Why Use A DES ESCO ? High Energy Bills Old Equipment is Broken - - PowerPoint PPT Presentation

why use a des esco
SMART_READER_LITE
LIVE PREVIEW

Why Use A DES ESCO ? High Energy Bills Old Equipment is Broken - - PowerPoint PPT Presentation

5/2/2016 Why Use A DES ESCO ? High Energy Bills Old Equipment is Broken Bond Levy Passed Free Grant Money / Utility Incentive Money Going Green Reducing Carbon Footprint Desire to use specific equipment or


slide-1
SLIDE 1
slide-2
SLIDE 2

5/2/2016 1

Why Use A DES ESCO ?

  • High Energy Bills
  • Old Equipment is Broken
  • Bond Levy Passed
  • Free Grant Money / Utility Incentive Money
  • Going “Green” – Reducing Carbon Footprint
  • Desire to use specific equipment or contractor

for installing large projects (avoid low bid issues that often arise)

2

Benefits of A DES ESCO?

  • DES Screening and Oversight of ESCOs
  • Guaranteed Energy Savings
  • Guaranteed Maximum Costs
  • Guaranteed Building Comfort
  • Contracting/Subcontractor Management
  • RFP and Procurement
  • Construction Management
  • Commissioning
  • Open Book Accounting

3

slide-3
SLIDE 3

5/2/2016 2

Who are the DES Approved ESCOs?

4

  • Abacus (Willdan Energy Solutions)
  • Ameresco
  • Apollo Solutions Group
  • Integrity
  • Johnson Controls
  • MacDonald‐Miller Facility Solutions
  • McKinstry
  • Schneider Electric
  • Siemens Industry
  • Sunset Air
  • Trane
  • University Mechanical Contractors

ESPC Behind the Scenes

1) Starts with a phone call 2) Proceeds to an Energy Study

  • We look at all building systems
  • Address “issues” in the building
  • Occupant complaints
  • Energy modeling
  • Review all incentive and grant opportunities
  • Open dialogue and feedback between the owner

and the ESCO to finalize scope of work

5

slide-4
SLIDE 4

5/2/2016 3

ESPC Behind the Scenes (cont’d)

3) DES Contracts are issued (IAA / ESPC) 4) Construction begins

  • Engineering/Design
  • RFP’s
  • Subcontractor Selection
  • Construction ‐ Progress Meetings
  • Substantial Completion
  • Closeout – Training – O&M Manuals/Documentation
  • Measure Energy Savings

6

Project #1: Clallam Transit Center

  • Original air conditioner was failing
  • Owner had difficulty getting good service from

local contractors

  • The utility company hired us for a free energy

audit

  • We replaced the old 30‐ton air conditioner

with a heat pump (heater & air conditioner)

  • We fixed the controls, including problems with

the controls the city did not know they had

7

slide-5
SLIDE 5

5/2/2016 4

Project #1: Clallam Transit Center

8

Project #1: Clallam Transit Center

9

slide-6
SLIDE 6

5/2/2016 5

Project #1: Clallam Transit Center

  • Project Summary
  • Guaranteed Construction Costs
  • $87k
  • Guaranteed Energy Savings
  • 30,000 kWh
  • $1,700 at current utility rates
  • Project Scope: New HVAC, Fix existing controls

(Retro‐Commissioning)

10

Project #2: William Shore Pool

  • Original equipment was under‐sized. The

facility could not heat the water to a proper temperature

  • Occupant complaints
  • DES assisted the Owner to find a qualified

ESCO that specialized in indoor pools

11

slide-7
SLIDE 7

5/2/2016 6

Project #2: William Shore Pool

12

Pre-Upgrade Energy Use: (kWh / month) 1st Year After- Upgrade Actual Utility Meter Monthly Use (kWh / month) 1st Year Actual Measured Savings (kWh / month) 2nd Year After- Upgrade Actual Utility Meter Monthly Use (kWh / month) 2nd Year Actual Measured Savings (kWh / month) Jan 198,571 96,920 101,651 86,520 112,051 Feb 195,524 118,560 76,964 65,760 129,764 Mar 174,191 90,360 83,831 59,280 114,911 Apr 222,951 66,200 156,751 52,440 170,511 May 178,762 77,520 101,242 67,000 111,762 Jun 151,335 53,480 97,855 46,360 104,975 Jul 162,001 57,760 104,241 41,120 120,881 Aug 136,098 59,640 76,458 53,600 82,498 Sep 133,050 51,160 81,890 45,880 87,170 Oct 120,860 75,560 45,300 41,200 79,660 Nov 151,335 113,320 38,015 55,480 95,855 Dec 210,761 92,840 117,921 72,360 138,401

TOTAL 2,035,440 953,320 1,082,120 687,000 1,348,440 Measured Energy Savings

Project #2: William Shore Pool

  • Project Summary
  • Guaranteed Construction Costs
  • $859k
  • Guaranteed Energy Savings
  • 848,000 kWh
  • $44,000 at current utility rates
  • Project Scope: New HVAC, Controls, Heat

Recovery, Air Source Heat Pump, Boiler

13

slide-8
SLIDE 8

5/2/2016 7

Project #3: King County Aquatic Center

  • Project was driven from comfort issues and
  • ld equipment
  • King County hired a Professional Engineer to

find a solution

  • ESCO proposed alternate solution that saved

energy compared to the Professional Engineer’s original solution

  • Actual construction costs exceeded ESCO’s

guaranteed costs, so ESCO paid the overage

14

Project #3: King County Aquatic Center

15

slide-9
SLIDE 9

5/2/2016 8

Project #3: King County Aquatic Center

  • Project Summary
  • Guaranteed Construction Costs
  • $2.4m
  • Guaranteed Energy Savings
  • 745,677 kWh
  • 37,384 Therms
  • $88,000 at Current Utility Rates
  • Project Scope: Solar PV Installed, HVAC, Controls,

Lighting, Boilers, Increased Air Flow, Heat Recovery

16

Project #4: Camas Police & Library

  • Project was driven from comfort issues and
  • ld equipment failures
  • Occupants were cold in the winter and hot in

the summer

  • Upgrades installed while building occupied 24

hours a day 7 days a week

  • Now half of heating remains off overnights
  • Exceed guaranteed energy savings

17

slide-10
SLIDE 10

5/2/2016 9

Project #4: Camas Police & Library

18

Project #4: Camas Police & Library

  • Project Summary
  • Guaranteed Construction Costs
  • $377k
  • Guaranteed Energy Saving
  • 205,243 kWh
  • 8,045 Therms
  • $17,000 at Current Utility Rates
  • Police Project Scope: New HVAC, New Controls
  • Library Project Scope: Optimizing Existing Controls

19

slide-11
SLIDE 11

5/2/2016 10

Project #5: Camas LED Street Lights

  • The City desired state of the art LED street

lighting

  • The City was already comfortable with the

DES/ESCO process from the Police/Library project

  • 3,300 New LED Lights currently being installed
  • Final construction costs 15% under budget.

This money goes back to the City!

20

Project #5: Camas LED Street Lights

21

slide-12
SLIDE 12

5/2/2016 11

Project #5: Camas LED Street Lights

  • Project Summary
  • Guaranteed Construction Costs
  • $2.1m
  • Guaranteed Energy Savings
  • 1,161,797 kWh
  • $91,000 at Current Utility Rates
  • Project Scope: Install and Replace Cobraheads,

Post Tops, ACORNs, Floods Street Lights

22

Project #6: Camas Waste Water Plant

  • The waste water treatment plant controls

never worked from day #1

  • This problem did not effect the water quality
  • r water permit issues but did waste energy
  • We helped the owner find a new qualified

controls contractor that they will continue to use in the future

  • We got the controls to work!

23

slide-13
SLIDE 13

5/2/2016 12

Project #6: Camas Waste Water Plant

24

Project #6: Camas Waste Water Plant

  • Project Summary
  • Guaranteed Construction Costs
  • $400k
  • Guaranteed Energy Saving
  • 387,013 kWh
  • $22,000 at current utility rates
  • Project Scope: VSDs, Fix Existing Aeration

Controls, Install New UV Controls

25

slide-14
SLIDE 14

5/2/2016 13

Project #7: Yakima School District

  • Project Summary (Phase 1)
  • Guaranteed Construction Costs
  • $5.5m
  • Guaranteed Energy Saving
  • 1,139,000 kWh
  • 767,100 therms
  • $117,000 at current utility rates
  • Project Scope: 4 Schools ‐ New HVAC, Controls,

Lighting

26

Project #8: Yakima School District

  • Project Summary (Phase 2)
  • Guaranteed Construction Costs
  • $3.0m
  • Guaranteed Energy Saving
  • 2,500,000 kWh
  • 136,000 therms
  • $263,000 at current utility rates
  • Project Scope: 10 Schools – Lighting, Boilers,

Cooling Towers

27

slide-15
SLIDE 15

5/2/2016 14

Project #9: Yakima School District

  • Project Summary (Phase 3)
  • Guaranteed Construction Costs
  • $1.2m
  • Guaranteed Energy Saving
  • 131,000 kWh
  • 4,900 therms
  • $10,735 at current utility rates
  • Project Scope: 12 Schools – Walk In Coolers and

Freezers, New Boilers, HVAC equipment

28 29

slide-16
SLIDE 16

5/2/2016 15

For More Information

  • Abacus / Willdan Contacts
  • Rich Davis (Senior Project Development Engineer)
  • 503‐936‐7163
  • rich.davis@willdan.com
  • Art Vertner (VP Project Development)
  • 206‐659‐3890
  • avertner@willdan.com
  • Pat Stephens (VP Project Development)
  • 503‐593‐9493
  • pstephens@willdan.com

30