Tracking Michigan Air Toxics Program Applicability Using MON Operating Scenarios
MCC Annual Conference October 17, 2017 Steve Zervas, Managing Consultant David Dempsey, Managing Consultant
Tracking Michigan Air Toxics Program Applicability Using MON - - PowerPoint PPT Presentation
Tracking Michigan Air Toxics Program Applicability Using MON Operating Scenarios MCC Annual Conference October 17, 2017 Steve Zervas, Managing Consultant David Dempsey, Managing Consultant Meaningful Change Exemption for Air Toxics
MCC Annual Conference October 17, 2017 Steve Zervas, Managing Consultant David Dempsey, Managing Consultant
Two Hazard Potentials are required to make a Meaningful Change determination – one for carcinogens and another for non-carcinogens. The Hazard Potential is Calculated as follows: Hazard Potential = PTE (lb/hr) / IRSL or Adjusted Annual ITSL The adjusted annual ITSL is the ITSL adjusted to an annual averaging time. To convert from: 1-Hr to Annual: multiply ITSL x 0.10 8-Hr to Annual: multiply ITSL x 0.11 24-Hr to Annual: multiply ITSL x 0.17
1.
Identify the TACs for both the existing permitted emission unit and the emission unit after the proposed change.
2.
Determine the hourly potential to emit (PTE) in pounds per hour for each TAC. PTE is defined in Rule 116(m).
3.
Identify all screening levels (SLs) for each TAC identified in Step 1. Some TACs have both an ITSL and an IRSL – both must be used.
4.
Convert each non-annual ITSL to adjusted annual ITSL.
5.
Calculate both a carcinogenic Hazard Potential (HP) and a non- carcinogenic HP for each SL. HP = (hourly PTE) / (IRSL or adjusted annual ITSL)
6.
Find the highest HP for non-cancer (based on ITSLs) and the highest HP for cancer (based on IRSLs) for both the existing operation and post-modification.
7.
Determine the percent change in each HP - an increase of more than 10% in either HP is “meaningful”.
˃
Changes cannot involve the installation or reconstruction of an Emission Unit
˃
Changes cannot result in emissions greater than an existing permit limit
˃
Some Meaningful Changes may be exempt – Rule 285(2)(c)(iii)
˃
Meaningful Increase:
don’t cause an increase in the Hazard Potential of more than 10%
individual TAC (e.g., of the same TAC, or any new TAC not in the baseline)
˃
Installation of control equipment may utilize this approach
˃
If a proposed change involves a TAC without a SL, it must be included – use regulatory guidance to develop an appropriate SL.
˃
Maintain records for each Meaningful Change evaluation performed
A facility obtained a permit in 1999 that included a 10 lb/hr emission limit for Compound A. No changes have occurred at the facility since then. The proposed change will increase Compound A to 12 lb/hr. Since the original permit was obtained, the ITSL for Compound A has increased from 1,200 µg/m3 (annual) to 5,000 µg/m3 (annual).
TAC PTE (lb/hr) IRSL (µg/m3) ITSL (µg/m3) Averaging Period Adjusted Annual ITSL Hazard Potential Baseline: Compound A
10
Annual
Proposed: Compound A
12
Annual
Evaluation: Even though the Hazard Potential decreases, this project cannot be exempt because the new emission rate will exceed an existing permit limit.
A facility obtained a permit in 2010 that included a carcinogen and two non-
carcinogens.
TAC PTE (lb/hr) IRSL (µg/m3) ITSL (µg/m3) Averaging Period Adjusted Annual ITSL Hazard Potential Baseline: Carc A
1.1 1.2
Non-Carc A
0.55
24-Hr 1,020 0.00054
Non-Carc B
16.2
1-Hr 1.7 9.53
Proposed (only the worst-case listed here): Carc B
0.6 0.8
Non-Carc G
12
8-Hr 1.16 10.34 Evaluation: Carcinogenic HP decreases from 0.917 to 0.75 – not Meaningful Change. Non-Carcinogenic HP increases from 9.53 to 10.34 = 8.5% increase – not Meaningful Change.
A facility obtained a permit in 2007 that included one carcinogen. The proposed change includes 2 non-carcinogens.
TAC PTE (lb/hr) IRSL (µg/m3) ITSL (µg/m3) Averaging Period Adjusted Annual ITSL Hazard Potential Baseline: Carc A
65 1.2
Proposed: Non-Carc X
15
24-Hr 170 0.088
Non-Carc Y
35
8-Hr 550 0.064 Evaluation: There is no baseline non-carcinogenic Hazard Potential. Therefore, no Meaningful Change calculation can be made. This project cannot be exempt.
More site-specific applicability determinations
…Our position is that submitting operating scenarios is critical to enforcement of the final rule, as they provide much of the information required to demonstrate compliance. Information in operating scenarios also is the cornerstone of the management of change strategy that was developed to address the constantly changing processing environment associated with batch processors. Although this management of change flexibility is optional at the discretion of the regulatory authority, 40 CFR part 63, subpart FFFF, provides the framework for implementing the strategy.
DD2
Slide 14 DD2 in other words, the MON provides an example of a well-described management of change procedure for evalating facility changes that could be applied for NSR.
David Dempsey, 7/22/2015
Description Identify all equipment routed Description of operating conditions Description of testing conditions
Monitoring requirements Monitoring levels that assure
What products do you manufacture? Are there multiple formulations for a
Different TAC composition
Is one product clearly the worst case HP? How many products do you need to have
IRSL or adjusted annual ITSL baseline PTE established by either
♦ the permit limits after April 17, 1992 ♦ the permit application
Hazard Potential (HP)
♦ Carcinogens ♦ Non-Carcinogen
Assumptions that affect PTE and HP
IRSL or adjusted annual ITSL PTE Hazard Potential (HP) for each TAC
Carcinogens Non-Carcinogens
Not average annualized
Products with TAC not worst-case for
Tracking multiple products with TAC
IRSL or adjusted annual ITSL baseline PTE established by either
♦ the permit limits established after April 17, 1992 ♦ the permit application or facility records
Hazard Potential (HP)