what is a grid scale
play

What is a grid-scale battery energy storage system (BESS) best - PowerPoint PPT Presentation

16 August 2017 South Australias electricity transmission specialist What is a grid-scale battery energy storage system (BESS) best used for in SA? Electric Energy Society of Australia Hugo Klingenberg Senior Manager Network Development


  1. 16 August 2017 South Australia’s electricity transmission specialist What is a grid-scale battery energy storage system (BESS) best used for in SA? Electric Energy Society of Australia Hugo Klingenberg Senior Manager Network Development electranet.com.au

  2. About ElectraNet > Principal Transmission Network Service Provider (TNSP) for South Australia > Owns and manages the SA regulated high-voltage electricity transmission network, and operates in Australia’s National Electricity Market (NEM) > 5,600 circuit kilometres of transmission line > Where is the Yorke Peninsula? 2 PUBLIC Distribution: Energy Networks 2016 Security Classification: Public

  3. Outline > Context and background > What is grid-scale BESS best used for in the South Australian Electricity System? – Not energy security – But rather system security > Broad range of services & benefits (Market services, e.g. arbitrage or Caps, USE reduction, capital deferral, network support, etc.) with the business case being very application specific > ESCRI case study > Discussion / questions 3 Security Classification & Distribution Security Classification: Public

  4. South Australia renewable energy snapshot SA has one of the highest interconnected system levels of intermittent renewable energy penetration in the world (about 41% of annual energy) Wind capacity Maximum demand 1500 MW 3400 MW Rooftop solar Average demand capacity 700 MW 1500 MW Minimum demand 800 MW and No coal fired decreasing generation Security Classification & Distribution Security Classification: Public

  5. Renewable energy integration - intermittency New challenges are emerging from the combination of high levels of intermittent generation and a relatively isolated and weakly interconnected system Intermittent generation capacity relative to Interconnector import capacity demand (MW) relative to peak demand (%) 3500 Maximum demand 3000 3100 MW Denmark 83 2500 2000 South Australia 30 Average demand 1500 1500 MW 1000 0 50 100 Minimum demand 800 MW 500 International experience shows that 0 stronger interconnection is needed to Wind Solar support increasingly high levels of Wind plus solar generation capacity is… intermittent generation and to support • 145% of average demand energy transformation • 275% of minimum demand 5 Security Classification: Public Security Classification & Distribution

  6. System security implications - inertia New measures are required to manage emerging system security challenges Changes in South Australian system inertia > In August 2016, AEMO reported growing SA exposure to high rate of change of frequency (RoCoF) > On 12 October, the SA Government introduced a 3 Hz/s RoCoF limit to protect against the non-credible loss of the Heywood Interconnector – the resulting Heywood Interconnector limit has bound about 20% of the time > Subsequently AEMO introduced new system strength measures for SA Source: AEMO > AEMC Future Power System Security work program is underway, including a number of Rule change AEMC – Australian Energy Market proposals Commission 6 Security Classification & Distribution Security Classification: Public

  7. Aspects of an energy only market > Energy – Wholesale market – Cap trading and other instruments > Ancillary Services > The challenge of energy security 7 Security Classification & Distribution Security Classification: Public

  8. The challenge of intermittent generation Wind and solar PV provide minimal support to SA for 15% of the time 8 Security Classification & Distribution Security Classification: Public Security Classification: Public

  9. Batteries and energy security Many batteries required to provide energy security > Assumptions: > Battery assumptions: – – Wind still night (12 hours) Batteries charged at 50% at start – – SA Government battery – 129 MWh Average state demand (1,500 MW) – – Residential battery – 10 kWh Imports from Victoria at 650 MW > How many batteries do we need? Type of battery Utility scale Residential Scenario 1 > 150 None Scenario 2 > 80 500,000 9 Security Classification & Distribution Security Classification: Public Security Classification: Public

  10. Batteries and energy security Batteries are limited in providing energy security, e.g. 8-9 Feb 2017 > Energy providers: – Fast start generators – Pumped Hydro Energy Storage – Transmission interconnectors Source: AEC article by Duncan MacKinnon, 16 July 2017 10 Security Classification & Distribution Security Classification: Public Security Classification: Public

  11. Ancillary services needs Ancillary services required in an “energy only” market for a viable electricity system • Associated with fault • Steady operation during levels and short normal operation and circuit ratios during disturbances • To operate the • Limits rapid rate of system securely and change of system ensure safe frequency (RoCoF) System protection systems Inertia • Required for fault Strength ride through and recovery from faults Frequency Voltage Control Control • Balancing load and generation • Stable operation during • Following a frequency normal conditions disturbance, control • Assist in fault ride required in different through and recovery timescales (<1 sec, up to during disturbances 60 sec,1 to 5 min, >5 min) 11 Security Classification & Distribution Security Classification: Public

  12. Ancillary services provided by? Various technologies can participate in providing the range of required services • Synchronous • Synchronous generators generators • Synchronous condensers • Synchronous • Synthetic inertia sources (e.g. condensers grid scale batteries, VSC HVDC • VSC HVDC / grid links, new wind farms with scale batteries controls) System (limited) Inertia Strength Voltage Frequency • Generators • Inertial response: Synchronous Control Control • Synchronous generators & synchronous condensers (arrest RoCoF) condensers • Batteries and other storage • SVCs/STATCONs • HVDC links • Capacitors/reactors • New wind farms with controls • Batteries and • Load shedding storage • Load shedding 12 Security Classification & Distribution Security Classification: Public

  13. Rate of change of frequency (RoCoF) • Following an unexpected loss of generation/ load the resulting imbalance of supply and demand causes system frequency to fall/ rise • If RoCoF is too high it could result in cascading trips of load or generation and emergency control schemes may not prevent system collapse 13 Security Classification & Distribution Security Classification: Public

  14. Frequency - separation event Typical frequency response: Arresting, stabilisation and recovery 14 Security Classification & Distribution Security Classification: Public

  15. Stabilisation and recovery Existing arrangements (governor action and FCAS) can cater for most events > Governor action > Contingency FCAS > Regulation FCAS > Aggregated distributed energy resources (DER) FCAS: Frequency control ancillary service 15 Security Classification & Distribution Security Classification: Public

  16. Arresting frequency A combination of inertia and FFR providers will be required in future Fast Frequency Response (FFR) > Inertial response – Synchronous generators – Synchronous condensers > Grid-scale battery storage, Murraylink, new wind farm controls > SPS / Demand response > Under frequency load shedding 16 Security Classification & Distribution Security Classification: Public

  17. Alternative Inertia and FFR characteristics to meet minimum 3 Hz/s RoCoF standard 17 Security Classification & Distribution Security Classification: Public

  18. Trade-off between FFR MW and system inertia requirements for different FFR response times to meet minimum 3 Hz/s RoCoF requirement Example 1: Example 2: Example 3: Example 4: 250 ms Faster Slower Inertia only response response response FFR response 250 150 350 N/A Time (ms) 4,000 – 4,500 4,000 – 4,500 4,500 – 5,000 5,000 – 5,500 Inertia (MWs) Inertia increase from example 1 N/A 0 500 1,000 (MWs) 300 – 350 FFR required (MW) 200 - 250 250 - 300 N/A FFR reduction from N/A ~100 ~50 300 - 350 example 1 (MW) 18 Security Classification & Distribution Security Classification: Public

  19. ESCRI case study 19 PUBLIC Distribution: Energy Networks 2016 Security Classification: Public

  20. ESCRI – Phase 1 > Energy Storage for Commercial Renewable Integration in South Australia > An Australian Renewable Energy Agency (ARENA) funded project that started out to investigate the business case for transmission grid-scale (5 – 30 MW) storage in South Australia 20 PUBLIC Distribution: Energy Networks 2016 Security Classification: Public

  21. ESCRI Phase 1 – Business Case Phase 2 – Project Delivery • • Regulatory environment Statutory approvals • • Initial siting Formal procurement • • Functional specification Finance raising • • Capital estimating Detailed design • • Technology selection Construction • • Commercial framework Commercial contracts • • Market impact & value Operation of asset 21 PUBLIC Distribution: Energy Networks 2016 Security Classification: Public

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend