Why Use A DES ESCO ? High Energy Bills Old Equipment is Broken - - PowerPoint PPT Presentation
Why Use A DES ESCO ? High Energy Bills Old Equipment is Broken - - PowerPoint PPT Presentation
5/2/2016 Why Use A DES ESCO ? High Energy Bills Old Equipment is Broken Bond Levy Passed Free Grant Money / Utility Incentive Money Going Green Reducing Carbon Footprint Desire to use specific equipment or
5/2/2016 1
Why Use A DES ESCO ?
- High Energy Bills
- Old Equipment is Broken
- Bond Levy Passed
- Free Grant Money / Utility Incentive Money
- Going “Green” – Reducing Carbon Footprint
- Desire to use specific equipment or contractor
for installing large projects (avoid low bid issues that often arise)
2
Benefits of A DES ESCO?
- DES Screening and Oversight of ESCOs
- Guaranteed Energy Savings
- Guaranteed Maximum Costs
- Guaranteed Building Comfort
- Contracting/Subcontractor Management
- RFP and Procurement
- Construction Management
- Commissioning
- Open Book Accounting
3
5/2/2016 2
Who are the DES Approved ESCOs?
4
- Abacus (Willdan Energy Solutions)
- Ameresco
- Apollo Solutions Group
- Integrity
- Johnson Controls
- MacDonald‐Miller Facility Solutions
- McKinstry
- Schneider Electric
- Siemens Industry
- Sunset Air
- Trane
- University Mechanical Contractors
ESPC Behind the Scenes
1) Starts with a phone call 2) Proceeds to an Energy Study
- We look at all building systems
- Address “issues” in the building
- Occupant complaints
- Energy modeling
- Review all incentive and grant opportunities
- Open dialogue and feedback between the owner
and the ESCO to finalize scope of work
5
5/2/2016 3
ESPC Behind the Scenes (cont’d)
3) DES Contracts are issued (IAA / ESPC) 4) Construction begins
- Engineering/Design
- RFP’s
- Subcontractor Selection
- Construction ‐ Progress Meetings
- Substantial Completion
- Closeout – Training – O&M Manuals/Documentation
- Measure Energy Savings
6
Project #1: Clallam Transit Center
- Original air conditioner was failing
- Owner had difficulty getting good service from
local contractors
- The utility company hired us for a free energy
audit
- We replaced the old 30‐ton air conditioner
with a heat pump (heater & air conditioner)
- We fixed the controls, including problems with
the controls the city did not know they had
7
5/2/2016 4
Project #1: Clallam Transit Center
8
Project #1: Clallam Transit Center
9
5/2/2016 5
Project #1: Clallam Transit Center
- Project Summary
- Guaranteed Construction Costs
- $87k
- Guaranteed Energy Savings
- 30,000 kWh
- $1,700 at current utility rates
- Project Scope: New HVAC, Fix existing controls
(Retro‐Commissioning)
10
Project #2: William Shore Pool
- Original equipment was under‐sized. The
facility could not heat the water to a proper temperature
- Occupant complaints
- DES assisted the Owner to find a qualified
ESCO that specialized in indoor pools
11
5/2/2016 6
Project #2: William Shore Pool
12
Pre-Upgrade Energy Use: (kWh / month) 1st Year After- Upgrade Actual Utility Meter Monthly Use (kWh / month) 1st Year Actual Measured Savings (kWh / month) 2nd Year After- Upgrade Actual Utility Meter Monthly Use (kWh / month) 2nd Year Actual Measured Savings (kWh / month) Jan 198,571 96,920 101,651 86,520 112,051 Feb 195,524 118,560 76,964 65,760 129,764 Mar 174,191 90,360 83,831 59,280 114,911 Apr 222,951 66,200 156,751 52,440 170,511 May 178,762 77,520 101,242 67,000 111,762 Jun 151,335 53,480 97,855 46,360 104,975 Jul 162,001 57,760 104,241 41,120 120,881 Aug 136,098 59,640 76,458 53,600 82,498 Sep 133,050 51,160 81,890 45,880 87,170 Oct 120,860 75,560 45,300 41,200 79,660 Nov 151,335 113,320 38,015 55,480 95,855 Dec 210,761 92,840 117,921 72,360 138,401
TOTAL 2,035,440 953,320 1,082,120 687,000 1,348,440 Measured Energy Savings
Project #2: William Shore Pool
- Project Summary
- Guaranteed Construction Costs
- $859k
- Guaranteed Energy Savings
- 848,000 kWh
- $44,000 at current utility rates
- Project Scope: New HVAC, Controls, Heat
Recovery, Air Source Heat Pump, Boiler
13
5/2/2016 7
Project #3: King County Aquatic Center
- Project was driven from comfort issues and
- ld equipment
- King County hired a Professional Engineer to
find a solution
- ESCO proposed alternate solution that saved
energy compared to the Professional Engineer’s original solution
- Actual construction costs exceeded ESCO’s
guaranteed costs, so ESCO paid the overage
14
Project #3: King County Aquatic Center
15
5/2/2016 8
Project #3: King County Aquatic Center
- Project Summary
- Guaranteed Construction Costs
- $2.4m
- Guaranteed Energy Savings
- 745,677 kWh
- 37,384 Therms
- $88,000 at Current Utility Rates
- Project Scope: Solar PV Installed, HVAC, Controls,
Lighting, Boilers, Increased Air Flow, Heat Recovery
16
Project #4: Camas Police & Library
- Project was driven from comfort issues and
- ld equipment failures
- Occupants were cold in the winter and hot in
the summer
- Upgrades installed while building occupied 24
hours a day 7 days a week
- Now half of heating remains off overnights
- Exceed guaranteed energy savings
17
5/2/2016 9
Project #4: Camas Police & Library
18
Project #4: Camas Police & Library
- Project Summary
- Guaranteed Construction Costs
- $377k
- Guaranteed Energy Saving
- 205,243 kWh
- 8,045 Therms
- $17,000 at Current Utility Rates
- Police Project Scope: New HVAC, New Controls
- Library Project Scope: Optimizing Existing Controls
19
5/2/2016 10
Project #5: Camas LED Street Lights
- The City desired state of the art LED street
lighting
- The City was already comfortable with the
DES/ESCO process from the Police/Library project
- 3,300 New LED Lights currently being installed
- Final construction costs 15% under budget.
This money goes back to the City!
20
Project #5: Camas LED Street Lights
21
5/2/2016 11
Project #5: Camas LED Street Lights
- Project Summary
- Guaranteed Construction Costs
- $2.1m
- Guaranteed Energy Savings
- 1,161,797 kWh
- $91,000 at Current Utility Rates
- Project Scope: Install and Replace Cobraheads,
Post Tops, ACORNs, Floods Street Lights
22
Project #6: Camas Waste Water Plant
- The waste water treatment plant controls
never worked from day #1
- This problem did not effect the water quality
- r water permit issues but did waste energy
- We helped the owner find a new qualified
controls contractor that they will continue to use in the future
- We got the controls to work!
23
5/2/2016 12
Project #6: Camas Waste Water Plant
24
Project #6: Camas Waste Water Plant
- Project Summary
- Guaranteed Construction Costs
- $400k
- Guaranteed Energy Saving
- 387,013 kWh
- $22,000 at current utility rates
- Project Scope: VSDs, Fix Existing Aeration
Controls, Install New UV Controls
25
5/2/2016 13
Project #7: Yakima School District
- Project Summary (Phase 1)
- Guaranteed Construction Costs
- $5.5m
- Guaranteed Energy Saving
- 1,139,000 kWh
- 767,100 therms
- $117,000 at current utility rates
- Project Scope: 4 Schools ‐ New HVAC, Controls,
Lighting
26
Project #8: Yakima School District
- Project Summary (Phase 2)
- Guaranteed Construction Costs
- $3.0m
- Guaranteed Energy Saving
- 2,500,000 kWh
- 136,000 therms
- $263,000 at current utility rates
- Project Scope: 10 Schools – Lighting, Boilers,
Cooling Towers
27
5/2/2016 14
Project #9: Yakima School District
- Project Summary (Phase 3)
- Guaranteed Construction Costs
- $1.2m
- Guaranteed Energy Saving
- 131,000 kWh
- 4,900 therms
- $10,735 at current utility rates
- Project Scope: 12 Schools – Walk In Coolers and
Freezers, New Boilers, HVAC equipment
28 29
5/2/2016 15
For More Information
- Abacus / Willdan Contacts
- Rich Davis (Senior Project Development Engineer)
- 503‐936‐7163
- rich.davis@willdan.com
- Art Vertner (VP Project Development)
- 206‐659‐3890
- avertner@willdan.com
- Pat Stephens (VP Project Development)
- 503‐593‐9493
- pstephens@willdan.com
30