SLIDE 1 Presentation to WCGCE on Trans Mountain Expansion Project
Adam Lind, Senior Pipeline Engineer
SLIDE 2 Outline
- Overview of Trans Mountain Pipeline
- Proposed Expansion Project
- Technical Challenges
– Routing, Construction and Geotechnical – System Hydraulics – Facilities – Integrity Management – Automation, Measurement and Leak Detection
SLIDE 3
Trans Mountain Pipeline – 60 Years of History
SLIDE 4
TRANS MOUNTAIN PIPELINE TODAY
SLIDE 5
SLIDE 6
- In operation since 1953
- 1,150 km from Edmonton to
Burnaby
- Transports refined products and
crude oils: conventional, synthetic and dilbit
- Regulated by the NEB
- Last expansion completed in 2008
– Anchor Loop
- Current capacity: 300,000 bpd
Existing relationships along the Right-of-Way
Trans Mountain Pipeline
SLIDE 7 TMPL Throughput 2012
2012 Trans Mountain Pipeline Throughput by Product Type
Refined Products Light Crude Heavy Crude Synthetic Crude
16% 17% 22% 45%
SLIDE 8 Trans Mountain – Historical Throughput
8
SLIDE 9
SLIDE 10
TRANS MOUNTAIN EXPANSION PROJECT OVERVIEW
SLIDE 11 Proposed Scope of Expansion Project
update announced
20-year commitments from shippers to use the line
- The proposed expansion to
increase capacity to 890,000 barrels per day
- Projected capital cost is
approximately $5.4 billion
SLIDE 12 Proposed Scope of Expansion Project
- Result: a dual-line
- peration – twinned
pipeline (approximately 980 km of new pipeline) with:
– Existing line for lighter products – The proposed new line for heavier oils
diameter
for a total of 35 pump stations along the route
SLIDE 13 Proposed Scope of Expansion project
storage tanks at existing facilities in Edmonton, Sumas and Burnaby for a total of 61 tanks along the route
the Westridge Marine Terminal
SLIDE 14
SLIDE 15
SLIDE 16 Trans Mountain Expansion Schedule
Regulatory Approvals 15 months Construction 2 years
2012 2014 2015 2016 2013 2017
Application Preparation 1.5 years
Commercial (Tolling) Approvals
SLIDE 17
MARINE
SLIDE 18 Marine Traffic
Current traffic in Port Metro Vancouver related to Westridge Marine Terminal operations
Current Estimated with Proposed Trans Mountain Expansion Project 8 vessels per month
- Jet fuel barges: 1
- Tankers: 5
- Crude oil barges: 2
- Currently: less than 3% of marine
traffic in Port Metro Vancouver 37 vessels per month
- Jet fuel barges: 1
- Tankers: 34
- Crude oil barges: 2
Should the proposed expansion be approved, the number of vessels, including tankers and barges, being loaded at the Westridge Marine Terminal could increase to approximately 37 per month (34 of which could be tankers) in 2017,
- r about 14% of today’s total Port Metro Vancouver vessel traffic.
SLIDE 19
TECHNICAL CHALLENGES
SLIDE 20
ROUTING, CONSTRUCTION AND GEOTECHNICAL
SLIDE 21 Routing
- Key criteria in route selection
– Follow existing 24” TMPL – Parallel other linear disturbances e.g. road, rail and power lines – Avoid environmentally/geotechnically sensitive areas where possible – Minimize number of major rivers that have to be crossed
- Issues faced during routing
– Hwy. 16, 5 and 1 were not there when pipeline was built in 1952/53
- Previous road expansions have left many pinch points between
existing RoW, road, rail, mountainsides and rivers
– Property development between Langley and Burnaby
SLIDE 23 Routing
- Show map from Chilliwack to Burnaby
- Close up map of Burnaby
SLIDE 24 Routing
- Show map from Chilliwack to Burnaby
- Close up map of Burnaby
SLIDE 25 Routing Outcome
- TMEP study corridor (Facilities Application will
be submitted to NEB late 2013)
– 70% adjacent to or in existing TMPL easement (typically 18 m wide) – 20% adjacent to other linear disturbances – 10% greenfield
- Uncertainty about 10% of the route, assessing
alternative routes due to:
– Landowner concerns – Aboriginal or Stakeholder concerns – Environmental reasons
SLIDE 26 Construction
- Rural vs. urban pipelining
- Mountainous terrain
– Blasting, backfill and pipe protection procedures, remediation – Will draw extensively on Anchor Loop experience
SLIDE 27
Canadian Rocky Mountain Parks UNESCO World Heritage Site
SLIDE 28 Regulatory Oversight
DFO NEB B Parks
SLIDE 29
Routing - Follow Existing Disturbances
SLIDE 30
Congested Transportation Corridor
SLIDE 31
Routing – Municipality of Jasper
SLIDE 32
ROW Access Bridges
SLIDE 33
Proximity to existing TMPL
SLIDE 34
Winter Construction
SLIDE 35
Steep Terrain – West Side Windy Point
SLIDE 36
Steep Terrain – East Side Windy Point
SLIDE 37
East Side Windy Point – 1952
SLIDE 38
Steep Terrain – Stringing Operations
SLIDE 39
Blast Rock Ditch
SLIDE 40
Unsuitable Backfill Material
SLIDE 41
Narrow ROW - Rainbow Hill
SLIDE 42
Athabasca River Crossing
SLIDE 43
Athabasca River Crossing
SLIDE 44
120+ Isolated Stream Crossings
SLIDE 45
Wetlands Construction
SLIDE 46
Rock Fall Hazard - Pallisades
SLIDE 47
Restoration
SLIDE 48
Restoration – Streambank Preparation
SLIDE 49
Restoration – Geikie Wetland, 15,000 Plants
SLIDE 50
Stream Restoration
SLIDE 51 Geotechnical
- Avoid areas prone to ground movement
– Detailed seismic study underway – Complete geohazard inventory developed – Leverage 60 year operating history and detailed natural hazard database
– HDD or micro-tunneling vs. conventional “open cut”
SLIDE 52
SYSTEM HYDRAULICS
SLIDE 53 System Hydraulics
- New 36” pipeline loop (Line 2)
– Sustainable annual average pipeline capacity of 540,000 bpd
- Based on an assumed slate of heavy crude oils
- Existing 24”/30” pipeline (Line 1)
– Sustainable average annual pipeline capacity of 350,000 bpd
- Based on an assumed slate of light crude oils and refined products
- Burnaby to Westridge
– Two new 30” pipelines 700,000 bpd – Existing 24” pipeline 500,000 – 700,000 bpd
SLIDE 54 System Hydraulics
- Steady state hydraulic studies completed to
verify preliminary results
- Pressure surge or transient studies needed to
ensure adequate overpressure protection
– Pressure surges must be < 110% of the MOP
SLIDE 55 Liquid Pipeline Operations
– Depends on flow regime – laminar vs. turbulent – Batches used to be physically separated
– Static pressure = Dynamic pressure – Formation of vapour space
SLIDE 56 Liquid Pipeline Operations
– Depends on flow regime – laminar vs. turbulent – Batches used to be physically separated
– Static pressure = Dynamic pressure – Formation of vapour space
SLIDE 57
FACILITIES
SLIDE 58 Burnaby Terminal Overview
Existing Planned
- 13 tanks
- 14 new tanks
- 1.6 million bbl capacity
- 3.9 million bbl incremental
capacity
- 24-inch pipeline entering from
southeast
- New 36 inch pipeline entering
from southeast
- 24 inch pipeline to Westridge
exiting to the northwest
Westridge exiting to the northwest
SLIDE 59
Burnaby Terminal – Existing & Planned
SLIDE 60 Westridge Marine Terminal Overview
Existing Planned
- Dock capable of loading 1
Aframax-sizing or smaller vessel
- One new dock complex (2 docks
with 3 berths) each capable of loading vessels the same size we load today
- Berth to be deactivated +
demolished after new berths enter service.
- Aframax vessels subject to same
restrictions, including being loaded at 85% capacity, 550,00 bbls.
- 4 PMV designated anchorage
locations
- No plans for additional anchorage
locations
- One 24-inch pipe from Burnaby
Terminal to remain in service
- Two new 30-inch delivery lines
from Burnaby Terminal
SLIDE 61
Westridge – Proposed Aerial view
SLIDE 62 Westridge – conceptual design
This image represents a conceptual design for Westridge Terminal, based on preliminary
- engineering. The design may change after further developmental and detailed
engineering.
SLIDE 63 Pump stations
- # of stations, pumps, horsepower, etc…
- Picture of TMPSE pump station
SLIDE 64 Remote valve sites
- # of stations, pumps, horsepower, etc…
- Picture of TMPSE pump station
SLIDE 65
INTEGRITY MANAGEMENT
SLIDE 66 Integrity Management
- Facilities and pipeline undergo hazard
identification process and incorporate safeguards into design
- If design fails, spills are prevented and/or
mitigated by procedures, inspection and detection
SLIDE 67 Design features
- Facilities – Materials, site selection, earthworks,
containment
- Pipeline – Pipe grade and wall thickness, depth
- f cover, routing and valve spacing/automation
SLIDE 68 Integrity Management
- Misinformation regarding properties of diluted
bitumen (“dilbit”)
- Similar to conventional heavy crude oils
- Must meet NEB approved TMPL tariff
specifications:
– Maximum temperature of 38 C – Maximum density of 940 kg/m3 – Maximum viscosity of 350 cSt at Reference Temperature – Maximum impurities (basic sediment and water) of 0.5% of volume – Maximum Reid Vapour Pressure of 103 kPa
SLIDE 69 Integrity Management
- Multiple studies on dilbit characteristics
– National Research Council – Effects of Diluted Bitumen on Crude Oil Transmission Pipelines – CEPA – Report on Dilbit Corrosivity – Natural Resources Canada (NRCan) – Bitumen-Derived Crude and Corrosivity – Alberta Innovates – Comparison of the Corrosivity of Dilbit and Conventional Crude – All are linked at http://www.transmountain.com/diluted-bitumen- info
SLIDE 70
AUTOMATION, MEASUREMENT AND LEAK DETECTION
SLIDE 71 Automation and Measurement
- SCADA (supervisory control and data
acquisition) is used to monitor pipeline process variables
– Pressure – Flow – Temperature – Density – Viscosity – Colour
SLIDE 72 Automation and Measurement
- SCADA system will be upgraded with satellite
communications from every remote site
- Pressure, temperature and flow rate
instrumentation is needed for computer-based leak detection systems
SLIDE 73 Leak Detection
- Current computer-based models
– Real Time Transient Models – Mass Balance Systems
- External leak detection systems
- Cable-based technologies
– Distributed Temperature Sensing – Hydrocarbon Sensing Cables – Vapour Sensing Tubes – Distributed Acoustic Systems
- Aerial-based technologies
SLIDE 74
Questions?
SLIDE 75
Celebrating 60 Years