STX FRANCE From Design To Construction of Offshore Wind Projects Pierre-Paul LACAS Hydrodynamic and Structural Engineer Technical manager for floating offshore wind projects pierre-paul.lacas@stxeurope.com SUMMARY Co Company stru


slide-1
SLIDE 1

STX FRANCE

From Design To Construction of Offshore Wind Projects

Pierre-Paul LACAS – Hydrodynamic and Structural Engineer Technical manager for floating offshore wind projects pierre-paul.lacas@stxeurope.com

slide-2
SLIDE 2

SUMMARY

Co Company stru tructure Ship ip build ilding back ckground Offshore e en ener ergy busin ines ess unit it References R&D programs

slide-3
SLIDE 3

ABOUT STX FRANCE…

slide-4
SLIDE 4

LOCATION

22 janvier 2018

Saint Nazaire, France Loire estuary 60km from Nantes

slide-5
SLIDE 5

COMPANY STRUCTURE

3 Business Units OFFSHORE ENERGY

Fincantieri (~50 + 1%) Naval Group (~14%) French state (~33%) Others (2%)

SHIPS SERVICES

slide-6
SLIDE 6

MAIN FIGURES

1,400 t of hoisting capacities 65,000 tons/year transformed steel Th The e lar argest er erectio ion do dock in n Eur Europ

  • pe

2,600 employees 6,000 persons on site 1 sheltered workshop with 2x60t hoisting capacity 6000 m² assembly area 1 sheltered painting workshop Of Offshor

  • re pr

proj

  • jects ded

dedic icated wor

  • rkshop
  • ps
slide-7
SLIDE 7

CORE BUSINESS

De Desig ign and and build build com

  • mple

lex na naval l str tructures  Integrate  Manage interfaces  Industrialize  Assemble  Commission

slide-8
SLIDE 8

OFFSHORE ENERGY BUSINESS UNIT

slide-9
SLIDE 9

MARKET AND ACTIVITIES

22 janvier 2018

  • Electrical Offshore Substations

Sc Scop

  • pe EP

EPCI for:

  • r:
  • Substructures and Foundations

Control and loop

Al All for

  • r on
  • ne

e and and on

  • ne

e for

  • r al

all !

FEED

General Arrangement

BASIC DESIGN

Architecture

DETAILED DESIGN

Advanced

T&I

Vessel Crane capacity

CONSTRUCTION

Strategy Material

INDUSTRIALIZATION

Workshop drawings

Effi ficie ient desi design by y mul multi-dis iscip iplin inary con

  • nstrain

int integr gratio ion

slide-10
SLIDE 10

REFERENCES (1/2)

22 janvier 2018

Deliv livery: 2011 Site: Onshore jacket prototype for Haliade 6MW Client: Alstom Site: Le Carnet - FRA Scop

  • pe: EPCI

Deliv livery: 2014 Site: Westermost Rough – UK: OSS 210MW (1200t) + post-pilled jacket (1500t) Clie ient: DONG Energy Scop

  • pe: EPC
slide-11
SLIDE 11

REFERENCES (2/2)

22 janvier 2018

Deliv livery: 2018 Site: Arkona – GER: OSS 385MW (4000t) + pre-pilled jacket (1800t) Clie ient: EON, Statoil, 50Hz Scop

  • pe: EPCIM

Deliv livery: 2018 Site: Rentel – BEL: OSS 309MW (1200t) + monopile (1600t) Clie ient: Otary Scop

  • pe: EPCI
slide-12
SLIDE 12

ENGINEERING AND FABRICATION OF INSTALLATION AIDS

22 janvier 2018

  • Lift

Lifting of

  • f top
  • pside  Spreader bar
  • Pile

ile dr driving  Template, follower

  • Bar

arge Transport  Sea fastening design

slide-13
SLIDE 13

COST REDUCTIONS BY INNOVATION AND DEVELOPMENT

slide-14
SLIDE 14

R&D

  • Proj
  • ject Par

artnership ip

  • In

n Ho Hous use De Develo lopment

slide-15
SLIDE 15

R&D PR PROJECTS Prod

  • duct

Perio iod Subje ubject

FONDEOL Jacket 2010-2011 Comparison of various foundation types & tank trials POSEOL Vessel 2010-2011 Installation vessel FONDEOL 2 Jacket 2011-2012 Environmental impact & monitoring AG4 Jacket 2012 DNV certification of jacket concept CHARGEOL Jacket 2012-2016 Complex loading applied on offshore structure SURFEOL Jacket 2013-2015 Measurement and maintenance ADUSCOR Jacket 2013-2015 Corrosion protection HYSMAR Jacket, Tidal 2013-2014 Hydrodynamic modeling APSTRAM Jacket 2013-2016 HLE material WATTEOL 500 OSS 2014-2015 DNV certification of OSS stress skin design ORCA Tidal 2015-2016 Tidal turbine foundation FEOS Floating OSS 2015-2017 Floater benchmarking and FEED JACKCLASS Jacket 2016 Fast track design of OSS jacket OMDYN 1 & 2 Cables 2016-2019 Dynamic cable for floating structure DIME Environmental loads 2017-2019 MetOcean data and extrem loads modeling JIP DNVGL Floating 2016-2018 Coupled analysis of floating wind turbine ROS 3D Pile 2017-2020 Soil FE modeling MONOCLASS Monopile 2017 Fast track design of MP SEEOS OSS 2017-2018 OSS standardization

slide-16
SLIDE 16

E.G. JACKET FOUNDATIONS

22 janvier 2018

Fabrication constraints

Fond marin

HENSEVELIE

Pile bottom

Pile Top

FZ

FX

M

Y

HAFFOUIL

L.

Pile design (axial + lateral)  OSS

METHODOLOGY AND TOOL DE DEVELOPMENT: -20 20% prim primary ry ste teel

AG4

STX Concept certification (DNV)

AG3 Ship impact SCF  WTG Clustering

slide-17
SLIDE 17

Semi-submersible concept

E.G. SEEOS CONCEPT (certification 2018) – PATENT PENDING

22 janvier 2018

Standardize the “OSS function” and provide customized add-ons

T1 T2 T3

  • 20%

% CAP CAPEX, OP OPEX, Co Cons nstruction ti time