we m re for m pr og r a m
play

WE M Re for m Pr og r a m L imit Advic e Re q uire me nts - PowerPoint PPT Presentation

WE M Re for m Pr og r a m L imit Advic e Re q uire me nts WRIG 1 October 2020 1. Limit Advice Overview Ag e nda 2. Limit Advice Requirements: Overview Thermal Limit Advice Format, form, manner and timeframe


  1. WE M Re for m Pr og r a m L imit Advic e Re q uire me nts WRIG – 1 October 2020

  2. 1. Limit Advice Overview Ag e nda 2. Limit Advice Requirements: Overview • Thermal Limit Advice • Format, form, manner and timeframe • Non-Thermal Limit Advice • Format, form, manner and timeframe • Review • General requirements • Publication • General review & request for updated Limit Advice • Retirement • WRIG 01/10/2020 Limit Advice Requirements 12/10/2020 2

  3. L imit Advic e Ove rvie w WRIG 01/10/2020 Limit Advice Requirements 12/10/2020 3

  4. WEM Rules 2.27A.2: L imit Advic e Information to be provided to AEMO by a Network Operator in respect to limitations of, or relating to, it Network (“Limit t Advice ce”) includes: (a) Limit Equations in respect of Network Limits, excluding Limit Equations for Essential System Services or, if, in respect of a particular Network element, a mathematical expression is not appropriate, the Network Overview Limit for that particular Network element; (b) Limit Advice Inputs; (c) Supporting information and data specified in WEM Procedure referred to in clause 2.27A.10 (A). WRIG 01/10/2020 Limit Advice Requirements 12/10/2020 4

  5. L imit Advic e Re q uire me nts WRIG 01/10/2020 Limit Advice Requirements 12/10/2020 5

  6. • WEM Rules 2.27A.10 (a) L imit Advic e • WEM Procedure to specify Re q uire me nts • Information & data to be provided to AEMO in relation to Limit Advice • Processes to be followed • Format • Form • Manner • Timeframe • Two forms of Limit Advice: • Thermal Limit Advice Overview • Thermal Network Limits • Examples: transmission line thermal limits • Non-Thermal Limit Advice • Non-thermal Network Limits • Examples: Voltage stability, transient stability • NOTE 1: Tranche 1B will have the definitions of Thermal Network Limits and Non-thermal Network Limits • NOTE 2: RCM requirements not included in this requirement. To be included later. WRIG 01/10/2020 Limit Advice Requirements 12/10/2020 6

  7. • Thermal Network Limits = Equipment thermal L imit Advic e limits Re q uire me nts • Background • Presently provided to support real-time contingency monitoring in AEMO’s EMS • Format, form and manner • Utilising existing processes Thermal Limit Advice • A list of SWIS equipment thermal limits provided to an agreed shared location • Timeframe • As soon as practicable when no longer complete, current or accurate • New equipment: must be provided 3 months prior to commissioning WRIG 01/10/2020 Limit Advice Requirements 12/10/2020 7

  8. Network Operator AEMO Requested by AEMO [Clause 2.27A.4] L imit Advic e START Network Operator’s obligation to provide Limit Advice [Clause 2.27A.1] Re q uire me nts Network Operator Typical review timeframe depends on provides complete, current and accurate Limit Advice type of Limit Advice [Clause 2.27A.6] (Paragrah 3.3) Draft Limit Advice Yes Review Non-thermal Further information or Limit Advice additional Limit (Paragrah 4) Advice? Additional Limit Advice Further information/ Non-thermal Limit additional Limit Advice Further information required? amount and complexity of Timeframe dependent on Advice: Overview (Paragrah 3.3) information No Finalise Limit Advice Final Limit Advice planned outage approval or unplanned outage events Timeframe dependent on progress of connection/ network augmentation, Refer to timeframe requirement in (Paragrah 3.3) Constraint Equation implemented Fixed timeframe Variable timeframe commissioning of connection/ network augmentation, planned outage or unplanned outage events WRIG 01/10/2020 Limit Advice Requirements 12/10/2020 8

  9. • Format, form and manner • Non-thermal Limit Equations L imit Advic e • Non-thermal Limit Advice Inputs, supporting Re q uire me nts information and data Non-thermal Limit Advice: Format, form and manner WRIG 01/10/2020 Limit Advice Requirements 12/10/2020 9

  10. Typical lead t time Cause of of non on-thermal L Limit Circumstances of of prov ovision on of of Maximu mum B m Business D Days to Timeframe me o of requireme ment for Advice r requirement non on-thermal L Limit Advice com omplete ( (from t the start of of non on-thermal Limit A Advice t to be L imit Advic e review) w) finalised A year or more in advance Significant change to SWIS under After Network augmentation/ 30 days Typically at least 3 months prior normal operation, due to reinforcement has been to commissioning of new network augmentation or approved for detailed design equipment Re q uire me nts reinforcement And, typically, 6 months prior to commissioning of new equipment Significant change to SWIS under After Detailed Planning Data in 30 days Typically, at least 3 months prior normal operation, due to new relation to relevant connection to commissioning of new connections details becomes available to the connection Network Operator, And, typically, 6 months prior to commissioning of new connection Months and up to a year in Single Outage As soon as practically possible 20 days If a Network Operator forms a advance after a Network Operator view that non-thermal Limit forms a view that a non- Advice is required for Outages, thermal Limit Advice is non-thermal Limit Advice should required for Outages, and be provided to AEMO for typically 4 months prior to finalisation as soon as practically finalisation of the Limit Advice possible. Non-thermal Limit Multiple Outages 20 days, and additional 2 days per Network Limit Where in relation to Planned Advice: Timeframe Outages, prior to approval of an Outage and typically 2 months prior to commencement of the Outage. Planned minor change to SWIS Typically, 3 months prior to Up to 20 days Typically 1 month prior to the under normal operation proposed changes approval of the change to the SWIS Immediate and up to 1 day in Unforeseen events As required and best endeavours As required and best endeavours Immediate and best endeavours advance [1] Examples of significant change to SWIS under normal operation include: a new generation or load connection, Network augmentations, and new Network equipment having significant impact on system normal operation. [2] Detailed Planning Data has the meaning given in Attachment 3 of Technical Rules. [3] Note that Constraint Equations for the power system under Outage conditions are typically implemented in advance and must be ready to be invoked when Outages take place. Therefore, relevant non-thermal Limit Advice must be provided as soon as practically possible, whenever a Network Operator forms a view that an updated or a new non-thermal Limit Advice is required. [4] Examples of minor changes to the SWIS under normal operation include: change of normally open or closed points, and change of switching philosophy of Network equipment. [5] Examples of unforeseen events include multiple and non-credible contingencies due to bushfire or storms determined and re-classified by AEMO as Credible Contingencies in accordance with clause 3.8A.5 of the WEM Rules. WRIG 01/10/2020 Limit Advice Requirements 12/10/2020 10

  11. • To support formulation of constraint equations L imit Advic e • WEM Market Objectives Re q uire me nts • Good electricity industry practice • AEMO is not required to • Review methodology & assumptions • Recalculate/modify Limit equations • To identify residual risks and unnecessary consequences: Non-thermal Limit Advice: Review • Failing to maintain Power System Security or Power System Reliability • Overly conservative such that inconsistent with WEM Market Objectives • Unintended impact on power systems • To inform AEMO’s request for clarification, additional information and Limit Advice [2.2 .27A.4 A.4] WRIG 01/10/2020 Limit Advice Requirements 12/10/2020 11

  12. • Publication L imit Advic e • Public information Re q uire me nts • When thermal Limit Advice is received • When non-thermal Limit Advice is finalised • General review of Constraint Equations & request for additional/updated Limit Advice • Retirement General requirements • As specified by NO to be obsolete WRIG 01/10/2020 Limit Advice Requirements 12/10/2020 12

  13. • Additional comments or questions can be Que stio ns provided to AEMO • WA.ETS@aemo.com.au • AEMO Contact – Josephine Nga WRIG 01/10/2020 Limit Advice Requirements 12/10/2020 13

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend