The Klingle Valley Trail a Roads-to-trails Story Paul Hoffman - PowerPoint PPT Presentation

The Klingle Valley Trail a Roads-to-trails Story Paul Hoffman August 17, 2017 District Department of Transportation Infrastructure Project Management Division Agenda About DDOT Klingle Roads demise Public controversy builds


  1. The Klingle Valley Trail a “ Roads-to-trails” Story Paul Hoffman August 17, 2017 District Department of Transportation Infrastructure Project Management Division

  2. Agenda About DDOT Klingle Road’s demise Public controversy builds • DPW/DDOT way forward • Environmental documentation and design Draft EIS and EA • Designs • Construction Rebuild utilities • Stream Restoration • Green Infrastructure • Permeable Pavement •

  3. DDOT is Born May 2002 – DC Council passes the District Department of Transportation Establishment Act of 2002, creating a cabinet-level agency responsible for the management of transportation infrastructure and operations. Prior to the Act, transportation was managed under the Department of Public Works.

  4. Project Location

  5. Project Location

  6. The public weighs in… Source: Washington Post

  7. Right-of-way Gov’t of India NPS Tregaron Conservancy National Zoo WMATA

  8. Timeline… Original Klingle Road 1831 Current Klingle Road Alignment 1930s Klingle Road Closed to Public 1991 Klingle Road Feasibility Study 2001 Klingle Road Restoration Act 2003 Draft Environmental Impact Statement 2005 Klingle Road Sustainable Development 2008 Amendment Act Final Environmental Assessment 2011 Final Design Complete October 2014 Construction Start July 2015 Construction Complete June 2017

  9. Keys to Design Stream Restoration • – Restore 4 heavily damaged segments of Klingle Creek Utilities • – Washington Gas: Full replacement of existing transmission line – DC Water: Rehab/replacement of sanitary sewer along trail • 2000+ LF of Cured-In-Place Pipe Trail • – Permeable pavement (DDOT Green Infrastructure compliant) – Connections to Porter Street and Rock Creek Trail – Install lighting along trail Retaining Walls • – Construct new retaining wall using salvaged stone – Repoint existing retaining walls

  10. Keys to Design (cont.) Stormwater • – Install new drainage structures along trail – Install bioretention facility and bioswale – Install flood control structure Urban Forestry/Landscaping • – Remove/replace hazardous trees – Re-establish Klingle Creek floodplain

  11. Gas Line Replacement Phase 2 Phase 1 Phase 3 Phase 4

  12. Sanitary Sewer Rehab

  13. Stream Restoration

  14. STREAM RESTORATION

  15. November 2014

  16. February 2016

  17. February 2016

  18. April 2016

  19. May 2017

  20. July 2015

  21. September 2016

  22. March 2016

  23. November 2014

  24. January 2016

  25. April 2016

  26. May 2017

  27. November 2014

  28. April 2016

  29. May 2017

  30. Existing Conditions RETAINING WALLS

  31. Retaining Walls

  32. East Wall

  33. Construction Progress – February 2017 Retaining Walls Existing Wall September 2016

  34. Construction Progress – Retaining Walls May 2017 Existing Wall September 2016

  35. National Park Service & DDOT INTERCHANGE CONNECTIONS

  36. Porter Street Interchange Stage 2A Stage 3 Stage 2

  37. TRAIL CONSTRUCTION

  38. Permeable Pavement 0.7 miles • Permeable pavement • – Creates a reservoir to store stormwater on site – Green Infrastructure

  39. Trail Construction Porous Stone Reservoir Excavation to Subgrade

  40. Construction Progress - Trail Porous Base Excavation

  41. Lighting 52 new LED light poles • Phillips Metroscape Fixture • Coordinated with NPS • Approved by the • International Dark-Sky Association No ‘up-lighting’ •

  42. Future Challenges Operations & Maintenance • – Regular vacuuming to maintain pavement – Winter safety – can’t use sand/salt – Bioretention/stormwater facility maintenance Public safety • – Metropolitan Police / National Park Police jurisdictions – Vandalism – Falling trees – Neighborhood opposition to lighting Access • – No access from Connecticut Avenue – Very limited street parking

  43. Trail Opening June 24, 2017 Ribbon • Cutting Ceremony – Attended by D.C. Mayor Muriel Bowser – Covered by multiple news outlets • Washington Post • WTOP • WAMU

  44. DDOT thanks De sig n T e a m Co nstruc tio n T e a m

  45. Que stio ns

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.