SLIDE 1
Welcome! January 29, 2016 Quarterly Meeting Jacquie Vargas - - PowerPoint PPT Presentation
Welcome! January 29, 2016 Quarterly Meeting Jacquie Vargas - - PowerPoint PPT Presentation
Welcome! January 29, 2016 Quarterly Meeting Jacquie Vargas Building Coordinator Program Director, Communications Manager Facilities Services E-mail: jmvarga5@Central.UH.EDU INTRODUCTION AVP / AVC F ACILITIE S Jacquie Vargas Communications
SLIDE 2
SLIDE 3
AVP / AVC F ACILITIE S
David Oliver
Associate Vice Chancellor/Associate Vice President Facilities/Construction Management E-mail: jdoliver@uh.edu
SLIDE 4
F ACILITIE S/ CONSTRUCTION MANAGE ME NT
SLIDE 5
OUTAGE S UPDATE
Mike Wheeler
- Sr. Project Manager, FMP,
LEED A.P. Facilities Services Email: mdwheel2@Central.UH.EDU
Karl Keilbach
Supvr, Electrical Facilities Operation and Maintenance Facilities Services Email: kkeilbac@Central.UH.EDU
SLIDE 6
2015 WINTE R OUTAGE A SUCCE SS, ALL MAJOR ITE MS WE RE COMPLE TE D.
- The four remaining item on the Hartford Steam Boiler (HSB) dated July 14, 2014,
were corrected.
Repair several overhead conductors and grounding cables Replace three (3) transformers in Engineer 1
- Cougar Sub station.
Preventative Maintenance (PM) and tested all yard equipment Demo & remove lighting in Sub station yard.
- Support for FP&C Projects.
STL & Fleming 15KV ATS replacement MREB electrical utilizes tie in for electrical service to building Kenmore Electric demo abandon sub feeder 4 in tunnel
SLIDE 7
2015 WINTE R OUTAGE A SUCCE SS, ALL MAJOR ITE MS WE RE COMPLE TE D.
- Multiple buildings
PM transformer vault and 480 switchgear
- Investigation the cause of the sub feeder 1 failure
Cause was found and corrective actions are being planned
- Work was completed, campus power was restored as scheduled
SLIDE 8
2015 WINTE R OUTAGE A SUCCE SS, ALL MAJOR ITE MS WE RE COMPLE TE D.
- Moving forward
- Items were discovered during outage that will require additional work
- We will need to prepare a scope of work and schedule the repairs
- Some generators did not perform well
- We will need to prepare a scope of work and schedule the repairs
- Facilities Services will be reaching out to the affected building once scope of
work is finalized to schedule corrections.
SLIDE 9
2016 WINTE R OUTAGE
- The program continues
- The Preventive Maintenance (PM) program has proven to be a success and it is planned to
continue.
- Communication with campus, through Building Coordinators
program to get the word out in advance
- As we make improvements to electrical system on campus we plan to
be able to isolate the outages, if possible, to minimize service interruptions during PM’s
SLIDE 10
KE Y ACCE SS/ SE CURITY
Ron Harris
Mgr., Electronic Access Control Department Public Safety E-mail: rwharris@uh.edu
Malcom Davis
Asst VC/VP, Public Safety Security DPS Administration E-mail: mdavis@uh.edu
SLIDE 11
DOOR PRIZE ! And the winner is…
SLIDE 12