3.4 QA/QC for the EHVDC cable systems Technologies for Global Energy Grid 27.06.2019 Dr. Roland D. Zhang Topics Introduction Why QA/QC important for EHVDC cable systems? What could we do for QA/QC? Discussion 2


slide-1
SLIDE 1

3.4 QA/QC for the EHVDC cable systems

Technologies for Global Energy Grid

  • Dr. Roland D. Zhang

27.06.2019

slide-2
SLIDE 2

Topics

  • Introduction
  • Why QA/QC important for EHVDC cable

systems?

  • What could we do for QA/QC?
  • Discussion

2

slide-3
SLIDE 3

Introduction

Insulation: MI (PPLP), Extruded Application: Submarine/underground etc.

27/6/2019 TGEG'19 Workshop 3

Source: ABB/nkt, Nexans

slide-4
SLIDE 4

Why QA/QC important (1)

27/6/2019 TGEG'19 Workshop 4

  • Minimizing risks by the application
  • f new technology without or with

very limited operation experience,

  • esp. for the “pilot project” with a

route length of 700 km EHVDC cables

  • Building the long-term partnership
  • btw. TSOs and all EHVDC cable

manufacturers regarding QA/QC, Win-Win-situation, possibly setting the benchmarks in this area

  • Enhancing the reliability and

availability of EHVDC cable systems

  • Decreasing the failure rate,

particularly avoiding the man-made failure, e.g. joint installation

slide-5
SLIDE 5

Why QA/QC important (2)

27/6/2019 TGEG'19 Workshop 5

  • Avoiding the systematic

failure/serial failure

  • Reducing the re-dispatch cost due

to the outage

  • Saving the reputation
  • Increasing TRL (Technical

Readiness Level) of new technology

  • Accelerating the energy transition
slide-6
SLIDE 6

What to Do for QA/QC (1)

27/6/2019 TGEG'19 Workshop 6

  • Design and Development:
  • Verification of pre-performed tests, i.e. development tests, PQ/EQ,

TT

  • Identification of new PQ, TT or EQ etc.
  • Control of ITP, Manufacturing Control Plan, QC-Plan, interface plan

etc.

  • FMECA and risk assessment of design, installation, testing etc.
  • Sub-suppliers’ qualification and verification
  • Manufacturing and Production
  • Factory audit, checking the attitude of production (floor) staff to

QA/QC

  • Material incoming check/control, traceability
  • Production supervision and witness of tests
  • Dealing with NC, Incident, RCA etc.
slide-7
SLIDE 7

What to Do for QA/QC (2)

27/6/2019 TGEG'19 Workshop 7

  • Installation
  • supervision of cable laying/installation incl. trial installation
  • Supervision of jointing process, assembly the termination
  • HSE, SOLAS
  • Commissioning:
  • SAT, Finger print measurements
  • Trial operation
  • Monitoring systems calibration and application
  • Operation:
  • Maintenance plan incl. RPP and SLA
  • Health Index/Condition monitoring
  • Decommissioning plan
slide-8
SLIDE 8

Discussion

27/6/2019 TGEG'19 Workshop 8

  • Generally, QA/QC for EHVDC cables

shall be initialised and involved as early as possible by TSOs and by cable manufacturers, “Thinking end at the beginning”

  • QA/QC → Balance of

risk/cost/performance of EHVDC cable system

  • Cooperation/Knowledge sharing
slide-9
SLIDE 9

Thank you very much for your attention!

9 27/6/2019 TGEG'19 Workshop