THE DEEP HEAT MINING PROJECT Status February 2006 by Robert J. - - PowerPoint PPT Presentation

the deep heat mining project
SMART_READER_LITE
LIVE PREVIEW

THE DEEP HEAT MINING PROJECT Status February 2006 by Robert J. - - PowerPoint PPT Presentation

THE DEEP HEAT MINING PROJECT Status February 2006 by Robert J. Hopkirk 1 & Markus O. Hring 2 DEEP HEAT MINING Association (CH-8162 Steinmaur) 1 Polydynamics Engineering, CH-8708 Mnnedorf 2 Hring Geo-Project. CH-8162 Steinmaur M.O.


slide-1
SLIDE 1

M.O. Häring, R.J. Hopkirk 2006

THE DEEP HEAT MINING PROJECT

Status February 2006

by

Robert J. Hopkirk 1 & Markus O. Häring

2

DEEP HEAT MINING Association (CH-8162 Steinmaur)

1 Polydynamics Engineering, CH-8708 Männedorf 2 Häring Geo-Project. CH-8162 Steinmaur

slide-2
SLIDE 2

M.O. Häring, R.J. Hopkirk 2006

DHM PILOT PROJECT

The DHM Association was set up at the request of the Federal Office of Energy (FOE) and started work in 1996, a Swiss R & D group having been

active already then for 20 years. It defined and undertook the following tasks:

  • It would discover how feasible EGS now really was .............. and if it might

probably become useful in Switzerland.

  • If yes, it would find several possible EGS sites and choose one for a pilot plant,
  • It would initiate, obtain finance for and plan this first pilot plant, ensuring that EGS

technology has the best possible chance to prove itself.

  • If the technology proves itself, DHMA would continue to promote it and to

encourage the necessary R & D and the motivation of young specialists.

The FOE would provide “seeding money” for these tasks. Power plant construction and operation must be financed from private sources.

2.

slide-3
SLIDE 3

M.O. Häring, R.J. Hopkirk 2006

SITE SELECTION

Criteria for site selection for the PILOT PLANT:

  • Do the local utilities and population need its energy production and do they

welcome the plant in their midst?

  • Are the geological and geothermal conditions as favourable as they can be

to maximize the chance of success?

  • Is land available?
  • Is water available?
  • Will the project be environmentally acceptable in construction and in
  • peration?

3.

slide-4
SLIDE 4

M.O. Häring, R.J. Hopkirk 2006

SITE SELECTION - superposed maps of site-critical parameters:

geology, crustal thickness and regions of large scale heat demand

4.

slide-5
SLIDE 5

M.O. Häring, R.J. Hopkirk 2006

SITE SELECTION - Heat flow map

Data from: “Geothermal map of Switzerland”, Medici & Rybach 1995

5.

slide-6
SLIDE 6

M.O. Häring, R.J. Hopkirk 2006

SIGNIFICANT DECISIONS

IN ORDER TO HELP MAKE EGS MORE ATTRACTIVE EVEN AT THE PILOT STAGE : 1. To aim for co-generation of electrical energy and heat to ensure greater income 2. To use a hybrid surface plant if possible, combining geothermal and other sources These two decisions point to Basle as first and Geneva as second choice

  • Both have expanding District Heating networks currently:

– Basle: covering a maximum demand already over 300MW – Geneva: covering a maximum demand of ca. 45MW

  • Both offer additional energy sources (eg. incineration plants)
  • Aims for GEOTHERMAL generation alone in the first pilot plant:

– 3MW(e) & 20 MW(th)

6.

slide-7
SLIDE 7

M.O. Häring, R.J. Hopkirk 2006

Two sites in the Rhine graben

EU Project Soultz-sous-forêts DEEP HEAT MINING Project, Basel

7.

Some similarities are likely between these two sites

slide-8
SLIDE 8

M.O. Häring, R.J. Hopkirk 2006

SITE SITUATION

E-W section across the southern Rhine Graben

seismic data from Bonjer 1997 8.

slide-9
SLIDE 9

M.O. Häring, R.J. Hopkirk 2006

DEEP HEAT MINING Basel

  • geothermal power plant using EGS technology

for co-generation of electricity and heat

  • electricity und heat for 5'000 households:
  • 20 MW thermal power
  • 3 MW electrical power
  • annual reduction of CO2 emissions:
  • 40'000 t

5 - 6 km 1 - 1.5 km

stimulated Fracture system Monitoring w ell Heat exchanger

9.

slide-10
SLIDE 10

M.O. Häring, R.J. Hopkirk 2006

DHM Basel - how it fits in

Monitoring Station Otterbach

DHM Pilot Plant Kleinhüningen

Monitoring Station

  • St. Johann

District heating grid

Minimum target output:

  • geothermal power plant using EGS

technology for co-generation of electricity and heat for 5'000 households:

  • 20 MW thermal power
  • 3 MW electrical power
  • annual reduction of CO2 emissions 40 kt/a

Desired rock heat exchanger:

  • Initial rock temperature 200 - 230°C
  • Probable depth 5-6 km
  • Three-well unit system - well spacing at

bottom-hole 700 - 1000 m

10.

slide-11
SLIDE 11

M.O. Häring, R.J. Hopkirk 2006

Project plan

Power plant construction

2009 6

Development & Construction

3rd deep well System stimulation and testing

2008 5

Circulation testing

2007 4

2nd deep well Monitoring System & 1st deep well to 5‘000 m +

2006 2

Exploration

Pre-project studies & pilot hole, assuring finance & permissions

2001 1 3

11.

slide-12
SLIDE 12

M.O. Häring, R.J. Hopkirk 2006

Exploration Concept

12.

slide-13
SLIDE 13

M.O. Häring, R.J. Hopkirk 2006

Financial Risk Management

high risk level low risk level

Mio CHF

Exploration phase Construction phase Milestones

10 20 30 40 50 60 70 80 90

1 2 3 5 4 6

13.

slide-14
SLIDE 14

M.O. Häring, R.J. Hopkirk 2006

Geothermal & monitoring well sites

14.

slide-15
SLIDE 15

M.O. Häring, R.J. Hopkirk 2006

Vertical Seismic Profile (VSP) in OT2 Dec. 2004

15.

slide-16
SLIDE 16

M.O. Häring, R.J. Hopkirk 2006

First indications of Basement stress field orientation

induced fractures

Monitoring well Otterbach 2

main Rhinegraben flexure

induced breakouts

16.

slide-17
SLIDE 17

M.O. Häring, R.J. Hopkirk 2006

The main site at Kleinhüningen

Summer 2004 - Before site preparation January 2006 - concreting rig foundation 17.

slide-18
SLIDE 18

M.O. Häring, R.J. Hopkirk 2006

DHM Basel - some more numbers

Exploration phase: 2 geothermal wells 5’000 - 6‘000 m 3 new monitoring wells 250 - 600 m 3 monitoring stations in existing holes 600 - 2‘750 m Main (geothermal) wells: April 2006 - November 2007 All monitoring wells but one are complete Instrumentation is being tested & installed Budget limit for exploration phase:

  • ca. 60 Mio CHF = Risk capital

Budget estimate for entire pilot plant:

  • ca. 100 Mio CHF

KCA-Deutag T45 Drill Rig

18.

slide-19
SLIDE 19

M.O. Häring, R.J. Hopkirk 2006

Vision for the future: Swiss EGS power plants

Up to several tens of plants by 2050

  • varying sizes, varying depths according to site characteristics and local

energy demands .......

  • Heat exchanger depth ranges

4

  • 7

km

  • Source temperatures

150

  • 250

°C

  • Number of wells per site

3

  • 20
  • Power outputs from geothermal energy alone
  • if for el. generation only

5

  • 40

Mwe (i.e.: without hybrid cycles)

  • if for heat production only

30

  • 200

MWth

  • Specific Investment

2

  • 3

Mio CHF/MW installed

  • Generating costs
  • electrical energy

0.1

  • 0.2

CHF/kWh

  • heat

0.03

  • 0.06

CHF/kWh

  • CO2- Reduction (heat prod. only)

10

  • 200

kt/a

19.

slide-20
SLIDE 20

M.O. Häring, R.J. Hopkirk 2006

Closing remarks - a caution

Use of EGS technology outside geothermal anomalies is itself still a vision Nothing is certain until EGS is proven to be commercially viable Several successful pilot plants are needed so that: underground heat exchangers can be created

  • at any promising site;
  • of the right size to fulfill a local energy demand.

Much depends upon “getting it right first time” in these pilot plants and DHM Basel is one of these - for Switzerland it is all-important. Only then can EGS become accepted as an Available Energy Source

20.

slide-21
SLIDE 21

M.O. Häring, R.J. Hopkirk 2006

THE END

Thank you for your patience and attention!

For the current status of DHM Basel see www.geothermal.ch For other aspects see www.dhm.ch

21.