2013 Virginia Concrete Conference Joint Maintenance and Best - - PowerPoint PPT Presentation

2013 virginia concrete conference joint maintenance and
SMART_READER_LITE
LIVE PREVIEW

2013 Virginia Concrete Conference Joint Maintenance and Best - - PowerPoint PPT Presentation

2013 Virginia Concrete Conference Joint Maintenance and Best Practices in Deck Joint Replacement Jeff Milton Bridge Preservation Specialist Structure and Bridge Division March 8, 2013 Presentation Outline Why Joints? Purpose of Joints


slide-1
SLIDE 1

2013 Virginia Concrete Conference Joint Maintenance and Best Practices in Deck Joint Replacement

Jeff Milton Bridge Preservation Specialist Structure and Bridge Division March 8, 2013

slide-2
SLIDE 2

Presentation Outline

2

  • Why Joints?
  • Purpose of Joints
  • Typical Joint Systems Used in Virginia
  • Leaking Joints
  • Virginia Bridge Program
  • Joint Maintenance Procedures
slide-3
SLIDE 3

Why Joints?

3

  • Beam and girder bridge superstructures may be constructed as simply

supported spans or as continuously supported spans.

  • Simply supported spans have only two supports, each located at or

very near the ends. A simple span bridge can have a single span supported by two abutments, or multiple spans that have independent superstructures supported by two abutments and one or more piers.

  • Deck joints will typically be required at both ends of a simply supported

span.

slide-4
SLIDE 4

Why Joints?

4

  • Continuously supported spans have one or more intermediate
  • supports. Continuously supported superstructures are somewhat more

complicated for engineers to analyze. But, when they are designed and constructed properly, they are easier to maintain since they have fewer components.

  • Deck joints will typically be required only at ends of beam or girder

sections in continuously supported spans.

  • By the nature of their construction, bridges with simply support spans

will have more joints than bridges with continuously supported spans.

slide-5
SLIDE 5

Purpose of Joints

5

  • The purpose of bridge deck expansion joints is to accommodate

movement of the superstructure. Superstructure movement is caused by the following :

  • Expansion and contraction caused by temperature variation
  • Concrete shrinkage and creep
  • Live load deflection
  • Wind and seismic loads
  • Settlement
slide-6
SLIDE 6

Typical Joint Systems Used in Virginia

6

  • The following types of joint systems may be found on existing bridges

in Virginia:

  • Armored Joints – Open or Sealed
  • Hot Poured Sealer /Expansion Material
  • Preformed Elastomeric Compression Seals
  • Poured (Silicone) Seals
  • Asphalt Plug Joints (limited number)
  • Strip Seals
  • Sliding Plate Joints
  • Finger Joints
  • Cushion Seal (previously denoted as elastomeric expansion dam – limited

number remaining)

slide-7
SLIDE 7

Typical Joint Systems Used in Virginia

7

  • Armored Joints
slide-8
SLIDE 8

Typical Joint Systems Used in Virginia

8

  • Hot Poured Sealer /Expansion Material
slide-9
SLIDE 9

Typical Joint Systems Used in Virginia

9

  • Preformed Elastomeric Compression Seals
slide-10
SLIDE 10

Typical Joint Systems Used in Virginia

10

  • Poured (Silicone) Seals
slide-11
SLIDE 11

Typical Joint Systems Used in Virginia

11

  • Asphalt Plug Joints (limited number)
slide-12
SLIDE 12

Typical Joint Systems Used in Virginia

12

  • Strip Seals
slide-13
SLIDE 13

Typical Joint Systems Used in Virginia

13

  • Sliding Plate Joints
slide-14
SLIDE 14

Typical Joint Systems Used in Virginia

14

  • Finger Joints
slide-15
SLIDE 15

Typical Joint Systems Used in Virginia

15

  • Cushion Seal (Elastomeric Expansion Dam)
slide-16
SLIDE 16

Leaking Joints

16

  • Leaking bridge deck expansion joints allow run-off water and deicing

chemicals to pass through the joints and onto superstructure and substructure members.

  • The following bridge components are adversely affected by leaking

joints:

  • End Diaphragms
  • Beam/Girder Ends
  • Bearings
  • Substructure Seat Areas
  • Other Substructure Areas
  • Leaking joints cause significant deterioration and damage to bridge

components and are a nationwide bridge maintenance problem. Many millions of dollars are spent each year repairing the damage caused by leaking joints.

slide-17
SLIDE 17

Leaking Joints

17

slide-18
SLIDE 18

Leaking Joints

18

slide-19
SLIDE 19

Leaking Joints

  • Deterioration and damage – steel End Diaphragms

19

slide-20
SLIDE 20

Leaking Joints

  • Deterioration and damage – steel End Diaphragms

20

slide-21
SLIDE 21

Leaking Joints

  • Deterioration and damage – concrete End

Diaphragms

21

slide-22
SLIDE 22

Leaking Joints

  • Deterioration and damage – steel beam ends

22

slide-23
SLIDE 23

Leaking Joints

  • Deterioration and damage – concrete beam ends

23

slide-24
SLIDE 24

Leaking Joints

  • Deterioration and damage – bearings

24

slide-25
SLIDE 25

Leaking Joints

  • Deterioration and damage – bearings

25

slide-26
SLIDE 26

Leaking Joints

  • Deterioration and damage – pier seats and cap

26

slide-27
SLIDE 27

Leaking Joints

  • Deterioration and damage – pier cap

27

slide-28
SLIDE 28

Leaking Joints

  • Deterioration and damage – overall

28

slide-29
SLIDE 29

Virginia’s Bridge Program

  • The Virginia Bridge Program consists of the following four work

actions:

· Preventive Maintenance · Restorative Maintenance · Rehabilitation · Replacement

  • Preventive Maintenance and Restorative Maintenance are the

components of Virginia’s Bridge Preservation Program.

  • Viewed from a high level –
  • Preventive maintenance candidates are structures in Good Condition (a low

General Condition Rating of 6 or greater)

  • Restorative maintenance candidates are structures in Fair Condition (a low

General Condition Rating equal to 5)

  • Rehabilitation and replacement candidates are structures in Poor Condition

(a low General Condition Rating of 4 or less )

29

slide-30
SLIDE 30

Virginia’s Bridge Program

  • Preventive maintenance can be condition based or non-condition
  • based. Non-condition based preventive maintenance is typically

referred to as Planned Preventive Maintenance.

  • Condition based Preventive Maintenance includes sealing leaking deck

joints on bridges that are in overall good condition

  • Planned Preventive Maintenance includes Scheduled Replacement of

Compression Seal Joints in good condition (10 year cycle) and Scheduled Replacement of Pourable Joints in good condition (6 year cycle)

  • Restorative Maintenance includes Reconstructing/Closing Joints on

bridges that are in fair condition

  • There are approximately 19,400 state maintained structures in the

inventory - approximately 11,850 of the structures are bridges

  • The current overall condition for the statewide inventory is shown

below:

  • 70% of the structures are in Good condition
  • 23% of the structure are in Fair condition
  • 7% of the structures are in Poor condition

30

slide-31
SLIDE 31

Joint Maintenance

  • Joint Maintenance activities include:
  • Cleaning and Flushing Troughs under open and finger joints
  • Replacing existing joint material with new material – where the surfaces

adjacent to the joint are in good condition – this activity may require saw cutting when the new material is a preformed elastomeric compression sealer

  • Reconstructing concrete slabs and/or back-walls adjacent to joints and

installing new joint material

  • Constructing Asphalt Plug Joints on decks having asphalt overlays
  • Eliminating joints by constructing joint closures and slab extensions

31

slide-32
SLIDE 32

Joint Maintenance

  • Cleaning and Flushing Troughs under
  • pen and finger joints

32

slide-33
SLIDE 33

Joint Maintenance

  • Replacing existing joint material with

new silicone material

33

slide-34
SLIDE 34

Joint Maintenance

  • Replacing existing joint material with

new silicone material

34

slide-35
SLIDE 35

Joint Maintenance

35

  • Replacing existing joint material with new

silicone material

slide-36
SLIDE 36

Joint Maintenance

  • Replacing existing joint material with new

silicone material

36

slide-37
SLIDE 37

Joint Maintenance

  • Reconstructing concrete slabs and back-walls

adjacent to joints and installing new joint material – Preformed Elastomeric Compression Seal

37

slide-38
SLIDE 38

Joint Maintenance

  • Reconstructing concrete slabs and back-walls

adjacent to joints and installing new joint material - Preformed Elastomeric Compression Seal

38

slide-39
SLIDE 39

Joint Maintenance

  • Reconstructing concrete slabs and back-walls

adjacent to joints and installing new joint material - Preformed Elastomeric Compression Seal

39

slide-40
SLIDE 40

Joint Maintenance

  • Reconstructing concrete slabs and back-walls

adjacent to joints and installing new joint material – Preformed Elastomeric Compression Seal

40

slide-41
SLIDE 41

Joint Maintenance

  • Reconstructing concrete slabs adjacent to joints

and installing new joint material – Strip Seal

41

slide-42
SLIDE 42

Joint Maintenance

  • Reconstructing concrete slabs adjacent to joints

and installing new joint material – Strip Seal

42

slide-43
SLIDE 43

Joint Maintenance

  • Reconstructing concrete slabs adjacent to joints

and installing new joint material – Strip Seal

43

slide-44
SLIDE 44

Joint Maintenance

  • Reconstructing concrete slabs and back-walls

adjacent to joints and installing new joint material – Tooth Joint

44

slide-45
SLIDE 45

Joint Maintenance

  • Reconstructing concrete slabs and back-walls

adjacent to joints and installing new joint material – Tooth Joint

45

slide-46
SLIDE 46

Joint Maintenance

  • Reconstructing concrete slabs and back-walls

adjacent to joints and installing new joint material – Tooth Joint

46

slide-47
SLIDE 47

Joint Maintenance

  • Reconstructing concrete slabs and back-walls

adjacent to joints and installing new joint material – Tooth Joint

47

slide-48
SLIDE 48

Joint Maintenance

  • Check Points for reconstructing concrete slabs and back-walls adjacent

to joints:

  • Mark area of concrete to be removed as shown on plan details
  • Outline area with saw cut to a depth of 1”
  • Remove concrete as shown on the plan details using hand tools and

pneumatic hammers. Pneumatic hammers should have maximum weight of 30 pounds and should be worked at an angle of 45 to 60 degrees to the plane

  • f the surface being removed
  • Set and secure forms for joint – adjusting joint opening as necessary for

temperature

  • Clean area by abrasive blast cleaning
  • Place new reinforcing steel as shown on plan details and check reinforcing

steel for section loss – bars that has lost ¼ or more of their original cross sectional area shall be lapped with new bars of the same size – lap shall be 30 diameters on each side

  • Remove dust and debris from area and ensure that existing concrete is in a

saturated-surface dry condition before placing new concrete

  • Measure and record dimensions of area before placing new concrete
  • Place, consolidate, and cure new concrete

48

slide-49
SLIDE 49

Joint Maintenance

  • Example of poor construction practice when reconstructing concrete

slabs and back-walls adjacent to joints

49

slide-50
SLIDE 50

Joint Maintenance

  • Example of poor construction practice when reconstructing

concrete slabs and back-walls adjacent to joints

50

slide-51
SLIDE 51

Joint Maintenance

  • Example of poor construction practice when reconstructing

concrete slabs and back-walls adjacent to joints

51

slide-52
SLIDE 52

Joint Maintenance

  • Constructing Asphalt Plug Joints on decks having

asphalt overlays

52

slide-53
SLIDE 53

Joint Maintenance

  • Constructing Asphalt Plug Joints on decks having

asphalt overlays

53

slide-54
SLIDE 54

Joint Maintenance

  • Constructing Asphalt Plug Joints on decks having

asphalt overlays

54

slide-55
SLIDE 55

Joint Maintenance

  • The best joint maintenance is to eliminate the joint
  • Chapter 32 of the Manual of the Structure and Bridge Division contains

the following instructions to designers –

  • The designer shall investigate the feasibility of eliminating all deck expansion
  • joints. Typically, issues requiring examination include, but are not limited to,

the nature and condition of the bearings, bearing layout, adequacy of fixed bearings and corresponding piers to handle longitudinal forces, adequacy of fixed and expansion bearings to handle transverse forces, movement capability of expansion bearings that remain active, pier flexibility, structure symmetry with respect to location of fixed pier(s), the size of any remaining joints, bridge length, degree of curvature, span lengths greater than 120, etc.

  • When the elimination of all pier joints is not possible, provide deck continuity
  • ver substructure units with potentially higher relative repair costs such as

tall column piers in the water as opposed to short piers on land

  • Elimination of the existing abutment joints by using deck extensions is also

expected; however, the issues relating to the nature of the bridge and the presence of existing approach slabs to remain in place may inhibit feasibility

  • Justification for any remaining joints shall be provided via email to the

Assistant State Structure and Bridge Engineer for Maintenance and posted in IPM.

55

slide-56
SLIDE 56

Joint Maintenance

56

  • Eliminating joints by constructing joint

closures at piers

slide-57
SLIDE 57

Joint Maintenance

57

  • Eliminating joints by

constructing joint closures at piers

slide-58
SLIDE 58

Joint Maintenance

58

  • Eliminating joints by constructing joint

closures at piers

slide-59
SLIDE 59

Joint Maintenance

59

  • Eliminating joints by constructing joint

closures (slab extensions) at abutments

slide-60
SLIDE 60

Joint Maintenance

60

  • Eliminating joints by constructing joint

closures (slab extensions) at abutments

slide-61
SLIDE 61

Joint Maintenance

61

  • Eliminating joints by constructing joint

closures (slab extensions) at abutments

slide-62
SLIDE 62

Joint Maintenance

62

  • Eliminating joints by constructing joint

closures (slab extensions) at abutments

slide-63
SLIDE 63

Joint Maintenance

63

  • Eliminating joints by constructing joint

closures (slab extensions) at abutments

slide-64
SLIDE 64

Thank you for your time and attention Questions??

2013 Virginia Concrete Conference Joint Maintenance and Best Practices in Deck Joint Replacement Jeff Milton Bridge Preservation Specialist Structure and Bridge Division