testing goals and notes
play

Testing Goals and Notes Sarah Lockwitz, FNAL Mini-Review Planned for - PowerPoint PPT Presentation

Testing Goals and Notes Sarah Lockwitz, FNAL Mini-Review Planned for July 28, 2016 Tentative Charge: 1. Is the proposed setup and test plan sufficient for evaluating the proposed ProtoDUNE-SP field cage design with regard to high voltage?


  1. Testing Goals and Notes Sarah Lockwitz, FNAL

  2. Mini-Review Planned for July 28, 2016 • Tentative Charge: • 1. Is the proposed setup and test plan sufficient for evaluating the proposed ProtoDUNE-SP field cage design with regard to high voltage? • 2. Are there any electrical or mechanical problems with the design of the test apparatus? • 3. Are there any safety issues to be addressed? • 4. Does the TSW contain the needed resources to do this? • Tentative Schedule: • 1. Overview and Motivation for the Test (20 min+10) • 2. Plan for ProtoDUNE-SP HV (20+10 min) (Bo or Francesco) • 3. Technical Review: Mechanical Specifications (Jeff) (25+15 min) • 4. Technical Review: Electrical Specifications (Glenn) (25+15 min) • 5. Cryogenics and plan for instrumentation (Alan with input from WM on camera) • 6. Phase II Plans (Cheng-Ju) (20 min) 2

  3. Goals of Testing: Ensure that the ProtoDUNE design is a success • Expose any weaknesses so that we can fix them • Test the high voltage features of the ProtoDUNE design • The beam plug is a challenging feature of the design • Beam plug must be tested in the field cage • There are enough untested features of the field cage that testing everything at once would make it difficult to determine the source of instabilities (if they arise) • Test the field cage without the beam plug first. Characterize performance. • Test the field cage with the beam plug to understand the beam plug performance. 3

  4. Testing Goals & Plans • We cannot do a full size test of ProtoDUNE • We will do a partial & scaled test in 35t. (Size effects?) • Cathode at full voltage (-180 kV), 10 TPC stages at correct voltage, anode plane at -47 kV, resistor chain to ground. • TPC has 4 parallel chains of 5.5 G Ω (11 stages x 500 M Ω . The 500 M Ω is from 2 1 G Ω resistors in parallel between each profile) • Resistors will have surge protection. The last stage beyond the TPC is under development. • Test interfaces. •Really want to evaluate these edges. •First one is at 177 kV •To get that voltage w/o the tail of resistors, one really gets into large tube to tube Δ Vs (~20 kV) 147 153 162 171 180 171 162 153 147 4

  5. Let’s think about this…it would be good to have an What is a successful test? answer by the review • We want the HV+TPC design to not adversely affect data-taking at ProtoDUNE • TPC should be robust (no breakage of field cage from HV) • We shouldn’t have instabilities that affect data-taking • HV system should not create troublesome noise for the DAQ (filter can be tested separately)* • System should not create light that adversely affects data-taking • Have not found this to be an issue in a non-broken TPC • Might want to put a PMT in the cryostat • Should not have freq. breakdowns (relative term, aim for zero). 5

  6. Rough Schedule • July: • Clean pieces • Complete design of field cage components • September: Install PhaseI HV Test including TPC circuit (resistors & varistors) • October: Purge, cool down & fill cryostat • Order long lead time materials • November: Perform Test • Mini-Review week of July 25th • December: Transfer LAr to LAPD. Warm up cryostat. • Fabricate parts Takes a little over 1 month • August: • January: Install Phase II • Remove 35t TPC • February: Purge cooldown & fill • Continue fabrication • March: Test Phase II • Test fit? 6

  7. Blips: Toroid and FCT signals while running Do not cause trips • Monitoring Ideas Can affect data-taking (shield plane reduces this) • 35t and another experiment have seen them • Both positive & negative polarities • • Toroid: Polarity of first pulse tells you where the Small test stand has not. • voltage drop was Not a deal breaker at this time, but something to be aware of. • Pick off/Field cage termination (required port) • HV Supply: Heinzinger offers much better current readout ability (~100 nA vs 10s uA with a Glassman) • Camera: M. Kordosky & group (required window(s) and/or feedthrough ports) • PMT/SiPMs? (required ports) • Any other ports needed? • Not planned at the moment: Antenna, microphones 7

  8. Membrane Performance? • The proposed test does not evaluate the effect of the TPC+cryostat membrane performance. This should be a low risk (40 cm away). • The 35t was done by a Japanese company and has a different profile than what Proto-DUNE will have (GTT). • We have some GTT profile onsite. We have some that people are willing to allow us to test. • If there’s a strong motivation, we can test them in a small test vessel we have onsite with access to TPC-quality argon. Would only be able to test up to ~100 kV at the moment (likely < 1 inch). We would have to pay for the argon. 8

  9. A Note on Cable Terminations • I saw Bo has requested DS 2134 cable. • I am sure people already have ideas about cable terminations. • If anyone would like an additional idea, we’ve used this technique for cable terminations at FNAL. Tevatron used them for decades. • I’m willing to share parts, help with drawings, etc. if anyone wants to use this. 9

  10. Cleaning G10/FR4 • An option for cleaning the G10/FR4 parts is an ultrasonic bath the TD at From T. Strauss FNAL has • The parts in the photo are ~2.5 m in length • On the G10, the cleaner used was Elba-Clean 65 (total cost to arrive at the lab was ~$1k) • If there’s interest, I can ask if this is available to use at the end of the summer. 10

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend