the city of clare a case study
play

The City of Clare, A Case Study A Case Study of Ammonia Reduction - PowerPoint PPT Presentation

The City of Clare, A Case Study A Case Study of Ammonia Reduction in a Lagoon Treatment System By John Holland The City of Clare WWTP The Clare WWTP was constructed in 1989. It is one of the few continuous flow through lagoons in


  1. The City of Clare, A Case Study A Case Study of Ammonia Reduction in a Lagoon Treatment System By John Holland

  2. The City of Clare WWTP  The Clare WWTP was constructed in 1989. It is one of the few continuous flow through lagoons in Michigan.  The plant consists of  Bar Screen  Microscreens  3 Aerated Lagoons  2 Clarifiers run in series  FeCl 2 and Polymer fed  UV Disinfection

  3. The City of Clare WWTP  The average influent ammonia nitrogen is ranges from 15 to 20 mg/L.  The average BOD ranges from 180 to 250 mg/L.  Average flow is 600,000 gallon per day.  Detention time is about 30 days in the lagoons.  During the winter water temperature can be as low as slightly above 32F.

  4. The issue.  The NPDES permit limit for Ammonia Nitrogen is 11.0 mg/L from May 1 st to Sept. 30th.  Even with this limit the Clare WWTP could not meet this limit during the months of May, June and part of July.  In 2008 the MDEQ issued a directive that the issue be resolved.

  5. The Solutions Examined  The City of Clare and their engineer of record, Goudie, Fraser and Associates began to look at possible solutions.  Solutions examined  Mechanical Plant  Turning part of one of the lagoons into basically an activated sludge pond.  Air stripping  Fixed media

  6. Solution Selected  The fixed media option was selected.  Most cost effective  Clare WWTP only needed to lower ammonia nitrogen by about 40% for 3 months of the year.  Could use existing aeration blower as back-up.  Did not require extensive modification to the plant.  Lagoons were left in operation as units were installed.

  7. The Fixed Media  The fixed media chosen was the ENTEX Technologies, Inc. Webitat modules.  A pilot study was performed in early spring to ensure that the units would work under the conditions present at the Clare WWTP.  The pilot study performed very well under the conditions.

  8. The Pilot Plant

  9. The Process  It was determined that 16 units would be installed.  The first 6 would be installed in lagoon #1 to enhance BOD removal.  There would be no changes to lagoon #2.  The final 10 units would be installed in lagoon #3 primary function would be ammonia nitrogen reduction.

  10. The Modules

  11. Installation

  12. Aeration System

  13. Piping and Control Valves

  14. Piping continued

  15. Lagoon Mixing  The Webitat units did require additional mixing to ensure proper removal.  The 8 - 30 HP aerators were removed from lagoon #1 and replaced with 6 – 15 HP aerators.  The diffuser system in lagoon #3 was determined to be sufficient for mixing.

  16. Operation  Units have controlled air flow  Control valves open once a week to full to scour the media

  17. And now for the Important Stuff  Well how’s it working?  Installed December 2011

  18. Ammonia Final Effluent 2012 20 25 10 15 0 5 1/1/2012 1/10/2012 1/19/2012 1/28/2012 2/6/2012 2/15/2012 2/24/2012 3/4/2012 3/13/2012 3/22/2012 3/31/2012 4/9/2012 4/18/2012 4/27/2012 5/6/2012 5/15/2012 5/24/2012 6/2/2012 6/11/2012 6/20/2012 6/29/2012 7/8/2012 7/17/2012 7/26/2012 8/4/2012 8/13/2012 8/22/2012 8/31/2012 9/9/2012 9/18/2012 9/27/2012 10/6/2012 10/15/2012 10/24/2012 11/2/2012 11/11/2012 11/20/2012 11/29/2012 12/8/2012 12/17/2012 12/26/2012 Series1

  19. Ammonia Final Effluent 2013 10 14 16 18 12 0 4 6 8 2 1/1/2013 1/10/2013 1/19/2013 1/28/2013 2/6/2013 2/15/2013 2/24/2013 3/5/2013 3/14/2013 3/23/2013 4/1/2013 4/10/2013 4/19/2013 4/28/2013 5/7/2013 5/16/2013 5/25/2013 6/3/2013 6/12/2013 6/21/2013 6/30/2013 7/9/2013 7/18/2013 7/27/2013 8/5/2013 8/14/2013 8/23/2013 9/1/2013 9/10/2013 9/19/2013 9/28/2013 10/7/2013 10/16/2013 10/25/2013 11/3/2013 11/12/2013 11/21/2013 11/30/2013 12/9/2013 12/18/2013 12/27/2013 Series1

  20. Ammonia Nitrogen 2014 20 25 30 10 15 0 5 1/1/2014 1/10/2014 1/19/2014 1/28/2014 2/6/2014 2/15/2014 2/24/2014 3/5/2014 3/14/2014 3/23/2014 4/1/2014 4/10/2014 4/19/2014 4/28/2014 5/7/2014 5/16/2014 5/25/2014 6/3/2014 6/12/2014 6/21/2014 6/30/2014 7/9/2014 7/18/2014 7/27/2014 8/5/2014 8/14/2014 8/23/2014 9/1/2014 9/10/2014 9/19/2014 9/28/2014 10/7/2014 10/16/2014 10/25/2014 11/3/2014 11/12/2014 11/21/2014 11/30/2014 12/9/2014 12/18/2014 12/27/2014 Series1

  21. 2014  Finally a cold winter to really test the system out.  How will it perform? – stay tuned!!!

  22. Questions

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend