2011 Half Yearly Results 25 August 2011 Forward looking statements - - PowerPoint PPT Presentation
2011 Half Yearly Results 25 August 2011 Forward looking statements - - PowerPoint PPT Presentation
2011 Half Yearly Results 25 August 2011 Forward looking statements This presentation may contain forward-looking statements and information that both represents management's current expectations or beliefs concerning future events and are
25 August 2011 | Page 1
Forward looking statements
This presentation may contain forward-looking statements and information that both represents management's current expectations or beliefs concerning future events and are subject to known and unknown risks and uncertainties. A number of factors could cause actual results, performance or events to differ materially from those expressed or implied by these forward-looking statements.
25 August 2011 | Page 2
Agenda
Introduction and highlights Simon Lockett Chim Sáo and Gajah Baru update Robin Allan Future developments update Neil Hawkings Exploration update Andrew Lodge Financial results Tony Durrant Summary Simon Lockett
25 August 2011 | Page 3
2011 Overall highlights
- Chim Sao and Gajah Baru projects on stream imminently
– Production of 60,000 boepd by year end
- 12 developments proceeding through development stages
– Building towards 100,000 boepd
- Resource additions through exploration on track to deliver 200 mmboe of
2P reserves by 2015
- Wytch Farm, Solan and Fyne acquisitions add 43 mmboe of reserves and
resources at a cost of around $5/bbl
- Financial strength positions us well
– Profits after tax of $88.5 million – Growing operating cash flows exceed capital commitments – Cash and undrawn bank facilities of $1.3 billion
25 August 2011 | Page 4
Chim Sáo and Gajah Baru update
25 August 2011 | Page 5
Chim Sáo – WHP
WHP Jacket prior to Load Out WHP Topsides onto Jacket WHP Jacket Sail Away WHP Topsides onto Jacket WHP Topsides Lift Off Barge Ensco 107 Rig & WHP
25 August 2011 | Page 6
Trading Tanker prior to Conversion Conversion of FPSO in Dry Dock Sail Away of Lewak Emas Arrival of Lewak Emas on Location
Chim Sáo – FPSO
25 August 2011 | Page 7
- FPSO is on location with mooring system,
risers and connections to the WHP installed and tested
- Safe handover of the FPSO processing
equipment from commissioning to
- perations is imminent
- Production crew familiarisation is ongoing
- First oil in tank expected 15 September
- Total costs of project within original budget
- f $800 million
Chim Sáo – production imminent
25 August 2011 | Page 8
Chim Sáo – reserves increasing
Chim Sáo
- Six production wells ready to produce
- MDS5 reservoir is significantly better than prognosed
- Additional potential in shallow MDS1 reservoir
Near field success
- N2P well intersected a 20m oil column
- Additional gross resource estimate 7 to 12 mmbo
Dua
- Dua subsea development is nearing project sanction
2000m 3060mss
Chim Sáo
West Closure Far Closure Near Closure
25 August 2011 | Page 9
Gajah Baru – Central Processing Platform (CPP)
CPP Jacket Load Out from NSB Yard (Batam) CPP Jacket Launch from Saipem S45 CPP Topsides Load Out from SM0E Yard (Batam) Up-ending of CPP Jacket by Castoro 8
25 August 2011 | Page 10
Gajah Baru – CPP topsides float-over
Completed Gajah Baru Complex CPP Topsides Float-over Operation Export Pipeline Installation Bridge Installation
25 August 2011 | Page 11
Gajah Baru – WHP, CPP
CPP from WHP Sea Aaryan Hook-up Accommodation Vessel CPP and WHP WHP from CPP CPP from Sea Aaryan
25 August 2011 | Page 12
- Project ahead of schedule
– Development drilling successfully completed in February 2011 – Jacket installed and piling completed in June 2011 – CPP topsides installed on jacket and bridge-linked to wellhead in July 2011 – Gas export pipeline installed and tested in July, dewatered and dried in August
- Production for fuel gas ready
- Gas export to start early September ahead of
contract date of 1 October
Gajah Baru – production imminent
25 August 2011 | Page 13
Future developments update
25 August 2011 | Page 14
Progress towards 100,000 boepd
Catcher Development planning underway Huntington Development drilling underway Gajah Baru Early first gas Rochelle Unitised development Chim Sáo First oil in next few weeks
2011 2012 2013-16
Fyne Operatorship acquired
East Fyne Central Fyne Appraisal target
25 August 2011 | Page 15
Chim Sáo Bream
Project Initiation Project Sanction Ready for Production
Asia North Sea
Future development portfolio
Concept Selection
Gajah Baru Catcher Solan Caledonia Rochelle Huntington Dua Cá Rồng Đo Fyne Frøy Block A Aceh Pelikan & Naga
North Sea Asia
25 August 2011 | Page 16
Huntington
- Drilling template installed
- First development well highly successful
- Work continuing on the Sevan Voyageur
FPSO upgrade project and sub-contracted modules
- Sevan’s plan is for FPSO sail-away in
April, implying June 2012 for first oil
25 August 2011 | Page 17
Rochelle
- Phase 1 field development plan approved (East area)
- Single field development area determined by DECC
- Unitised development – Premier 15% equity
- Plans for West area being integrated
– West area pipeline route survey completed (May)
- Scott tariff arrangements concluded
– Initial tie-in works completed during Scott shutdown (August)
- Subsea long lead equipment ordered
- Drilling rig contract being negotiated
- First gas targeted for 4Q 2012
Rochelle
25 August 2011 | Page 18
Natuna Sea Block A
- 2010 was a record year for Block A gas sales
– From Singapore demand of 355 bbtud, Block A sold 160 bbtud vs a DCQ of 126 bbtud
- 1H 2011, Singapore demand was 373 bbtud
with Block A supplying 154 bbtud
- Gajah Baru builds up to 130 bbtud in 2012
- In 2011 expect to approve:
– Anoa phase 4 compression expansion (2013) – Pelikan and Naga field developments (2013)
- Total sales capacity will increase to
400 bbtud
- Gajah Puteri planned for 2015
Natuna ‘A’ 2015
25 August 2011 | Page 19
Catcher
- Formal concept selection underway
- Development options
– FPSO – Fixed Platform – FSO – Subsea wells – Platform wells – Gas export/injection
- Premier’s objective is to
proceed with fast track development
Catcher Development Field Illustration
25 August 2011 | Page 20
Fyne
- In May, option exercised to become operator with a 39.9% equity stake
– Pre-development work progressed – Joint venture partners evaluating development options – Project sanction planned for early 2012 with first oil targeted for mid-2014
- Development options
– Stand-alone – FPSO – Platform – Subsea-tieback to host – Eg Anasuria
- Additional discoveries and exploration potential
provide upside opportunity – Appraisal well planned for Q4 2011 to de-risk East Fyne area – Erne exploration well planned for Q4 2011
East Fyne Central Fyne NW Fyne Appraisal target
Height above 4583ft N
1000m
25 August 2011 | Page 21
Solan
- SPA and Loan Agreement executed in May
- Premier will become the operator with a 60% equity stake
- Further engineering studies are underway
- Project now targeting 2014 for first oil
- 8
- 8500
- 8000
- 8
5
- 9000
- 9
- 9500
- 8500
- 8500
- 8
5
- 8500
- 9
- 8000
- 7500
- 8000
- 7500
- 8000
205_26a-7z 205_26a-7 205_26a-5z 205_26a-5 205_26a-3 205_26a-4 205_26a-8 205_26a-8z 205_26a-8z 205_26a-8z 205_26a-8z 205_26a-8z 205_26a-8z 205_26a-8z 205_26a-8y 205_26a-8y 205_26a-8y
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
N/G
- 9800
- 9700
- 9600
- 9500
- 9400
- 9300
- 9200
- 9100
- 9000
- 8900
- 8800
- 8700
- 8600
- 8500
- 8400
- 8300
- 8200
- 8100
- 8000
- 7900
- 7800
- 7700
- 7600
- 7500
- 7400
- 7300
Depth Producer at reservoir level (Active 8 ½” Section) Injector at reservoir level (Active 8 ½” Section) Background Map = Top Solan Depth ft TVDSS with P50 Field Outline Well Penetrations shown at Top Solan
N
1km P1 P2 8 ½” (June 2013) W1 8 ½” (June 2012) W2 P3 in Upside Case (July 2014) Location of Wellhead Cluster at Sea Bed
Producer & Injector 12 ¼” Sections at reservoir level (Cased) Injector at reservoir level (Inactive 8 ½” Section)
W1 12 ¼” (May 2012) P2 12 ¼” August 2012 P1 12 ¼” (July 2012) P1 8 ½” (May 2013) W2 (June 2014)
Main decision points for well steering or completion
- ptions
Current uncertainty in FWL across field
25 August 2011 | Page 22
Progress on other developments
Bream (Norway) Dua (Vietnam) Block A Aceh (Indonesia) Frøy (Norway) Caledonia (UK) CRD (Vietnam)
CRD-1X CRD-2X
Anomalies associated with Gas Cau sequence
25 August 2011 | Page 23
A path to 100,000 boepd
1000
Development capex (US$ million)
400 200 500 700 900 2011 2013 2012 2015 800 600 100 300 2014 120,000
Production outlook (bbls/day)
40,000 20,000 60,000 2011 2014 2012 2013 2016 100,000 80,000 2015
Future Norway Developments Future UK Developments Future Asia Developments End of Year Run Rate Huntington, Rochelle (UK) Chim Sáo, Gajah Baru (Asia) On Production
25 August 2011 | Page 24
Exploration update
25 August 2011 | Page 25
Progress towards 200 mmboe of discoveries
200 100 50 2010 2011 150 2012 2013 2014 250
Target cumulative risked additions Actual cumulative proved and probable discovered resources Actual cumulative plus possible resources
Global exploration: Forecast resource additions (mmboe)
2009
Exploration and appraisal drilling
- At least 9 wells planned for the remainder of 2011
- Discoveries at Burgman in the UK, K27 in
Pakistan and North West of Chim Sáo in Vietnam
- Grosbeak and Cá Rồng Đo appraisal wells
successfully completed
- Net estimated resource additions 20 to 30 mmboe
New ventures
- PSCs signed for exploration blocks L10A and
L10B in Kenya
- Exercised option to farm-in to the Greater Fyne
area in the UK – East Fyne appraisal well and Erne prospect to be drilled 2H 2011
- Premier pre-qualified for the Iraq 4th Exploration
round in 2012
- Actively pursing new venture opportunities in all
focus areas and themes
25 August 2011 | Page 26 Unrisked Resource Portfolio Risked Resource Portfolio
Discovered resource under appraisal 80 mmboe Leads 1,500 mmboe Prospects 450 mmboe Total 1,950 mmboe Leads 180 mmboe Prospects 120 mmboe Total 380 mmboe
- Unrisked prospective resource portfolio – 1,950 mmboe
– 450 mmboe in prospects – 1,500 mmboe in leads
- Portfolio increased from 2010
– Increased lead inventory in MEAP (Kenya) – Prospect inventory adjusted post Tuna drilling
- Risked pospective resource portfolio – 380 mmboe
– 120 mmboe in prospects – 180 mmboe in leads – Greater focus to lead maturation in 2012
- Discovered resource under appraisal – 80 mmboe
Resource portfolio
On track to deliver 200 mmboe
- f 2P reserves by 2015
Discovered resource under appraisal 80 mmboe
25 August 2011 | Page 27
Samedi 15
Norway PL378: Grosbeak UK P077: East Fyne
P1784: Typhoon 14 PL406: Gardrofa P1466: Bluebell P1212: Stingray 12 Blk 104: Jackfruit 34 6 Natuna: Biawak Besar 4 Natuna: Anoa Deep 3.5 Buton: Benteng 23 3 Aceh: Matang 18 10 K-29 P1875: Erne Badhra-7 K-30 Badhra-6 Parh
Norway PL374S: Blabaer
P1430: Cougar P1420: New York 53 P1420: Manhattan P1420: Newark K-32 Badhra South Blk 07: Blue Marlin 72 6 Blk 07: Silver Sillago 60 15 1 2 1 4 2 P1430: Rapide P1430: Bonneville Blk 07: AD Deep Aceh: Peudawa Rayeu Tuna: Singa Laut Blk 07: CRT P1559: Cornet 3 1 1 2 4 4 PL359: Luno II 21 4 P1181: Lacewing 15 2 P1430: Carnaby 10 7 11 4 17 6 2 6 1 1 2 8 <1 1 2 4 <1 <1 <1 1
Vietnam Block 12W: CS NW Vietnam Block 07/03: CRD
Leads
Total Unrisked: 1500 Total Risked :180
Prospects
Total Unrisked: 270 Total Risked: 63
Mature Prospects
Total Unrisked: 180 Total Risked: 57
Appraisal
Total: 80
Appraise Drill Evaluate
Acquire Licence Drill Decision Appraisal Approval Gate Project Extension Gate
MEAP North Sea Asia
NB: Resource estimates identified for 2011-2012 prospective drilling candidates
<10 10-25 25-50 >50 Prospect potential resource mmboe (net unrisked): Risked
Progress towards 200 mmboe of discoveries
Pre- Development
Seismic
32 6 60 10
25 August 2011 | Page 28
Exploration – Indonesia/Vietnam – Nam Con Son Basin Key prospects with Oligocene reservoirs at optimum depths
Gajah Laut Utara Belut Laut
Silver Sillago Fault Terrace CRD NE Blue Marlin AD Deep Mackerel Singa Laut Fault Terrace
Top Oligocene Structure Map
CRD
- Unique integrated
database
- New petroleum system
established
- 600 mmbo and
>1 TCF of unrisked prospective resource potential
25 August 2011 | Page 29 Silver Sillago Chim Sáo
SW NE NW SE
Top NCS Top Basement Top Cau MMU Dua
- Similar proximal access to source package
- Fault seal remains a key risk
Silver Sillago Line Chim Sáo Line
Exploration – Vietnam – Block 07/03 Chim Sáo vs Silver Sillago
CS-2X MMU Top Basement Top Cau MDS5
25 August 2011 | Page 30
- Oligocene prospectivity remains up dip from proven source kitchens
- Singa Laut /Kuda Laut
– Oligocene sandstones at 3,000 mss – Fault seal risk mitigated by anticline to the west of bounding fault (Kuda Laut) – Unrisked resource estimate 100 mmboe
Gajah Laut Utara-1
TD 4687m
Belut Laut-1
TD 4977m
Kuda Laut Singa Laut MMU L.Terumbu Arang Gabus
Exploration – Indonesia – Tuna PSC
Depth of Top Oligocene in Gajah Laut Utara
25 August 2011 | Page 31
- Premier has the regional database to
pursue amplitude supported Tertiary prospects throughout the Central North Sea
- The focus is towards basin margin
settings in structural/stratigraphic traps
- Over the next 12 months Premier will
drill at least 5 exploration wells on this play
- These wells will test a total gross
unrisked prospective resource of 100 mmbo (net 40 mmbo)
- New venture options are being actively
pursued both in the UK and Norway
Exploration – North Sea Building on the Catcher success
Carnaby East Fyne / Erne Bluebell
Eocene Turbidite Sand Fairway
Typhoon
25 August 2011 | Page 32
Appraisal – UK – Block 21/28a – Greater Fyne Area
East Fyne Appraisal
- Premier 39.9% equity
- Well planned for Q4 2011, targeting Eocene Tay Sands
- Gross prospective resource estimate 9-12-16 mmbo
Erne
- Premier equity 50%
- Well planned for Q4 2011 – ‘Catcher’ Tay play type analogue
- Gross prospective resource estimate 10-18-35 mmbo
Main Mid-Tay Chalk Upper Tay Horda
Central Fyne East Fyne
Appraisal well 21/28a-9 21/28a-9Y
East Fyne
Approx position of predicted OWC in TWT
- W. Guillemot
Erne Prospect
Chalk Upper Tay BTM
Tay amplitudes Erne Prospect
25 August 2011 | Page 33
Bluebell (P1466 ) (15/24c,15/25f)
- Premier 60% equity
- Palaeocene reservoir – Crevasse play
- Gross prospective resource estimate 9-19-31 mmboe
- Partial carry by farm-in partner
- Well planned for Q4 2011
- Valuable tieback opportunity
Exploration – UK – Bluebell
Top Forties Depth SS, CI=5 m Top Forties Lambda Rho Extraction Top Forties Lambda Rho Extraction Near Offset Lamda Rho, HC Indicator Bluebell Bluebell
Bluebell Well Location Bluebell Site Survey
Bluebell
Bluebell Well Location Bluebell
25 August 2011 | Page 34
Block 21/7b
Typhoon (21/7b)
- Premier 70% equity
- Block awarded in 2010
- Gross prospective resource estimate
– 20-27-36 mmbo (Tay reservoir)
- Risk assessment
– Moderate risk – Seismic reprocessing ongoing
- Well planned for Q2 2012
Exploration – UK – Typhoon
Typhoon
Scolty Oil discovery
Block 21/8
Typhoon Amplitude response
- n inverted data
Typhoon Prospect
25 August 2011 | Page 35
Carnaby
Exploration – UK – Carnaby
Carnaby (28/9)
- Premier 35% equity
- Gross prospective resource estimate
– 15-30-50 mmbo (Tay reservoir)
- Expected phase oil
– Gas in shallower Eocene targets (Upper Tay)
- Risk assessment
– Moderate risk at lower Tay level - oil quality – High risk at Cromarty level - reservoir presence and charge
- Acquisition of new 3D seismic data ongoing
- Well planned for Q2 2012
Varadero Carnaby Catcher N & E
Catcher Main Catcher E Carnaby Varadero
N S
Lower Tay Upper Tay
Burgman
Cromarty Depth Structure
Carnaby Prospect
Eocene ( Lower Tay) amplitude extraction
Carnaby
Burgman
Burgman
25 August 2011 | Page 36
Exploration – Norway – Luno II
Luno II (PL 359)
- Premier equity 30%
- Greater Luno is a regional high
– Focus for oil migration – Regional top seal drapes the high – Jurassic/Triassic reservoirs flank the high and, where fractured, basement is also a reservoir – ~2,000 mmboe discovered to date
- Key play risks
– Reservoir presence on the margins of the high – Lateral seal
- Aldous Major South discovery
– Proves eastern margin of the basement high – Reserve estimate ~1,200 mmbo
- Luno II
– Southwest margin prospect down dip from cemented basement- up dip from proven source kitchen – Mesozoic sand presence interpreted from seismic and local well data
- Gross prospective resource estimate
– 45-148-286 mmbo (Operator estimate)
- Well planned for Q2 2012
Aldous/ Avaldnes
PL 359
BCU Time Map
C.I. 100 ms
Luno/Apollo Ragnarrock
NE Luno II Prospect
BCU Jurassic Triassic
SW 10km
Luno II Prospect
25 August 2011 | Page 37
Asia
2011 2012 Q3 Q4 Q1 Q2
Vietnam 104/109-05 Qua Mit Vang (Jackfruit) Buton Benteng-1 Natuna Sea Block A Anoa Deep Biawak Besar Block A Aceh Matang
North Sea
Norway PL406 Gardrofa PL359 Luno II UK P1466 Bluebell P077 East Fyne P1430 Carnaby P1212 / P1771 Stingray Block 21/29d Erne P1784 Typhoon P1557 West Orkney
Middle East & Pakistan
Pakistan Kadanwari K-29 K-30 Bhit-Badhra Badhra-6 Parh Kenya Blocks 10A & 10B 2D & 3D Seismic
Exploration drilling Q3 2011 to Q2 2012
- ~ 300 mmboe
gross unrisked resource
- 2011 full year
exploration expenditure ~ $250 million pre tax 12 to 15 exploration and appraisal wells planned in 2012
Contingent Wells Firm Wells: Rig Contracted Firm Wells: Rig TBC Seismic Programme All well timings are subject to revision for operational reasons Aqua Marine Driller W Callisto Antareja-8 W Callisto Bredford Dolphin Sedco 704 Sedco 704 WilPhoenix
25 August 2011 | Page 38
Financial results
25 August 2011 | Page 39
Production update
1H 2011
- Steady performance in Pakistan
- Anoa field in Indonesia continues to
respond well to Singapore demand
- Reduced facility up-time in UK North Sea
Outlook
- Recovery in UK performance
- New fields in Asia drive 60 kboepd year-
end run rate
- 2012 average of around 60 to 65 kboepd
- 75 kboepd run rate post Huntington
80
Production (working interest) (kboepd net)
20 30 50 70 2010 A 2011 E 1H 2011 2H 2011 E 2012 E 60 40 10
Mid Point Estimate End of Period Run rate
25 August 2011 | Page 40
Revenue and income statement
6 months to 30 June 2010 Average gas pricing ($/mcf) 2011 2010 Singapore $18.5 $13.8 Pakistan $3.7 $3.3 Average Brent oil price was $111.1/bbl (2010: $77.3/bbl) Operating costs per barrel ($/bbl) 2011 2010 UK $34.2 $24.7 Indonesia $9.6 $7.1 Pakistan $2.1 $1.6 Group $14.0 $12.9 Tax credit arises due to revaluation of UK tax allowance pool following UK government tax changes Highlights 6 months to 30 June 2011 Working Interest Production (kboepd) Entitlement Interest Production (kboepd) Realised oil price ($/bbl) Realised gas price ($/mcf) Sales and other operating revenues Cost of sales Gross profit Exploration/New Business General and administration costs Operating profit Financial Items Profit before taxation Taxation credit/(charge) Profit after tax 46.6 42.6 78.1 5.8 $m 367 (189) 178 (46) (8) 124 (12) 112 (50) 62 36.9 33.8 109.7 8.3 $m 342 (200) 142 (91) (9) 42 (9) 33 56 89 2011 sales revenues include realised hedging loss on oil and gas production of $58.2 million (pre-tax)
25 August 2011 | Page 41
Overseas UK PRT CT Prior period revisions UK deferred tax credits Tax credit for the period 6 months to 30 June 2010 $m
Group taxation position
27.8 17.7 nil (18.4) 27.1 22.5 49.6 Recognised previously as deferred tax asset Currently unrecognised Tax allowances at 1 Jan 2011 2011 estimated net additions Estimated end 2011 position UK Tax Allowance Position $m 972 140 1,112 238 1,350
- Additional deferred tax credits mainly due to change in UK tax rate
- UK allowances of $140 million not yet recorded
- UK cash corporate taxes not anticipated until at least 2015
6 months to 30 June 2011 $m 46.0 30.4 nil (0.6) 75.8 (131.8) (56.0)
25 August 2011 | Page 42
Cash flow
Cash flow from operations Taxation Operating cash flow Capital expenditure (Acquisitions)/disposals, net Finance and other charges, net Pre-licence expenditure Net cash flow 6 months to 30 June 2010 $m
1H 2011 Development Exploration
Estimated capex split ($m)
178 119 297 1H 2011 2010 Cash Net Debt
Balance sheet ($m)
300 406 902 483 582 804 Undrawn facilities
273 (51) 222 (212) 20 (27) (11) (8) 6 months to 30 June 2011 $m
1H 2010 142 70 212
246 (4) 242 (297) (87) (24) (10) (176)
Outlook
- Forecast full-year 2011 spend – $500m (development) and $250m(exploration)
- Net debt of around $600m (gearing of 32%)
- Net debt peak of around $750m on forward curve
31 Dec
25 August 2011 | Page 43
Summary
25 August 2011 | Page 44
- Asian development project success
- Stronger North Sea production performance anticipated in 2H
- Good progress on pipeline of development projects
- Exploration on target to deliver 200 mmboe of discoveries
- Acquisition track record at reasonable prices
- Strong first half year financial results and balance sheet position
Delivering on strategy
25 August 2011 | Page 45