2015 full year results
play

2015 Full Year Results DELIVERING WORLD CLASS PROJECTS 25 February - PowerPoint PPT Presentation

2015 Full Year Results DELIVERING WORLD CLASS PROJECTS 25 February 2016 IMPORTANT NOTICE DISCLAIMER Certain statements included in this presentation contain forward-looking information concerning the strategy of KAZ Minerals PLC (KAZ


  1. 2015 Full Year Results DELIVERING WORLD CLASS PROJECTS 25 February 2016

  2. IMPORTANT NOTICE DISCLAIMER Certain statements included in this presentation contain forward-looking information concerning the strategy of KAZ Minerals PLC (“KAZ Minerals”) and its business, operations, financial performance or condition, outlook, growth opportunities and circumstances in the countries, sectors or markets in which it operates. By their nature, forward-looking statements involve uncertainty because they depend on future circumstances, and relate to events, not all of which are within KAZ Minerals’ control or can be predicted by KAZ Minerals. Although KAZ Minerals currently believes that the expectations reflected in such forward-looking statements are reasonable, no assurance can be given that such expectations will prove to have been correct. Actual results could differ materially from those set out in the forward-looking statements. No part of this presentation constitutes, or shall be taken to constitute, an invitation or inducement to invest in KAZ Minerals, or any other entity, and shareholders are cautioned not to place undue reliance on the forward-looking statements. Except as required by the Rules of the UK Listing Authority and applicable law, KAZ Minerals undertakes no obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise. Neither this presentation, which includes the question and answer session, nor any part thereof may be recorded, transcribed, distributed, published or reproduced in any form, except as permitted by KAZ Minerals. By attending this presentation, whether in person or by webcast or call, you agree with the foregoing and that, upon request, you will promptly return any records or transcript of the presentation without retaining any copies. Basis of preparation The divestment of a number of the Group’s relatively mature mining and power operations, primarily located in the Zhezkazgan and Central Regions (the ‘Disposal Assets’) was approved by the independent shareholders on 15 August 2014. Following shareholder approval, the Disposal Assets were classified as assets held for sale and treated as a discontinued operation in the financial statements from the beginning of the year until their disposal on 31 October 2014. Unless otherwise stated, financial and operating data for 2014 reflect continuing operations only. 1

  3. AGENDA 1. Review of 2015 Oleg Novachuk CEO 2. Bozshakol – ramping up 3. Aktogay – on track 4. Financial update Andrew Southam CFO 5. Delivering growth Oleg Novachuk CEO 2

  4. 1. Review of 2015 OLEG NOVACHUK CHIEF EXECUTIVE OFFICER

  5. 2015 HIGHLIGHTS Strong operational delivery Delivering growth Copper cathode 81 kt, in line with guidance Bozshakol By-products in line or ahead of guidance Commissioning works commenced Over 10 million tonnes of ore mined at Bozshakol First copper concentrate in February 2016, and Aktogay to be shipped in March 2016 $50 million reduction to total project budget Resilient financial performance Lower pricing partially offset by cost control and Aktogay tenge devaluation First copper cathode in December 2015, EBITDA 1 $202 million (2014: $355 million) shipped in January 2016 Gross cash costs 230 USc/lb (H2 2014: 277) 2 Sulphide project on track for 2017 First quartile net cash costs 109 USc/lb NFC deferral of $300 million capex to 2018 (H2 2014: 107) 2 Notes: 4 1. EBITDA (excluding MET and special items) from continuing operations. 2. H2 2014 is considered to be more representative of the East Region as a stand-alone business.

  6. HEALTH AND SAFETY Targeting zero fatalities Consistent reduction in fatalities since 2010 3 fatalities in 2015 (2014: 7) 1 , man-hours increased 78% Fatality rate reduced to 0.07 per million hours (2014: 0.30) 1 Total Recordable Injury Frequency Rate 1.25 (2014: 3.48) 1,2 2016 priorities Best practice being embedded at growth projects and transferred to other assets Safety leadership training Promote a ‘learning culture’ Improve procedures in high risk areas of underground mining, energy isolation and working at height Occupational health initiatives Notes: 5 1. Continuing operations only. 2. ICMM definitions for TRIFR were adopted by the Group in 2015. The 2014 TRIFR for continuing operations has been estimated by applying the new injury definition to available historic data.

  7. GUIDANCE ACHIEVED OR EXCEEDED FOR ALL METALS East Region and Bozymchak FY 2015 FY 2015 Guidance Actuals Strong underlying copper in concentrate 80 – 85 kt Copper cathode 81 kt output of 89 kt Zinc in concentrate output at top end of Zinc in 90 – 95 kt 94 kt guidance concentrate Silver output 25% ahead of guidance, 2,250 – 2,500 koz Silver granule 3,135 koz supported by high grades and release of work in progress Gold output in line with guidance as increased 34 – 38 koz Gold bar 35 koz production from Bozymchak offset lower output from East Region 6

  8. 2. Bozshakol – ramping up OLEG NOVACHUK CHIEF EXECUTIVE OFFICER

  9. BOZSHAKOL STATUS Completed  Pre-production mining  Primary crusher  Overland ore conveyor  Sulphide concentrator  Tailings facilities  First concentrate production  Ongoing Sulphide concentrator commissioning Dispatch of first copper concentrate (March 2016) Ramp up sulphide production to commercial levels Clay plant (summer 2016) Bozshakol sulphide concentrator 8

  10. BOZSHAKOL MINING Operations team Pit plan Recruitment and training of operations personnel progressing well Production Pre-production mining operations began in May 2015 7,099 kt of ore was extracted in 2015: Timing: – 532 kt of sulphide ore (grade 0.52%) Stage 1 2015-2022 – 6,567 kt of clay ore stockpiled (grade 0.70%) Stage 2 The ore mined in 2015 contained 70 koz of gold Stage 3 Mining fleet fully deployed 2023 onwards Stage 4 9

  11. BOZSHAKOL CONCENTRATOR RAMP UP Fire damage repair complete Copper cathode 45 – 65 kt Commissioning is progressing well equivalent 2016 Expect to declare the project commercial in 2016 Full capacity will be reached in 2017 Gold bar 50 – 70 koz equivalent 2016 5 MT clay plant commissioning Commercial Initial ramp up to production - 60% of capacity 25 MT sulphide 2017 fully 2018 peak for 3 months ore throughput ramped up production 2016 2017 2018 10

  12. MARKETING OF CONCENTRATE First shipment expected to be dispatched to Chinese smelters in March 2016 Annual contracts are in place for sale of concentrate The concentrate is attractive to Chinese smelters: – High sulphur content benefits Chinese smelting technology – “Clean concentrate” with low/no deleterious content (e.g. arsenic, iridium) TC/RCs are calculated with reference to annual benchmarks set by the China Smelters Purchase Team and Japanese smelters Bozshakol 8 days to Chinese border Rail connections Aktogay 2 days Balkhash Rail access Almaty to China 11

  13. 12 Crushed ore stockpile

  14. 13 Tailings thickeners

  15. 3. Aktogay – on track OLEG NOVACHUK CHIEF EXECUTIVE OFFICER

  16. AKTOGAY SX/EW PRODUCTION UPDATE Completed Ongoing  Mining (commenced June 2015) Filling heap leach cells 104-109  Cells 101-103 sufficient for current Copper cathode production is expected to ramp up heap leaching volumes swiftly to 15 kt in 2016  SX/EW processing facilities First cathode production on 1 December 2015  First copper from oxide ore Produced 0.4 kt of copper cathode in December 2015 3 MT of oxide ore extraction in 2015, average copper grade 0.37% Copper cathode production at Aktogay 15

  17. 16 SX/EW facility

  18. 17 EW facility

  19. 18 cathode at Aktogay The first copper

  20. AKTOGAY SULPHIDE PROJECT STATUS Completed Ongoing  Sulphide concentrator building enclosed Overland conveyor structural steel  Primary crusher foundations Mill installation  Road and rail infrastructure Flotation cells placement  Mining operations commenced (oxide layer) Tailings facilities Permanent camp Aktogay sulphide concentrator 19

  21. Aktogay SAG and ball mill installation 20

  22. 21 Aktogay flotation cell installation

  23. FY 2016 PRODUCTION GUIDANCE Aktogay Group East Region & Bozshakol Bozymchak Copper cathode 70 – 75 kt 45 – 65 kt 15 kt 130 – 155 kt equivalent Zinc in 70 – 75 kt 70 – 75 kt concentrate Silver granule 2,250 – 2,500 koz 2,250 – 2,500 koz Gold bar 40 – 50 koz 90 – 120 koz 50 – 70 koz equivalent 22

  24. 4. Financial update ANDREW SOUTHAM CHIEF FINANCIAL OFFICER

  25. FINANCIAL UPDATE 2015 2014 1 $m (unless otherwise stated) Operational management in a low commodity price environment Revenue 665 846 ‒ EBITDA of $202 million, strong operating margin EBITDA 2 202 355 ‒ Cost control initiatives and favourable exchange East Region and Bozymchak 240 399 led to a lower gross cash cost of 230 USc/lb Margin 36% 47% ‒ Net cash cost of 109 USc/lb, first quartile operations EPS 3 ($) (0.02) 0.19 Gross cash cost (USc/lb) (17)% 277 230 4 H2 2014 FY 2015 Notes: 24 1. Continuing operations only. 2. EBITDA (excluding MET and special items). 3. EPS based on underlying (loss)/profit from continuing operations excluding special items. 4. H2 2014 is considered to be the most representative period of the performance of the East Region as a stand-alone business.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend