The City of Clare, A Case Study A Case Study of Ammonia Reduction - - PowerPoint PPT Presentation

the city of clare a case study
SMART_READER_LITE
LIVE PREVIEW

The City of Clare, A Case Study A Case Study of Ammonia Reduction - - PowerPoint PPT Presentation

The City of Clare, A Case Study A Case Study of Ammonia Reduction in a Lagoon Treatment System By John Holland The City of Clare WWTP The Clare WWTP was constructed in 1989. It is one of the few continuous flow through lagoons in


slide-1
SLIDE 1

The City of Clare, A Case Study

A Case Study of Ammonia Reduction in a Lagoon Treatment System By John Holland

slide-2
SLIDE 2

The City of Clare WWTP

 The Clare WWTP was constructed in 1989. It is one of

the few continuous flow through lagoons in Michigan.

 The plant consists of

 Bar Screen  Microscreens  3 Aerated Lagoons  2 Clarifiers run in series  FeCl2 and Polymer fed  UV Disinfection

slide-3
SLIDE 3

The City of Clare WWTP

 The average influent ammonia nitrogen is ranges from

15 to 20 mg/L.

 The average BOD ranges from 180 to 250 mg/L.  Average flow is 600,000 gallon per day.  Detention time is about 30 days in the lagoons.  During the winter water temperature can be as low as

slightly above 32F.

slide-4
SLIDE 4

The issue.

 The NPDES permit limit for Ammonia Nitrogen is 11.0

mg/L from May 1st to Sept. 30th.

 Even with this limit the Clare WWTP could not meet

this limit during the months of May, June and part of July.

 In 2008 the MDEQ issued a directive that the issue be

resolved.

slide-5
SLIDE 5

The Solutions Examined

 The City of Clare and their engineer of record, Goudie,

Fraser and Associates began to look at possible solutions.

 Solutions examined

 Mechanical Plant  Turning part of one of the lagoons into basically an

activated sludge pond.

 Air stripping  Fixed media

slide-6
SLIDE 6

Solution Selected

 The fixed media option was selected.

 Most cost effective  Clare WWTP only needed to lower ammonia nitrogen

by about 40% for 3 months of the year.

 Could use existing aeration blower as back-up.  Did not require extensive modification to the plant.  Lagoons were left in operation as units were installed.

slide-7
SLIDE 7

The Fixed Media

 The fixed media chosen was the ENTEX Technologies,

  • Inc. Webitat modules.

 A pilot study was performed in early spring to ensure

that the units would work under the conditions present at the Clare WWTP.

 The pilot study performed very well under the

conditions.

slide-8
SLIDE 8

The Pilot Plant

slide-9
SLIDE 9

The Process

 It was determined that 16 units would be installed.  The first 6 would be installed in lagoon #1 to enhance

BOD removal.

 There would be no changes to lagoon #2.  The final 10 units would be installed in lagoon #3

primary function would be ammonia nitrogen reduction.

slide-10
SLIDE 10

The Modules

slide-11
SLIDE 11
slide-12
SLIDE 12
slide-13
SLIDE 13

Installation

slide-14
SLIDE 14

Aeration System

slide-15
SLIDE 15

Piping and Control Valves

slide-16
SLIDE 16

Piping continued

slide-17
SLIDE 17

Lagoon Mixing

 The Webitat units did require additional mixing to

ensure proper removal.

 The 8 - 30 HP aerators were removed from lagoon #1

and replaced with 6 – 15 HP aerators.

 The diffuser system in lagoon #3 was determined to be

sufficient for mixing.

slide-18
SLIDE 18

Operation

 Units have controlled air flow  Control valves open once a week to full to scour the

media

slide-19
SLIDE 19

And now for the Important Stuff

Well how’s it working?

 Installed December 2011

slide-20
SLIDE 20

Ammonia Final Effluent 2012

1/1/2012 1/10/2012 1/19/2012 1/28/2012 2/6/2012 2/15/2012 2/24/2012 3/4/2012 3/13/2012 3/22/2012 3/31/2012 4/9/2012 4/18/2012 4/27/2012 5/6/2012 5/15/2012 5/24/2012 6/2/2012 6/11/2012 6/20/2012 6/29/2012 7/8/2012 7/17/2012 7/26/2012 8/4/2012 8/13/2012 8/22/2012 8/31/2012 9/9/2012 9/18/2012 9/27/2012 10/6/2012 10/15/2012 10/24/2012 11/2/2012 11/11/2012 11/20/2012 11/29/2012 12/8/2012 12/17/2012 12/26/2012 5 10 15 20 25 Series1

slide-21
SLIDE 21

Ammonia Final Effluent 2013

1/1/2013 1/10/2013 1/19/2013 1/28/2013 2/6/2013 2/15/2013 2/24/2013 3/5/2013 3/14/2013 3/23/2013 4/1/2013 4/10/2013 4/19/2013 4/28/2013 5/7/2013 5/16/2013 5/25/2013 6/3/2013 6/12/2013 6/21/2013 6/30/2013 7/9/2013 7/18/2013 7/27/2013 8/5/2013 8/14/2013 8/23/2013 9/1/2013 9/10/2013 9/19/2013 9/28/2013 10/7/2013 10/16/2013 10/25/2013 11/3/2013 11/12/2013 11/21/2013 11/30/2013 12/9/2013 12/18/2013 12/27/2013 2 4 6 8 10 12 14 16 18 Series1

slide-22
SLIDE 22

Ammonia Nitrogen 2014

1/1/2014 1/10/2014 1/19/2014 1/28/2014 2/6/2014 2/15/2014 2/24/2014 3/5/2014 3/14/2014 3/23/2014 4/1/2014 4/10/2014 4/19/2014 4/28/2014 5/7/2014 5/16/2014 5/25/2014 6/3/2014 6/12/2014 6/21/2014 6/30/2014 7/9/2014 7/18/2014 7/27/2014 8/5/2014 8/14/2014 8/23/2014 9/1/2014 9/10/2014 9/19/2014 9/28/2014 10/7/2014 10/16/2014 10/25/2014 11/3/2014 11/12/2014 11/21/2014 11/30/2014 12/9/2014 12/18/2014 12/27/2014 5 10 15 20 25 30 Series1

slide-23
SLIDE 23

2014

 Finally a cold winter to really test the system out.  How will it perform? – stay tuned!!!

slide-24
SLIDE 24

Questions