TIP Modification Pony Express Pkwy Eagle Mountain/Saratoga Springs - - PowerPoint PPT Presentation

tip modification
SMART_READER_LITE
LIVE PREVIEW

TIP Modification Pony Express Pkwy Eagle Mountain/Saratoga Springs - - PowerPoint PPT Presentation

TIP Modification Pony Express Pkwy Eagle Mountain/Saratoga Springs SECTION | TITLE TIP Modification Pony Express Parkway Selected in 2016 Awarded $9,801,350 (MAG Exchange) Nearly completed the project. Sewer trench repair and


slide-1
SLIDE 1

SECTION | TITLE

TIP Modification

Pony Express Pkwy Eagle Mountain/Saratoga Springs

slide-2
SLIDE 2

Pony Express Parkway

Selected in 2016

Awarded $9,801,350 (MAG Exchange)

Nearly completed the project.

Sewer trench repair and drainage improvements.

Requesting 10% contingency = $980,135

Over $500,000 must be approved by RPC TIP Modification

slide-3
SLIDE 3

TIP Modification

slide-4
SLIDE 4

TIP Modification

slide-5
SLIDE 5

Pony Express Pkwy

Repairs and modifications: $1,064,756

10% contingency = $980,135

Additional $84,621 and match on the contingency funds will be split by Eagle Mountain and Saratoga Springs TIP Modification

slide-6
SLIDE 6

Pony Express Parkway

Suggested motion: “I move that MPO Regional Planning Committee modify the Transportation Improvement Program to add $980,135 contingency funds to the Pony Express Pkwy widening project.” TIP Modification