive as Market Recovers and Producers Look for Supply There are few projects that are:  large  high grade  district scale  in good jurisdictions  at advanced stage of de-risking

Slide retrieved from GOLDCORP corporate presentation dated Nov/2015

slide-30
SLIDE 30

Sabina undervalued compared to peer average

30

Information retrieved from National Bank Financial reports

Precious Metal Developer Companies Company Ticker (C$) NAV/Share(C$) P/NAV (x) Atlantic Gold AGB.V $0.92 $1.14 0.77 AuRico Metals AMI.TO $0.98 $1.10 0.75 Belo Sun Mining BXS.TO $1.01 $1.45 0.79 Dalradian Resources DNA.TO $1.50 $1.72 0.42 Lundin Gold LUG.TO $6.10 $7.09 0.73 Lydian International LYD.TO $0.47 $0.83 0.63 Midas Gold MAX.TO $1.07 $1.04 0.84 Orezone Gold ORE.V $1.22 $1.27 0.88 Pilot Gold PLG.TO $0.85 $1.21 0.71 TMAC Resources TMR.TO $18.95 $11.08 1.9 Victoria Gold VIT.V $0.67 $0.59 1.13 Average 0.84 Sabina Gold & Silver SBB.TO $1.27 $2.79 0.52

slide-31
SLIDE 31

Few projects with after tax IRR >30% with production ~200,000 oz per year at US$1200 gold price

31

50 100 150 200 250 300 350 400 450 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50%

LOM Annual Production (Koz/yr) After-Tax IRR (%) at $1,200/oz

After-Tax IRR and LOM Annual LOM Production Matrix

SBB

PVG KAM DNA GQC ICG AGB AMM PRO VIT BSX NCA MAX CNL TMR

Back River – Large, Robust, Good Jurisdiction

Source: company public information and Cormark Securities based on internal modelling of these projects at US$1200 gold and $0.75 US$:C$ Exchange

slide-32
SLIDE 32

Executive Management Board of Directors Bruce McLeod, President, CEO & Director Bruce McLeod (Pres. & CEO) Elaine Bennett, VP Finance & CFO Roy Wilkes (Chairman) Nicole Hoeller, VP Communications & Corp. Secretary David Fennell Jonathan Goodman James Morton Technical Management Anthony Walsh Angus Campbell, VP Exploration Walter Segsworth Wes Carson, VP Project Development Anna Stylianides Matthew Pickard, VP, Environment & Sustainability

Combined e explorati tion, n, m mine d ne deve velopment, t, p permitti tting g operati tions ns & & cap capital m marke kets e experience i in n over er 70 projects & co companies

Management & Board

32

slide-33
SLIDE 33

Sabina Gold & Silver Corp. Symbol: SBB Listed exchange TSX Market cap. ~C$270 million Shares outstanding 215 million Shares outstanding (diluted) 220 million Cash (Q2) ~C$43 million Debt None 52 week trading range C$0.315 -$1.86 Recent Price ~C$1.25 Analyst Coverage BMO Capital Markets Andrew Kaip Paradigm Capital Don MacLean Cormark Securities Tyron Breytenbach RBC Capital Markets Sam Crittenden National Bank Financial Adam Melnyck Dundee Capital Markets Ron Stewart Canaccord Eric Zaunscherb Haywood Geordie Mark Major Shareholders Holdings (I&O) Dundee Precious Metals 10.7% Sun Valley Gold 10.5% Silver Wheaton 5.3% Management (options included) 3.0%

Corporate Summary & Cash Position

33

slide-34
SLIDE 34

Back River Feasibility Study QA/QC

34 The FS was prepared under the direction of JDS Energy & Mining Inc. by leading independent industry consultants, all Qualified Persons (QP) under National Instrument 43-101. Angus Campbell, P.Geo, Vice-President, Exploration, is a qualified person under NI-43-101 where the information relates to mineral resource estimates and Wes Carson, P.Eng Vice-President, Project Development is a qualified persons under NI 43-101 for the feasibility study and both approve the scientific and technical information contained herein. A National Instrument compliant 43-101 technical report will be filed on the project within 45 days from September 14, 2015. Further information can be found at Technical Report and Feasibility Study for the

Back River Gold Property, Nunavut” dated June 22, 2015 and filed on SEDAR at http://www.sedar.com. Qualified Person, Designation Company QP Responsibility/Role Gord Doerksen, P.Eng. JDS Energy & Mining Inc. Executive Summary, Introduction, Reliance

  • n Other Experts, Reserves, Infrastructure,

Market Studies, Capex, Opex, Economic Analysis, Adjacent Properties, Environmental, Other Relevant Data, Interpretations, Recommendations, References, Abbreviations, Project Execution Plan, Logistics, Infrastructure, G&A Dino Pilotto, P.Eng. JDS Energy & Mining Inc. Mining Methods Andrew Fowler, MAusIMM, CP (Geo) AMC Mining Consultants (Canada) Ltd. Mineral Resource Estimates for George Dinara Nussipakynova, P.Geo AMC Mining Consultants (Canada) Ltd. Mineral Resource Estimates for Goose John Morton Shannon, P.Geo AMC Mining Consultants (Canada) Ltd. Property Description, Accessibility, History, Geology, Deposits, Exploration, Drilling, sample Preparation, Data Verification Maritz Rykaart, P.Eng. SRK Consulting (Canada) Inc. Geochemistry, Tailings Management, Water Management Stacy Freudigmann, P.Eng Canenco Canada Inc. Metallurgy, Recoveries, Process Rob Mercer, Ph.D., P.Eng Knight Piésold Ltd. Geomechanical

slide-35
SLIDE 35

Appendix

35

slide-36
SLIDE 36

36

Back River 2015 Mineral Reserve Estimate

Area

Classification

Tonnes (kt) Au (g/t)

Contained Au (koz)

Total Open Pit Proven 6,983 5.97 1,340 Probable 1,885 5.52 335 Total Underground Proven 20 9.52 6 Probable 3,471 7.37 822 Total Back River Property Proven 7,003 5.98 1,346 Probable 5,356 6.72 1,157

A gold price of US$1,250/oz is assumed. An exchange rate of CDN$1.15 to US$1.00 is assumed. The numbers might not add due to rounding. Notes for open pit: Dilution and recovery factors are applied as per open pit mining method. COG of 2.08 g/t was used for the Umwelt Open Pit Mineral Reserve Estimate. COG of 2.14 g/t was used for the Llama Open Pit Mineral Reserve Estimate. COG of 2.07 g/t was used for the Goose Main Open Pit Mineral Reserve Estimate. Notes for underground: Dilution and recovery factors are applied as per post pillar cut-and-fill underground mining method. COG of 3.86 g/t was used for the Umwelt underground Mineral Reserve Estimate. QP JDS

slide-37
SLIDE 37

37

Back River October 2014 Mineral Resource Estimate

CIM definitions were used for the Mineral Resources.

  • Ms. D. Nussipakynova, P.Geo. and Dr. A. Fowler, Ph.D., MAusIMM, CP (Geo), both from AMC and Qualified Persons under NI 43-

101, take responsibility for the Mineral Resource estimates. Open pit Mineral Resources are constrained by an optimized pit shell at a gold price of US$1,500 oz. The cut-off grade applied to the open pit Resources is 1.0 g/t Au. The underground cut-off grade is 4.0 g/t Au for all George Mineral Resources (LCPn, LCPs, Locale 1, Locale 2, GH, and Slave), 3.5 g/t Au for Goose Main, Echo, and Llama, and 4.5 g/t for the Umwelt deposit. The George Mineral Resources were estimated within mineral domains expanded to a minimum width of 2 m for the underground Mineral Resources. Drilling results up to December 31, 2013 are included, except for Echo (July 4, 2014) and LOC1 and LOC2 (July 21, 2014). The numbers might not add due to rounding.

Classification Tonnes (kt) Au (g/t) Metal (koz Au) Measured 10,273 5.27 1,740 Indicated 17,969 6.22 3,593 Measured and Indicated 28,242 5.87 5,333 Inferred 7,750 7.43 1,851

Mineral Resources that are not mineral reserves do not have demonstrated economic viability. Mineral resource estimates do not account for mineability, selectivity, mining loss and dilution. There is no certainty that the inferred mineral resources will be converted to measured and indicated categories through further drilling, or into mineral reserves, once economic considerations are applied.

slide-38
SLIDE 38

38

Overwhelming Support Received by intervenors and Kitikmeot communities at the hearings

Organization Final comment Kitikmeot Inuit Association “We urge the NIRB to approve the Sabina project and recommend to the responsible minister that it move on to the regulatory stage.” Government of Nunavut “I would like to reiterate our statement of support from our presentation and indicate that, based on the Government of Nunavut’s review and the treatment of our recommendations, we would be able to support this project.” Environment and Climate Change Canada Acknowledged support of Sabina commitments relating to mitigation and monitoring Fisheries and Oceans Canada “Fisheries and Oceans Canada and Sabina have come to an agreement on all of DFOs recommendations.” Indigenous and Northern Affairs Canada “Sabina has made commitments and proposed wordings for terms and conditions that satisfy the issues and concerns raised by Indigenous and Northern Affairs Canada.” Natural Resources Canada “In their final submission, the proponent [Sabina] has addressed Natural Resources Canada’s recommendations.” Transport Canada “Transport Canada has provided recommendations related to the project components that fall within our mandate and are satisfied with the responses that have been provided by Sabina.” Cambridge Bay Hunters and Trappers Organization “…I am prepared to support what you are going after...” “I want to continue working with you, and you know, let’s keep the community consultation ongoing and also the community involvement.” Community of Kugluktuk (member) “In terms of the Kugluktuk Taliqas, we are in favour of the mining company going forward to create employment for our young people.” Community of Bay Chimo (member) “And we say Yes.” Community of Gjoa Haven (member) “…the biggest problems in Gjoa Haven is that we don’t have a lot of jobs, and for that reason alone, Gjoa Haven is in favour of Sabina starting the mine…” Community of Taloyoak (member) “…but I would make it clear that we are supportive of Sabina.” Community of Kugaaruk (member) “I believe what the company is saying about their intentions of using the land in a way that is acceptable to us. Thank you. And for that reason, we say we agree that development happens.” Community of Bathurst Inlet (member) “I would like to say I’m going to support the Sabina mine.”

slide-39
SLIDE 39

Mitigation Measures - Overview of Staged Reduction Management Sabina is committed to protection of Caribou should their ranges ever overlap the project areas