The Klingle Valley Trail a Roads-to-trails Story Paul Hoffman - - PowerPoint PPT Presentation

the klingle valley trail a roads to trails story
SMART_READER_LITE
LIVE PREVIEW

The Klingle Valley Trail a Roads-to-trails Story Paul Hoffman - - PowerPoint PPT Presentation

The Klingle Valley Trail a Roads-to-trails Story Paul Hoffman August 17, 2017 District Department of Transportation Infrastructure Project Management Division Agenda About DDOT Klingle Roads demise Public controversy builds


slide-1
SLIDE 1

The Klingle Valley Trail a “Roads-to-trails” Story

Paul Hoffman August 17, 2017

District Department of Transportation Infrastructure Project Management Division

slide-2
SLIDE 2

Agenda

About DDOT Klingle Road’s demise

  • Public controversy builds
  • DPW/DDOT way forward

Environmental documentation and design

  • Draft EIS and EA
  • Designs

Construction

  • Rebuild utilities
  • Stream Restoration
  • Green Infrastructure
  • Permeable Pavement
slide-3
SLIDE 3

DDOT is Born

May 2002 – DC Council passes the District Department of Transportation Establishment Act of 2002, creating a cabinet-level agency responsible for the management of transportation infrastructure and operations. Prior to the Act, transportation was managed under the Department of Public Works.

slide-4
SLIDE 4

Project Location

slide-5
SLIDE 5

Project Location

slide-6
SLIDE 6
slide-7
SLIDE 7
slide-8
SLIDE 8
slide-9
SLIDE 9
slide-10
SLIDE 10
slide-11
SLIDE 11
slide-12
SLIDE 12

The public weighs in…

Source: Washington Post

slide-13
SLIDE 13

Right-of-way

National Zoo NPS Tregaron Conservancy Gov’t

  • f India

WMATA

slide-14
SLIDE 14

Timeline…

Original Klingle Road 1831 Current Klingle Road Alignment 1930s Klingle Road Closed to Public 1991 Klingle Road Feasibility Study 2001 Klingle Road Restoration Act 2003 Draft Environmental Impact Statement 2005 Klingle Road Sustainable Development Amendment Act 2008 Final Environmental Assessment 2011 Final Design Complete October 2014 Construction Start July 2015 Construction Complete June 2017

slide-15
SLIDE 15

Keys to Design

  • Stream Restoration

– Restore 4 heavily damaged segments of Klingle Creek

  • Utilities

– Washington Gas: Full replacement of existing transmission line – DC Water: Rehab/replacement of sanitary sewer along trail

  • 2000+ LF of Cured-In-Place Pipe
  • Trail

– Permeable pavement (DDOT Green Infrastructure compliant) – Connections to Porter Street and Rock Creek Trail – Install lighting along trail

  • Retaining Walls

– Construct new retaining wall using salvaged stone – Repoint existing retaining walls

slide-16
SLIDE 16

Keys to Design (cont.)

  • Stormwater

– Install new drainage structures along trail – Install bioretention facility and bioswale – Install flood control structure

  • Urban Forestry/Landscaping

– Remove/replace hazardous trees – Re-establish Klingle Creek floodplain

slide-17
SLIDE 17

Gas Line Replacement

Phase 1 Phase 2 Phase 4 Phase 3

slide-18
SLIDE 18

Sanitary Sewer Rehab

slide-19
SLIDE 19

Stream Restoration

slide-20
SLIDE 20

STREAM RESTORATION

slide-21
SLIDE 21

November 2014

slide-22
SLIDE 22

February 2016

slide-23
SLIDE 23

February 2016

slide-24
SLIDE 24

April 2016

slide-25
SLIDE 25

May 2017

slide-26
SLIDE 26

July 2015

slide-27
SLIDE 27

September 2016

slide-28
SLIDE 28

March 2016

slide-29
SLIDE 29

November 2014

slide-30
SLIDE 30

January 2016

slide-31
SLIDE 31

April 2016

slide-32
SLIDE 32

May 2017

slide-33
SLIDE 33

November 2014

slide-34
SLIDE 34

April 2016

slide-35
SLIDE 35

May 2017

slide-36
SLIDE 36

RETAINING WALLS

Existing Conditions

slide-37
SLIDE 37

Retaining Walls

slide-38
SLIDE 38

East Wall

slide-39
SLIDE 39
slide-40
SLIDE 40
slide-41
SLIDE 41
slide-42
SLIDE 42
slide-43
SLIDE 43
slide-44
SLIDE 44
slide-45
SLIDE 45

Construction Progress – Retaining Walls

Existing Wall September 2016

February 2017

slide-46
SLIDE 46

Construction Progress – Retaining Walls

Existing Wall September 2016

May 2017

slide-47
SLIDE 47

INTERCHANGE CONNECTIONS

National Park Service & DDOT

slide-48
SLIDE 48

Porter Street Interchange

Stage 3 Stage 2 Stage 2A

slide-49
SLIDE 49
slide-50
SLIDE 50
slide-51
SLIDE 51
slide-52
SLIDE 52
slide-53
SLIDE 53
slide-54
SLIDE 54

TRAIL CONSTRUCTION

slide-55
SLIDE 55

Permeable Pavement

  • 0.7 miles
  • Permeable pavement

– Creates a reservoir to store stormwater on site – Green Infrastructure

slide-56
SLIDE 56

Trail Construction

Excavation to Subgrade Porous Stone Reservoir

slide-57
SLIDE 57

Construction Progress

  • Trail

Excavation Porous Base

slide-58
SLIDE 58

Lighting

  • 52 new LED light poles
  • Phillips Metroscape Fixture
  • Coordinated with NPS
  • Approved by the

International Dark-Sky Association

  • No ‘up-lighting’
slide-59
SLIDE 59

Future Challenges

  • Operations & Maintenance

– Regular vacuuming to maintain pavement – Winter safety – can’t use sand/salt – Bioretention/stormwater facility maintenance

  • Public safety

– Metropolitan Police / National Park Police jurisdictions – Vandalism – Falling trees – Neighborhood opposition to lighting

  • Access

– No access from Connecticut Avenue – Very limited street parking

slide-60
SLIDE 60

Trail Opening

  • June 24, 2017 Ribbon

Cutting Ceremony

– Attended by D.C. Mayor Muriel Bowser – Covered by multiple news outlets

  • Washington Post
  • WTOP
  • WAMU
slide-61
SLIDE 61

DDOT thanks

De sig n T e a m Co nstruc tio n T e a m

slide-62
SLIDE 62

Que stio ns

slide-63
SLIDE 63