Trans Mountain Expansion Project Adam Lind, Senior Pipeline Engineer - - PowerPoint PPT Presentation

trans mountain expansion project
SMART_READER_LITE
LIVE PREVIEW

Trans Mountain Expansion Project Adam Lind, Senior Pipeline Engineer - - PowerPoint PPT Presentation

Presentation to WCGCE on Trans Mountain Expansion Project Adam Lind, Senior Pipeline Engineer Oct. 23 Burnaby, BC Outline Overview of Trans Mountain Pipeline Proposed Expansion Project Technical Challenges Routing,


slide-1
SLIDE 1

Presentation to WCGCE on Trans Mountain Expansion Project

Adam Lind, Senior Pipeline Engineer

  • Oct. 23 – Burnaby, BC
slide-2
SLIDE 2

Outline

  • Overview of Trans Mountain Pipeline
  • Proposed Expansion Project
  • Technical Challenges

– Routing, Construction and Geotechnical – System Hydraulics – Facilities – Integrity Management – Automation, Measurement and Leak Detection

slide-3
SLIDE 3

Trans Mountain Pipeline – 60 Years of History

slide-4
SLIDE 4

TRANS MOUNTAIN PIPELINE TODAY

slide-5
SLIDE 5
slide-6
SLIDE 6
  • In operation since 1953
  • 1,150 km from Edmonton to

Burnaby

  • Transports refined products and

crude oils: conventional, synthetic and dilbit

  • Regulated by the NEB
  • Last expansion completed in 2008

– Anchor Loop

  • Current capacity: 300,000 bpd

Existing relationships along the Right-of-Way

Trans Mountain Pipeline

slide-7
SLIDE 7

TMPL Throughput 2012

2012 Trans Mountain Pipeline Throughput by Product Type

Refined Products Light Crude Heavy Crude Synthetic Crude

16% 17% 22% 45%

slide-8
SLIDE 8

Trans Mountain – Historical Throughput

8

slide-9
SLIDE 9
slide-10
SLIDE 10

TRANS MOUNTAIN EXPANSION PROJECT OVERVIEW

slide-11
SLIDE 11

Proposed Scope of Expansion Project

  • Jan. 10, 2013: Scope

update announced

  • Based on revised 15- and

20-year commitments from shippers to use the line

  • The proposed expansion to

increase capacity to 890,000 barrels per day

  • Projected capital cost is

approximately $5.4 billion

slide-12
SLIDE 12

Proposed Scope of Expansion Project

  • Result: a dual-line
  • peration – twinned

pipeline (approximately 980 km of new pipeline) with:

– Existing line for lighter products – The proposed new line for heavier oils

  • 36-inch pipeline

diameter

  • 11 new pump stations

for a total of 35 pump stations along the route

slide-13
SLIDE 13

Proposed Scope of Expansion project

  • Estimated 21 new

storage tanks at existing facilities in Edmonton, Sumas and Burnaby for a total of 61 tanks along the route

  • Three loading berths at

the Westridge Marine Terminal

slide-14
SLIDE 14
slide-15
SLIDE 15
slide-16
SLIDE 16

Trans Mountain Expansion Schedule

Regulatory Approvals 15 months Construction 2 years

2012 2014 2015 2016 2013 2017

Application Preparation 1.5 years

Commercial (Tolling) Approvals

slide-17
SLIDE 17

MARINE

slide-18
SLIDE 18

Marine Traffic

Current traffic in Port Metro Vancouver related to Westridge Marine Terminal operations

Current Estimated with Proposed Trans Mountain Expansion Project 8 vessels per month

  • Jet fuel barges: 1
  • Tankers: 5
  • Crude oil barges: 2
  • Currently: less than 3% of marine

traffic in Port Metro Vancouver 37 vessels per month

  • Jet fuel barges: 1
  • Tankers: 34
  • Crude oil barges: 2

Should the proposed expansion be approved, the number of vessels, including tankers and barges, being loaded at the Westridge Marine Terminal could increase to approximately 37 per month (34 of which could be tankers) in 2017,

  • r about 14% of today’s total Port Metro Vancouver vessel traffic.
slide-19
SLIDE 19

TECHNICAL CHALLENGES

slide-20
SLIDE 20

ROUTING, CONSTRUCTION AND GEOTECHNICAL

slide-21
SLIDE 21

Routing

  • Key criteria in route selection

– Follow existing 24” TMPL – Parallel other linear disturbances e.g. road, rail and power lines – Avoid environmentally/geotechnically sensitive areas where possible – Minimize number of major rivers that have to be crossed

  • Issues faced during routing

– Hwy. 16, 5 and 1 were not there when pipeline was built in 1952/53

  • Previous road expansions have left many pinch points between

existing RoW, road, rail, mountainsides and rivers

– Property development between Langley and Burnaby

slide-22
SLIDE 22

Routing

  • For example…
slide-23
SLIDE 23

Routing

  • Show map from Chilliwack to Burnaby
  • Close up map of Burnaby
slide-24
SLIDE 24

Routing

  • Show map from Chilliwack to Burnaby
  • Close up map of Burnaby
slide-25
SLIDE 25

Routing Outcome

  • TMEP study corridor (Facilities Application will

be submitted to NEB late 2013)

– 70% adjacent to or in existing TMPL easement (typically 18 m wide) – 20% adjacent to other linear disturbances – 10% greenfield

  • Uncertainty about 10% of the route, assessing

alternative routes due to:

– Landowner concerns – Aboriginal or Stakeholder concerns – Environmental reasons

slide-26
SLIDE 26

Construction

  • Rural vs. urban pipelining
  • Mountainous terrain

– Blasting, backfill and pipe protection procedures, remediation – Will draw extensively on Anchor Loop experience

slide-27
SLIDE 27

Canadian Rocky Mountain Parks UNESCO World Heritage Site

slide-28
SLIDE 28

Regulatory Oversight

DFO NEB B Parks

slide-29
SLIDE 29

Routing - Follow Existing Disturbances

slide-30
SLIDE 30

Congested Transportation Corridor

slide-31
SLIDE 31

Routing – Municipality of Jasper

slide-32
SLIDE 32

ROW Access Bridges

slide-33
SLIDE 33

Proximity to existing TMPL

slide-34
SLIDE 34

Winter Construction

slide-35
SLIDE 35

Steep Terrain – West Side Windy Point

slide-36
SLIDE 36

Steep Terrain – East Side Windy Point

slide-37
SLIDE 37

East Side Windy Point – 1952

slide-38
SLIDE 38

Steep Terrain – Stringing Operations

slide-39
SLIDE 39

Blast Rock Ditch

slide-40
SLIDE 40

Unsuitable Backfill Material

slide-41
SLIDE 41

Narrow ROW - Rainbow Hill

slide-42
SLIDE 42

Athabasca River Crossing

slide-43
SLIDE 43

Athabasca River Crossing

slide-44
SLIDE 44

120+ Isolated Stream Crossings

slide-45
SLIDE 45

Wetlands Construction

slide-46
SLIDE 46

Rock Fall Hazard - Pallisades

slide-47
SLIDE 47

Restoration

slide-48
SLIDE 48

Restoration – Streambank Preparation

slide-49
SLIDE 49

Restoration – Geikie Wetland, 15,000 Plants

slide-50
SLIDE 50

Stream Restoration

slide-51
SLIDE 51

Geotechnical

  • Avoid areas prone to ground movement

– Detailed seismic study underway – Complete geohazard inventory developed – Leverage 60 year operating history and detailed natural hazard database

  • River crossing design

– HDD or micro-tunneling vs. conventional “open cut”

slide-52
SLIDE 52

SYSTEM HYDRAULICS

slide-53
SLIDE 53

System Hydraulics

  • New 36” pipeline loop (Line 2)

– Sustainable annual average pipeline capacity of 540,000 bpd

  • Based on an assumed slate of heavy crude oils
  • Existing 24”/30” pipeline (Line 1)

– Sustainable average annual pipeline capacity of 350,000 bpd

  • Based on an assumed slate of light crude oils and refined products
  • Burnaby to Westridge

– Two new 30” pipelines  700,000 bpd – Existing 24” pipeline  500,000 – 700,000 bpd

slide-54
SLIDE 54

System Hydraulics

  • Steady state hydraulic studies completed to

verify preliminary results

  • Pressure surge or transient studies needed to

ensure adequate overpressure protection

– Pressure surges must be < 110% of the MOP

slide-55
SLIDE 55

Liquid Pipeline Operations

  • Product quality

– Depends on flow regime – laminar vs. turbulent – Batches used to be physically separated

  • Slack flow

– Static pressure = Dynamic pressure – Formation of vapour space

slide-56
SLIDE 56

Liquid Pipeline Operations

  • Product quality

– Depends on flow regime – laminar vs. turbulent – Batches used to be physically separated

  • Slack flow

– Static pressure = Dynamic pressure – Formation of vapour space

slide-57
SLIDE 57

FACILITIES

slide-58
SLIDE 58

Burnaby Terminal Overview

Existing Planned

  • 13 tanks
  • 14 new tanks
  • 1.6 million bbl capacity
  • 3.9 million bbl incremental

capacity

  • 24-inch pipeline entering from

southeast

  • New 36 inch pipeline entering

from southeast

  • 24 inch pipeline to Westridge

exiting to the northwest

  • Two new 30-inch lines to

Westridge exiting to the northwest

slide-59
SLIDE 59

Burnaby Terminal – Existing & Planned

slide-60
SLIDE 60

Westridge Marine Terminal Overview

Existing Planned

  • Dock capable of loading 1

Aframax-sizing or smaller vessel

  • One new dock complex (2 docks

with 3 berths) each capable of loading vessels the same size we load today

  • Berth to be deactivated +

demolished after new berths enter service.

  • Aframax vessels subject to same

restrictions, including being loaded at 85% capacity, 550,00 bbls.

  • 4 PMV designated anchorage

locations

  • No plans for additional anchorage

locations

  • One 24-inch pipe from Burnaby

Terminal to remain in service

  • Two new 30-inch delivery lines

from Burnaby Terminal

slide-61
SLIDE 61

Westridge – Proposed Aerial view

slide-62
SLIDE 62

Westridge – conceptual design

This image represents a conceptual design for Westridge Terminal, based on preliminary

  • engineering. The design may change after further developmental and detailed

engineering.

slide-63
SLIDE 63

Pump stations

  • # of stations, pumps, horsepower, etc…
  • Picture of TMPSE pump station
slide-64
SLIDE 64

Remote valve sites

  • # of stations, pumps, horsepower, etc…
  • Picture of TMPSE pump station
slide-65
SLIDE 65

INTEGRITY MANAGEMENT

slide-66
SLIDE 66

Integrity Management

  • Facilities and pipeline undergo hazard

identification process and incorporate safeguards into design

  • If design fails, spills are prevented and/or

mitigated by procedures, inspection and detection

slide-67
SLIDE 67

Design features

  • Facilities – Materials, site selection, earthworks,

containment

  • Pipeline – Pipe grade and wall thickness, depth
  • f cover, routing and valve spacing/automation
slide-68
SLIDE 68

Integrity Management

  • Misinformation regarding properties of diluted

bitumen (“dilbit”)

  • Similar to conventional heavy crude oils
  • Must meet NEB approved TMPL tariff

specifications:

– Maximum temperature of 38 C – Maximum density of 940 kg/m3 – Maximum viscosity of 350 cSt at Reference Temperature – Maximum impurities (basic sediment and water) of 0.5% of volume – Maximum Reid Vapour Pressure of 103 kPa

slide-69
SLIDE 69

Integrity Management

  • Multiple studies on dilbit characteristics

– National Research Council – Effects of Diluted Bitumen on Crude Oil Transmission Pipelines – CEPA – Report on Dilbit Corrosivity – Natural Resources Canada (NRCan) – Bitumen-Derived Crude and Corrosivity – Alberta Innovates – Comparison of the Corrosivity of Dilbit and Conventional Crude – All are linked at http://www.transmountain.com/diluted-bitumen- info

slide-70
SLIDE 70

AUTOMATION, MEASUREMENT AND LEAK DETECTION

slide-71
SLIDE 71

Automation and Measurement

  • SCADA (supervisory control and data

acquisition) is used to monitor pipeline process variables

– Pressure – Flow – Temperature – Density – Viscosity – Colour

slide-72
SLIDE 72

Automation and Measurement

  • SCADA system will be upgraded with satellite

communications from every remote site

  • Pressure, temperature and flow rate

instrumentation is needed for computer-based leak detection systems

slide-73
SLIDE 73

Leak Detection

  • Current computer-based models

– Real Time Transient Models – Mass Balance Systems

  • External leak detection systems
  • Cable-based technologies

– Distributed Temperature Sensing – Hydrocarbon Sensing Cables – Vapour Sensing Tubes – Distributed Acoustic Systems

  • Aerial-based technologies
slide-74
SLIDE 74

Questions?

slide-75
SLIDE 75

Celebrating 60 Years