Perkins Coie LLP
Utility Scale Solar Update
Wisconsin Public Utility Institute March 5, 2019 Andrew C. Hanson
Utility Scale Solar Update March 5, 2019 Andrew C. Hanson Perkins - - PowerPoint PPT Presentation
Wisconsin Public Utility Institute Utility Scale Solar Update March 5, 2019 Andrew C. Hanson Perkins Coie LLP Overview Status of Utility-Scale Solar in the Midwest Transmission Project Development and Construction
Perkins Coie LLP
Wisconsin Public Utility Institute March 5, 2019 Andrew C. Hanson
Perkins Coie LLP | PerkinsCoie.com
2
3
4
Energy Assessment: 2016
5
Energy Assessment: 2018
Perkins Coie LLP
Perkins Coie LLP | PerkinsCoie.com 7 https://api.misoenergy.org/PublicGiQueueMap/index.html
Perkins Coie LLP | PerkinsCoie.com 8 https://api.misoenergy.org/PublicGiQueueMap/index.html
Perkins Coie LLP | PerkinsCoie.com 9 https://api.misoenergy.org/PublicGiQueueMap/index.html
10
Energy Assessment: 2018
Perkins Coie LLP | PerkinsCoie.com
Perkins Coie LLP | PerkinsCoie.com
12
Perkins Coie LLP | PerkinsCoie.com 13
Perkins Coie LLP | PerkinsCoie.com
14
Source: https://cdn.misoenergy.org/Definitive%20Planning%20Phase%20Estimated%20Schedule106547.pdf
15
Perkins Coie LLP
Perkins Coie LLP | PerkinsCoie.com
17
Perkins Coie LLP | PerkinsCoie.com
18
cost and risk;
systems (e.g., embedment depth for driven piles);
substation suitable for interconnection, with no or minimal network upgrades needed, or where the cost of upgrades is largely known;
support;
resources in or near the project (e.g., parks, wetlands, waters, habitats).
Perkins Coie LLP | PerkinsCoie.com
19
Power Purchase Agreement
Creditworthiness of off-taker Minimum output guarantee and replacement costs for curtailments Conditions precedent – fully developed interconnected project with milestones and completion date Develop-Transfer Asset Purchase - transfer of identified Project assets Assume only identified Project liabilities Consider contract assignability Purchase of Project Company (Equity Purchase) - acquire all assets of Project company Assume all liabilities of Project company Dissolution of entity post-closing
Build-Transfer
Developer develops, constructs, and transfers project to new owner
Perkins Coie LLP | PerkinsCoie.com
20
The project owner claims the ITC in the year the project is placed into service. The ITC vests linearly over a 5 year period. If the project owner sells the project before the end
To qualify for ITC at a level greater than 10%, project construction commences before 1/1/2022 and is placed in service by 12/31/2024. ITC % is based on the year the project construction commences: 2019 – 30%; 2020 – 26%; 2021 - 22%; and 2022 or later - 10%. Two methods to determine "commence-construction" date: (1) start physical work of a significant nature or (2) meet "5% safe harbor test" by incurring 5% or more of the total cost of the facility.
Perkins Coie LLP | PerkinsCoie.com 21
Land Rights Permits Studies and Reports Contracts (Generator Interconnection Agreement, etc.) Site Plan Interconnection and Transmission Solar Data Environmental Attributes Intellectual Property (project name, data, reports)
Perkins Coie LLP | PerkinsCoie.com 22
Leased Land Lease Terms and Conditions Duration/Termination Rights Prior Encumbrances (SNDA) Estoppel Certificates Owned (“Fee Simple”) Land Substation and O&M facility Rights of Way; Easements; Shared Rights Public and Private Preliminary Title Commitment Survey Title Insurance – Endorsements Recording
Perkins Coie LLP | PerkinsCoie.com
23
Permits
Conditional Use Permit Environmental (e.g. stormwater) Others Non-appealable status
Contracts
Generator Interconnection Agreement Other interconnection related agreements Consultant agreements for reports and studies Assignability Studies and Reports
Avian, Wildlife Assessment Congestion and Curtailment Assessment Cultural Resource Study Decommissioning Cost Analysis and Plan Interconnection Studies Phase I Environmental Site Assessment Preliminary Geotech Report Reactive Power Study Stability Analysis Wetlands Assessment/Field Delineation Solar Analysis/Capacity/Net Capacity Factor Report Depreciable Life Studies and Degradation Analysis
Perkins Coie LLP | PerkinsCoie.com 24
Responsible Party - Buyer vs. Developer EPC vs. BOP - selection of contractor and price Solar Panel/Equipment supply Schedule: mechanical completion, substantial completion and final completion ITC Requirements Warranty Period
Perkins Coie LLP | PerkinsCoie.com 25
Perkins Coie LLP | PerkinsCoie.com 26
Perkins Coie LLP
Perkins Coie LLP | PerkinsCoie.com 28
property
CONE for the relevant Resource Adequacy Planning Year;
generating assets to avoid or defer future investments in the Company’s distribution system…”
Perkins Coie LLP | PerkinsCoie.com 29
located in Wisconsin;
agreement, including depreciation, return on invested capital and O&M
capacity position during the MISO Resource Adequacy Planning Year at the time the agreement is executed
Perkins Coie LLP | PerkinsCoie.com
33 East Main Street Suite 201 Madison, WI 53703-3095
31