Supporting a Clean Energy Future Supporting a Clean Energy Future - - PowerPoint PPT Presentation

supporting a clean energy future supporting a clean
SMART_READER_LITE
LIVE PREVIEW

Supporting a Clean Energy Future Supporting a Clean Energy Future - - PowerPoint PPT Presentation

Supporting a Clean Energy Future Supporting a Clean Energy Future David H. Boguslawski VP Transmission Strategy & Operations Northeast Utilities NE Electricity Restructuring Roundtable Boston, MA Dec. 09, 2011 1 A comprehensive


slide-1
SLIDE 1

1

Supporting a Clean Energy Future Supporting a Clean Energy Future

David H. Boguslawski VP – Transmission Strategy & Operations Northeast Utilities NE Electricity Restructuring Roundtable Boston, MA

  • Dec. 09, 2011
slide-2
SLIDE 2

2

A comprehensive approach is needed to meet New A comprehensive approach is needed to meet New England England’ ’s s RPS RPS and carbon goals and carbon goals

New England New England’ ’s goals increase s goals increase

  • ver time
  • ver time

Closing the gap will require a Closing the gap will require a 3 3-

  • part approach

part approach

  • 1. Managing consumption
  • 2. Importing clean,

economic power

  • 3. Building domestic

renewable resources and the enabling transmission

5,000 10,000 15,000 20,000 25,000

Gigawatt Hours (GWh) 2009 2013 2017 2020

Class I Renewable Goals

Existing Class 1 Renewables

Gap

slide-3
SLIDE 3

3

The Northern Pass Project The Northern Pass Project -

  • Description

Description

  • Delivers enough renewable, low-carbon

energy to power 1 million homes

  • US segment owned jointly by NU and

NSTAR

  • Quebec segment owned by HQ-

TransEnergie

  • Transmission cost-based rates using a

“participant pays” model – Revenue requirements paid for by Hydro-Quebec US – Transmission rights assigned to Hydro-Quebec US

  • Operation by ISO-New England
  • Target in-service date is 2016

1,200 MW HVDC Line from Hydro- Quebec to central NH 1,200 MW HVDC Line from Hydro- Quebec to central NH AC line from central NH to NE transmission grid AC line from central NH to NE transmission grid

slide-4
SLIDE 4

4

The Northern Pass Project The Northern Pass Project -

  • Schedule

Schedule

May 2009 FERC approval of Project structure Dec 2009 FERC Order on rehearing requests Oct 2010 Executed Transmission Service Agreement with HQ Hydro Renewable Energy Oct 2010 DOE Presidential Permit application Feb 2011 FERC approves transmission service agreement Mar 2011 DOE holds 7 scoping meetings in NH Jun 2011 U.S. Forest Service application 2012-2013 DOE permitting process 2012-2013 ACOE permitting process 2012-2013 New Hampshire permitting process (Site Evaluation Committee) 2014-2016 Proposed construction Ongoing outreach efforts

= Completed

slide-5
SLIDE 5

5

The Northern Pass Project The Northern Pass Project -

  • Benefits

Benefits

Economic Benefits

  • Annual New England energy savings of $200 - $325 million
  • Creates 1,200 jobs
  • Provides $22 - $27 million in annual taxes

Environmental Benefits

  • Reduces carbon dioxide emissions up to 5 million tons a year
  • Complements the development and operation of local

renewable resources

Reliability Benefits

  • Provides new capacity
  • Increases fuel diversity (not natural gas)
slide-6
SLIDE 6

6

New England New England’ ’s s RPS RPS gap is large and growing gap is large and growing

Likely (Existing) Renewables in ISO Queue at 30%* The Problem (Additional need)

Gigawatt Hours (GWh) Surplus 5,000 10,000 15,000 20,000 25,000 2009 2013 2017 2020 “Demand” for Class I Renewables

Potential Gap = 12,700 GWh Project Lead Time

5 - 8 years

  • Based on ISO historical observation

RSP 2010, pp 132-133

slide-7
SLIDE 7

7

New England New England’ ’s supply options s supply options Cost

Options for 12,700 GWh Cost 36 biomass plants at 50 - MW each with an 80% capacity factor (Wood is not scalable)

$ 5.5 Billion plus $ T

1,074 3-MW of offshore windmills at 45% capacity

$22.6 Billion plus $ T

12,078 MW of solar panels at 12% capacity factor

$64 Billion plus $ t

1,380 3-MW of onshore windmills at 35% capacity factor

$9.4 Billion plus $ T

slide-8
SLIDE 8

8

Wind Zones Load centers

  • Wind Power = Air Density x

Rotor Area x (Wind Speed)3

  • ISO-NE “Governors’ Blueprint”

study verifies need for more transmission

  • ME-NH and North-South

interface limitations must be addressed

  • NESCOE focus on regional

procurement of renewable energy

New England New England’ ’s best onshore wind s best onshore wind is remote from load centers is remote from load centers

North-South Interface

slide-9
SLIDE 9

9

Transmission to support Transmission to support renewables renewables has many dimensions has many dimensions

We have:

  • Collaborated with NE Transmission

Owners

  • Reached out to wind developers

and regulators

  • Analyzed wind sites and routing
  • ptions
  • Studied NE system constraints
  • Assessed business structures
  • Reviewed financing requirements
  • Identified consumer benefits and

impacts

There are many challenges:

  • Changes to public policy
  • Project scope, size and products
  • Open access compliance
  • Project creditworthiness
  • Start-up process/timing
  • Cost recovery and allocation
  • Regional planning process
  • Operations/maintenance
  • Operational priority
  • “Service Territory” issues
slide-10
SLIDE 10

10

Summary Summary

  • A comprehensive approach is needed

to meet New England’s clean energy goals

  • Transmission infrastructure will be

needed to…

  • Import clean, economic power from

Canada

  • Develop domestic wind resources
  • NU will continue to promote solutions

to public policy goals that are best for

  • ur customers
slide-11
SLIDE 11

This presentation was given at the 12.9.2011 New England Electricity Restructuring Roundtable, “Renewable Energy-Related Transmission for New Englanders: by Land and by Sea” convened and moderated by Raab Associates, Ltd.