wake field monitors conception installation and
play

Wake field monitors conception, installation and measurements in - PowerPoint PPT Presentation

Wake field monitors conception, installation and measurements in the CTF3 TBM and TBTS Reidar Lunde Lillestl The University of Oslo / CERN 28. January 2015 1/30 Introduction / Motivation CTF3 Measurements Summary / Outlook Outline 1


  1. Wake field monitors conception, installation and measurements in the CTF3 TBM and TBTS Reidar Lunde Lillestøl The University of Oslo / CERN 28. January 2015 1/30

  2. Introduction / Motivation CTF3 Measurements Summary / Outlook Outline 1 INTRODUCTION / MOTIVATION WFMs in CLIC Available modes in the CLIC structure 2 THE CLIC TEST FACILITY 3 The CTF3 and CLEX The Two-Beam Module (TBM) WFM signal connections in the CTF3 WFM scan experimental setup in the TBM 3 MEASUREMENTS Two-Beam Test Stand (TBTS) measurements First Two-Beam Module (TBM) measurements The PSI electro-optical front-end 4 SUMMARY 2/30

  3. Introduction / Motivation CTF3 Measurements Summary / Outlook Introduction / Motivation • In order to achieve the necessary luminosity for CLIC, we need to preserve a small main beam emittance. L ∝ ( ǫ x ǫ y ) − 1 (Picture is monopole 2 wakefield, not dipole) • One cause for emittance blow-up can be transverse wakes in the accelerating structures, which can kick the beam. • Dipole wakefields depend on the beam offset from the axis, so we need to minimize the beam offset in the structures. • Wakefield monitors (WFMs) finds the beam position based on these wakes. Then, alignment of the accelerating structures can be done, and this is foreseen after 1-to-1 steering and DFS. • For CLIC, the specification is an alignment of the accelerating structures of 5 µ m. 3/30

  4. Introduction / Motivation CTF3 Measurements Summary / Outlook WFM Test stand (see earlier talk this session) WFM ACS Beam pipe with bellows Hexa- Base + pod active optical table N. Galindo 4/30

  5. Introduction / Motivation CTF3 Measurements Summary / Outlook Wakefield monitors in CLIC • TD24 accelerating structures: 24 normal cells and 2 matching cells • 4 damping slots for each cell • 4 bent waveguides with rf absorbers make up the wakefield monitors. • In CTF3, the bent waveguides are currently installed on the 2nd cell, not the middle one • 2 coaxial rf pickups are installed on different sides of each bent waveguide. One measures TM-like modes, and the other measures TE-like modes. • In CTF3, the signals picked up are measured using log detectors. 5/30

  6. Introduction / Motivation CTF3 Measurements Summary / Outlook Available modes, found with GdfidL TM-like modes Slightly different now (2nd cell) TE-like modes F. Peauger 6/30

  7. Introduction / Motivation CTF3 Measurements Summary / Outlook 18 GHz TM dipole mode – electric field map F. Peauger 7/30

  8. Introduction / Motivation CTF3 Measurements Summary / Outlook Outline 1 INTRODUCTION / MOTIVATION WFMs in CLIC Available modes in the CLIC structure 2 THE CLIC TEST FACILITY 3 The CTF3 and CLEX The Two-Beam Module (TBM) WFM signal connections in the CTF3 WFM scan experimental setup in the TBM 3 MEASUREMENTS Two-Beam Test Stand (TBTS) measurements First Two-Beam Module (TBM) measurements The PSI electro-optical front-end 4 SUMMARY 8/30

  9. Introduction / Motivation CTF3 Measurements Summary / Outlook The CLIC Test Facility 3 (CTF3) 1-4 × 1-2 × TBM 9/30

  10. Introduction / Motivation CTF3 Measurements Summary / Outlook The Two Beam Test Stand • In operation since 2008 • Many results on • two-beam acceleration, • rf breakdowns, • rf breakdown kicks, • PETS recirculation, • on/off mechanism, • CLIC instrumentation, • octupole component of fundamental frequency mode • and recently also WFMs 10/30

  11. Introduction / Motivation CTF3 Measurements Summary / Outlook The remaking of CLEX 11/30

  12. Introduction / Motivation CTF3 Measurements Summary / Outlook The Two-Beam Module in CTF3 Drive beam Probe beam • 2 PETS • 4 Accelerating structures (2 superstructures) • 2 Quadrupoles • 2 WFMs • 2 Stripline BPMs • 4 × 2 × 2 = 16 WFM signals 12/30

  13. Introduction / Motivation CTF3 Measurements Summary / Outlook WFM signal connections in CTF3 13/30

  14. Introduction / Motivation CTF3 Measurements Summary / Outlook WFM scan experimental setup • Focus beam using quadrupole triplet • Use corrector(s) to steer beam • Read position on downstream screen (and with BPMs) 0 0 7 5 6 6 0 / / 0 0 0 0 4 0 5 5 1 0 5 0 0 0 0 6 4 0 5 0 0 0 0 0 0 5 9 6 7 7 9 1 1 6 6 6 6 3 3 0 8 6 5 2 4 0 2 7 7 0 0 5 5 5 0 0 8 8 8 7 7 7 7 5 5 5 5 0 J J 0 J 0 0 0 V 0 0 0 0 0 0 V 0 V S S 0 0 0 0 D J D D V V V C B M D C / C / C C M V / M D D D H H H F T P H T F P A A / T F P P H P P Q D D Q Q M B B M Q B B M D Q B . . B B D . . . . . A A . . . . . A . . A A . . . . . A A A A A . A A A A . A A A A A A C C C C A C C C C C C C C C C C C C C C C C 174 263 213 259 246 201 466 539 500 300 897 1142 1005 1764 860 403 500 500 602 488 7464 CAS.BPM0820 CAS.MTV0830 1339 1071 4383 1307 14/30

  15. Introduction / Motivation CTF3 Measurements Summary / Outlook Outline 1 INTRODUCTION / MOTIVATION WFMs in CLIC Available modes in the CLIC structure 2 THE CLIC TEST FACILITY 3 The CTF3 and CLEX The Two-Beam Module (TBM) WFM signal connections in the CTF3 WFM scan experimental setup in the TBM 3 MEASUREMENTS Two-Beam Test Stand (TBTS) measurements First Two-Beam Module (TBM) measurements The PSI electro-optical front-end 4 SUMMARY 15/30

  16. Introduction / Motivation CTF3 Measurements Summary / Outlook TBTS measurements (i) Wakefield signals as a function of corrector current (Changing a single corrector) L. Navarro 16/30

  17. Introduction / Motivation CTF3 Measurements Summary / Outlook TBTS measurements (ii) WF signals as a function of WF signals correlation beam position (Signals in ACS2 vs. (Originally position on signals in ACS1) downstream screen, adjusted L. Navarro to the ACS position) 17/30

  18. Introduction / Motivation CTF3 Measurements Summary / Outlook TBTS measurements (iii) Beam position correlation (a misalignment was found in the horizontal plane) Right : Residuals of the vertical fit With scaling, the L. Navarro resolution can fulfil the CLIC requirements 18/30

  19. Introduction / Motivation CTF3 Measurements Summary / Outlook First results in TBM: Delta signals at ∼ 18 GHz − 3 x 10 0.2 8 Beam Beam 6 0.15 LEFT LEFT 4 0.1 ∆ H signal ∆ V signal 2 0 0.05 − 2 0 − 4 − 0.05 − 6 2000 2200 2400 2600 2800 3000 1500 2000 2500 3000 Time [ps] Time [ps] 0.6 0.3 Beam Beam 0.5 0.25 TOP RIGHT TOP RIGHT 0.4 0.2 ∆ H signal ∆ V signal 0.3 0.15 0.2 0.1 0.1 0.05 0 0 − 0.1 − 0.05 2000 2200 2400 2600 2800 3000 2000 2200 2400 2600 2800 3000 Time [ps] Time [ps] 19/30

  20. Introduction / Motivation CTF3 Measurements Summary / Outlook Delta signals over sum signals, vs. position (all at ∼ 18 GHz) 3 0.7 0.65 2.5 0.6 2 0.55 ∆ H / Σ H ∆ H / Σ H 1.5 0.5 1 0.45 0.5 0.4 0 0.35 − 1.5 − 1 − 0.5 0 0.5 1 − 1 − 0.5 0 0.5 1 1.5 Beam position in X [mm] Beam position in Y [mm] 0.1 2.5 0.09 2 0.08 0.07 1.5 ∆ V / Σ V ∆ V / Σ V 0.06 1 0.05 0.04 0.5 0.03 0.02 0 − 1.5 − 1 − 0.5 0 0.5 1 1.5 − 1 − 0.5 0 0.5 1 1.5 Beam position in X [mm] Beam position in Y [mm] 20/30

  21. Introduction / Motivation CTF3 Measurements Summary / Outlook Single antenna signals ( ∼ 24 GHz) 0.01 0.06 0 0.05 Beam Beam − 0.01 FAR LEFT 0.04 FAR LEFT − 0.02 0.03 ’Left’ signals ’Up’ signals − 0.03 0.02 − 0.04 0.01 − 0.05 0 − 0.06 − 0.01 − 0.07 − 0.02 − 0.08 − 0.03 0 2000 4000 6000 8000 10000 2000 2200 2400 2600 2800 3000 Time [ps] Time [ps] 0.15 0.08 Beam Beam 0.06 TOP RIGHT TOP RIGHT 0.1 0.04 ’Left’ signals ’Up’ signals 0.05 0.02 0 0 − 0.02 − 0.05 − 0.04 2000 2200 2400 2600 2800 3000 2000 2200 2400 2600 2800 3000 Time [ps] Time [ps] 21/30

  22. Introduction / Motivation CTF3 Measurements Summary / Outlook Background issues ( ∼ 24 GHz) Possible peak detected as zero, because of the strange looking background signal! (Background somewhat different between datasets, so it is challenging to subtract) 22/30

  23. Introduction / Motivation CTF3 Measurements Summary / Outlook Drive beam noise in WFM signals 2.5 1.6 1.4 Proper 2 ’Left’ antenna signal (treated) 1.2 WFM Drive ∆ H signal (treated) signal – 1 1.5 beam 0.8 in 1 0.6 TBM 0.4 0.5 0.2 0 0 0 200 400 600 800 1000 0 200 400 600 800 1000 Time [ns] Time [ns] Drive beam in Test Beam Line (timing wrong) 23/30

  24. Introduction / Motivation CTF3 Measurements Summary / Outlook The PSI electro-optical front-end • New WFM front-end, based on an electro-optical approach • Radiation hardness well understood, can carry signals with negligible EM interference • Use of Electro-Optical Modulators, that via the applied electric fields change the phase delay of light paths in a LiNbO 3 crystal and enables QAM modulation M. Dehler • Possible testing in the TBM this year 24/30

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend