SEPTEMBER 5 - 7, 2018
A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design
Brian Ehsani
A Cost Benefit Analysis of Faster Transmission System Protection - - PowerPoint PPT Presentation
A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design Brian Ehsani SEPTEMBER 5 - 7, 2018 Agenda Example System And Clearing Times Ground Grid Design Cost Analysis Additional Conclusions
SEPTEMBER 5 - 7, 2018
A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design
Brian Ehsani
SEPTEMBER 5 - 7, 2018
Agenda
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
Fault Clearing Times
– Protection scheme (OC, Step Distance, DCB, differential) – DC system (single or redundant) – Breaker failure scheme
breaker op time delay
remote end clearing time (assumes DC system has failed)
SEPTEMBER 5 - 7, 2018
Protection Costs to Reduce Trip Time
installed per position (line, transformer, bus etc.)
– PTs for distance protection – More expensive relays and panel equipment – Communications equipment installation – Redundant DC system installation
SEPTEMBER 5 - 7, 2018
15kA Available Fault Current
SEPTEMBER 5 - 7, 2018
20kA Available Fault Current
SEPTEMBER 5 - 7, 2018
40kA Available Fault Current
SEPTEMBER 5 - 7, 2018
SEPTEMBER 5 - 7, 2018
Cost of Ground Grid Design
– Soil – Fault current – Clearing time
ground grid costs
SEPTEMBER 5 - 7, 2018
Step And Touch Potentials
between a persons feet is sizeable enough to cause fatality
between objects being touched and the person’s feet is sizeable enough to cause fatality
various parameters of the station
SEPTEMBER 5 - 7, 2018
Step And Touch Potentials
SEPTEMBER 5 - 7, 2018
13.5 Cycle Clearing Times
Ground grid design is safe. No touch potentials are shown.
SEPTEMBER 5 - 7, 2018
35.5 Cycle Clearing Times
Ground grid design is unsafe. Touch potentials are shown.
SEPTEMBER 5 - 7, 2018
Ground Grid Assumptions
split factor)
extents of the tested area
SEPTEMBER 5 - 7, 2018
Ground Grid Voltage Potential Mitigation
ground rods around outside border
mitigate voltage potential issues there
where there is a voltage potential issue
grid is redrawn with a more dense spacing
SEPTEMBER 5 - 7, 2018
13.5 Cycle Clearing Time 17.0 Cycle Clearing Time
SEPTEMBER 5 - 7, 2018
23.0 Cycle Clearing Time 35.7 Cycle Clearing Time
SEPTEMBER 5 - 7, 2018
Incremental Grid Cost
$50/foot
clearing time
comes from the conductors needed to make the grid safe.
any useful information
SEPTEMBER 5 - 7, 2018
Tested Grounding Scenarios
respective voltage/current level with 75 Ohm-meter uniform soil
Ohm-meter, 75 Ohm-meter, and 225 Ohm-meter
SEPTEMBER 5 - 7, 2018
Cost Analysis
SEPTEMBER 5 - 7, 2018
15kA Grid Cost With 75 Ohm-Meter Soil
the fastest
scheme to match installed equipment/relaying
SEPTEMBER 5 - 7, 2018
20kA Grid Cost With 75 Ohm-Meter Soil
SEPTEMBER 5 - 7, 2018
40kA Grid Cost With 75 Ohm-Meter Soil
SEPTEMBER 5 - 7, 2018
How Much of an Impact Does Soil Have?
and fast clearing times
models
SEPTEMBER 5 - 7, 2018
How Fault Current Influence Costs
13.5 cycles varies with fault current
15kA
Fault Current Total Cost Cost Increase over 13.5 cycles 15kA $264,900 $38,000 20kA $311,650 $40,000 40kA $723,800 $92,400 23 Cycle Clear Time
SEPTEMBER 5 - 7, 2018
Should Cheaper Relay Schemes Be Used?
cycle breakers did not justify the installation of new breakers
that are generally fast enough for most situations
not have slow trip times due to coordination might be able to use overcurrent relaying
will occur with more complex soil models
SEPTEMBER 5 - 7, 2018
Additional Conclusions
SEPTEMBER 5 - 7, 2018
Additional Considerations
relay tripping speed is weak
faster tripping such as system stability or equipment damage concerns
clearing time to match installed relaying and equipment
SEPTEMBER 5 - 7, 2018
Additional Considerations
clearing times through breaker failure trip time delay reduction
faster remote end clearing time for single DC systems
events – system impact will vary by breaker reliability.
SEPTEMBER 5 - 7, 2018
Process Improvements
phase of a project
selection to determine situations where upgraded relaying is worth the additional price
SEPTEMBER 5 - 7, 2018