virginia p3 update 2015
play

VIRGINIA P3 UPDATE- 2015 Jackie Cromwell, VAP3 VIRGINIA LEADERSHIP - PowerPoint PPT Presentation

VIRGINIA P3 UPDATE- 2015 Jackie Cromwell, VAP3 VIRGINIA LEADERSHIP IN PUBLIC-PRIVATE PARTNERSHIPS PPTA enabling legislation 1995 Numerous revisions to PPTA Guidelines over time Creation of VAP3 office in 2010 2014


  1. VIRGINIA P3 UPDATE- 2015 Jackie Cromwell, VAP3

  2. VIRGINIA LEADERSHIP IN PUBLIC-PRIVATE PARTNERSHIPS PPTA enabling legislation • 1995 Numerous revisions to PPTA • Guidelines over time Creation of VAP3 office in • 2010 2014 – Substantial update to • PPTA Implementation Manual & Guidelines Goal is to build strategic • program, extend VAP3 leadership Virginia is a national leader • and 2 nd globally in P3 project development

  3. I-95 & I-495 EXPRESS LANES PROJECTS I-495 Express Lanes Opened to traffic November 2012 • Virginia’s $409 million investment • leveraged a $1.9 billion project Transurban increased its equity • investment in 2014 Over 10 million users in first two years • I-95 Express Lanes Opens in December 2014 • Virginia contribution of $71 million • leveraged $925 million project Adds to managed lanes system that • include I-495 Express Lanes

  4. ELIZABETH RIVER TUNNEL PROJECT Two-lane tunnel connects • Norfolk and Portsmouth Parallels existing Midtown Tunnel • under Elizabeth River Includes maintenance, safety • improvements for existing Midtown and Downtown Tunnels, extension of MLK Freeway VDOT maintains ownership and • oversight Private partner ERC will finance • and build facilities, operate and maintain for 58-year concession period

  5. PARTNERSHIPS CREATE HUGE PUBLIC BENEFITS P3 Project Project Cost State % of Jobs Economic Activity Contribution Total Supported Cost 495 Express $ 1.9 B $ 409 M 22 % 31,000 $ 3.5 B Lanes 95 Express $ 925 M $ 71 M 7.6 % 8,000 $ 2 B Lanes Midtown Tunnel $ 2.1 B $ 420.5 M 20 % 1,700 $ 170-254 M Total Benefits $ 4.9 B $ 901 M 18.4 % 40,700 jobs ~ $5.7 B

  6. CHANGES IN PPTA PROCESS • 2012 PPTA Implementation Manual and Guidelines were used as foundation to solicit 100+ responses • Key responses were : – Broad cross section of respondents – Overwhelmingly positive – Both broad and specific – Included in new 2014 PPTA Manual & Guidelines • Comments were incorporated in 2014 PPTA Implementation Manual and Guidelines – Guidelines including VfM, Risk, and Public Engagement are currently being updated and released for public comments

  7. PPTA PROJECT DELIVERY FRAMEWORK * Parties to be notified and briefed upon request after the Oversight Board decision: ‒ Chairs of General Assembly committees ‒ MPO’s ‒ Interested members of General Assembly ‒ Special interest groups ‒ Regulatory Agencies Briefing Focus: ‒ Public ‒ Detail - Level Screening Report ‒ Desirability as P3 ‒ Feasibility as P3 ‒ HB 2 Prioritization ‒ Duration of P3 development and procurement Briefing Focus: ‒ RFI results (as appropriate) ‒ Schedule ‒ Refresh on the high points from Project Draft and Final Development Contract Documents ‒ Preliminary Procurement documents posted on P3 ‒ Risk Analysis and Value -for-Money Website for review & ‒ Estimated project cost Briefing Focus: comment ‒ Potential public subsidy ‒ Major Business Points ‒ Potential economic benefits ‒ Updated Risk Allocation & Management ‒ Preliminary Business Points Plan ‒ Initial Finding of Public Interest ‒ Statutory Audit results ‒ Final Value -for-Money Analysis ‒ Updated economic benefits ‒ Project bid results Final Contract ‒ Public subsidy (if required) Documents posted ‒ Final Finding of Public Interest on P3 Website

  8. KEY CHANGES IN 2014 PPTA MANUAL & GUIDELINES Increase Transparency Brief Oversight Board at their public • meetings Findings of Public Interest • Brief General Assembly • Transportation Committee Chairmen Enhance Competition Coordinate P3 process with HB 2 • Additional review when there is only • one proposer Additional review if material change • in project scope or risk allocation

  9. KEY CHANGES IN 2014 PPTA MANUAL & GUIDELINES Increase Public Engagement Develop P3 Public Engagement • Guidelines New VAP3 website information • 24/7 website comment opportunities • Improve Risk Assessment and Management Revise Risk Management Guidelines • Include risk workshop and • discussions, risk registers and risk management plans

  10. PROJECT SCREENING PROCESS Solicited P3 Projects Unsolicited P3 Projects High-Level Policy Review with Screening with Recommendations Recommendations Agency Detail-Level Screening with Recommendations NO NO PPTA Steering Returned to Committee Agency or Proposer Oversight Board* Project Development

  11. PROJECT SCREENING PROCESS Solicited P3 Projects Unsolicited P3 Projects High-Level Screening Criteria High-Level Policy Review with Ability to Transfer Risk Screening with • Recommendations Recommendations Funding Requirement • Agency Ability to Raise Capital • Detail-Level Complexity of Effectively Leveraging • Screening with Recommendations Private Sector Innovation/Expertise NO NO Consistent with Federal Requirements • PPTA Steering Returned to Accelerated Project Development Committee • Agency or Proposer Satisfies Public Transportation Need • Oversight Addresses Priorities in State, Regional Board* • and/or Local Transportation Plan Project Project Efficiencies through PPTA Delivery Development •

  12. PROJECT SCREENING PROCESS Solicited P3 Projects Unsolicited P3 Projects Detail-Level Screening Criteria High-Level Policy Review with Public Need and Benefits Screening with • Recommendations Recommendations Economic Development • Agency Market Demand for PPTA Delivery • Detail-Level Stakeholder Support • Screening with Recommendations Legislative Considerations NO NO • Technical Feasibility PPTA • Steering Returned to Committee Systematic Interface and Compatibility Agency or • Proposer Financial Feasibility • Oversight Board* Legal/Legislative Feasibility • Project Risks • Project Development Life Cycle Management •

  13. CURRENT VAP3 PIPELINE Status of VAP3 Pipeline Projects in current VAP3 Pipeline 15 Projects have completed High-Level 12 Screening Projects have advanced to Detail-Level 7 Screening Projects Detail-Level Screening underway 4 Projects with completed Detail-Level 3 Screening Projects advanced as P3’s into Project 1 Development

  14. CURRENT PPTA PIPELINE

  15. CURRENT PPTA PIPELINE

  16. FUTURE OF VIRIGINIA P3 PROGRAM New 2014 PPTA Manual and • Guidelines will continue to strengthen transparency, competition, public engagement, risk assessment and management P3 benefits -- equity, risk sharing, • life-cycle costs, timely delivery Continue review of P3 process, • decision- making, & accountability

  17. FUTURE OF VIRIGINIA P3 PROGRAM VAP3 Pipeline will broaden in scope: • Real Estate transactions • Optimizing existing assets Current VAP3 Pipeline contains procurement types: • PPTA • PPEA • VPPA VAP3 Pipeline is continuously updated and on Website

  18. P3 PROGRAM NEXT STEPS • Finalized 2014 PPTA Implementation Manual and Guidelines • Coordinated with transportation agencies adoption of the 2014 PPTA Manual • Finalize Guidelines in early 2015: 1. Risk Management 2. Public Engagement 3. Value for Money Analysis • Draft PPEA Manual in early 2015

  19. P3 PUBLIC ENGAGEMENT VAP3 new website – live in early December and serves as • basis for P3 program & project information Twitter - VAP3 live and serves as quick release of • information Apps – under consideration to share and interact with • consumers

  20. P3 LESSONS LEARNED Permanent office acts as • champion, catalyst, guide Consistent, detailed guidelines • facilitate delivery, realization of public benefits Continuous reviews of assumptions • and conclusions improve project decisions Effective communications focus on • benefits produced, broad policy goals advanced Steady flows of information to • agencies, officials, planners, media build understanding and trust Others have good ideas, too, and • competition is growing

  21. P3 SHARED CHALLENGES Public funds are shrinking • Traditional delivery methods are not filling the gap • Political focus too often is short-term and small, not strategic • Engagement allows us to see members of the public as customers • and consumers of services willing to pay for what they value P3s remain unnecessarily complex, mystery to many • More standard approaches, terms are needed • New P3 approaches can help fill gaps beyond transportation •

  22. THANK YOU Virginia P3 Update - 2015 www.p3virginia.org Jackie Cromwell Virginia Office of Public-Private Partnerships Jackie.Cromwell@P3.Virginia.gov

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend