Testing Goals and Notes Sarah Lockwitz, FNAL Mini-Review Planned for - - PowerPoint PPT Presentation
Testing Goals and Notes Sarah Lockwitz, FNAL Mini-Review Planned for - - PowerPoint PPT Presentation
Testing Goals and Notes Sarah Lockwitz, FNAL Mini-Review Planned for July 28, 2016 Tentative Charge: 1. Is the proposed setup and test plan sufficient for evaluating the proposed ProtoDUNE-SP field cage design with regard to high voltage?
Mini-Review Planned for July 28, 2016
- Tentative Charge:
- 1.
Is the proposed setup and test plan sufficient for evaluating the proposed ProtoDUNE-SP field cage design with regard to high voltage?
- 2.
Are there any electrical or mechanical problems with the design of the test apparatus?
- 3.
Are there any safety issues to be addressed?
- 4.
Does the TSW contain the needed resources to do this?
- Tentative Schedule:
- 1.
Overview and Motivation for the Test (20 min+10)
- 2.
Plan for ProtoDUNE-SP HV (20+10 min) (Bo or Francesco)
- 3.
Technical Review: Mechanical Specifications (Jeff) (25+15 min)
- 4.
Technical Review: Electrical Specifications (Glenn) (25+15 min)
- 5.
Cryogenics and plan for instrumentation (Alan with input from WM on camera)
- 6.
Phase II Plans (Cheng-Ju) (20 min)
2
Goals of Testing: Ensure that the ProtoDUNE design is a success
- Expose any weaknesses so that we can fix them
- Test the high voltage features of the ProtoDUNE design
- The beam plug is a challenging feature of the design
- Beam plug must be tested in the field cage
- There are enough untested features of the field cage that testing everything at once
would make it difficult to determine the source of instabilities (if they arise)
- Test the field cage without the beam plug first. Characterize performance.
- Test the field cage with the beam plug to understand the beam plug performance.
3
Testing Goals & Plans
- We cannot do a full size test of ProtoDUNE
- We will do a partial & scaled test in 35t. (Size effects?)
- Cathode at full voltage (-180 kV), 10 TPC stages at correct voltage, anode plane at -47 kV, resistor chain to ground.
- TPC has 4 parallel chains of 5.5 GΩ (11 stages x 500 MΩ. The 500 MΩ is from 2 1 GΩ resistors in parallel
between each profile)
- Resistors will have surge protection. The last stage beyond the TPC is under development.
- Test interfaces.
4
180 171 162 153 147 171 162 153 147
- Really want to evaluate these edges.
- First one is at 177 kV
- To get that voltage w/o the tail of resistors, one
really gets into large tube to tube ΔVs (~20 kV)
What is a successful test?
- We want the HV+TPC design to not adversely affect data-taking at ProtoDUNE
- TPC should be robust (no breakage of field cage from HV)
- We shouldn’t have instabilities that affect data-taking
- HV system should not create troublesome noise for the DAQ (filter can be tested separately)*
- System should not create light that adversely affects data-taking
- Have not found this to be an issue in a non-broken TPC
- Might want to put a PMT in the cryostat
- Should not have freq. breakdowns (relative term, aim for zero).
5
Let’s think about this…it would be good to have an answer by the review
Rough Schedule
- July:
- Complete design of field cage components
including TPC circuit (resistors & varistors)
- Order long lead time materials
- Mini-Review week of July 25th
- Fabricate parts
- August:
- Remove 35t TPC
- Continue fabrication
- Test fit?
- Clean pieces
- September: Install PhaseI HV Test
- October: Purge, cool down & fill cryostat
- November: Perform Test
- December: Transfer LAr to LAPD. Warm up cryostat.
Takes a little over 1 month
- January: Install Phase II
- February: Purge cooldown & fill
- March: Test Phase II
6
Monitoring Ideas
- Toroid: Polarity of first pulse tells you where the
voltage drop was
- Pick off/Field cage termination (required port)
- HV Supply: Heinzinger offers much better current
readout ability (~100 nA vs 10s uA with a Glassman)
- Camera: M. Kordosky & group (required window(s)
and/or feedthrough ports)
- PMT/SiPMs? (required ports)
- Any other ports needed?
- Not planned at the moment: Antenna,
microphones
7
Blips: Toroid and FCT signals while running
- Do not cause trips
- Can affect data-taking (shield plane reduces this)
- 35t and another experiment have seen them
- Both positive & negative polarities
- Small test stand has not.
Not a deal breaker at this time, but something to be aware of.
Membrane Performance?
- The proposed test does not evaluate the effect of
the TPC+cryostat membrane performance. This should be a low risk (40 cm away).
- The 35t was done by a Japanese company and
has a different profile than what Proto-DUNE will have (GTT).
- We have some GTT profile onsite. We have
some that people are willing to allow us to test.
- If there’s a strong motivation, we can test them
in a small test vessel we have onsite with access to TPC-quality argon. Would only be able to test up to ~100 kV at the moment (likely < 1 inch). We would have to pay for the argon.
8
A Note on Cable Terminations
- I saw Bo has requested DS 2134 cable.
- I am sure people already have ideas
about cable terminations.
- If anyone would like an additional idea,
we’ve used this technique for cable terminations at FNAL. Tevatron used them for decades.
- I’m willing to share parts, help with
drawings, etc. if anyone wants to use this.
9
Cleaning G10/FR4
- An option for cleaning the G10/FR4
parts is an ultrasonic bath the TD at FNAL has
- The parts in the photo are ~2.5 m
in length
- On the G10, the cleaner used was
Elba-Clean 65 (total cost to arrive at the lab was ~$1k)
- If there’s interest, I can ask if this is
available to use at the end of the summer.
10