STX FRANCE From Design To Construction of Offshore Wind Projects Pierre-Paul LACAS Hydrodynamic and Structural Engineer Technical manager for floating offshore wind projects pierre-paul.lacas@stxeurope.com SUMMARY Co Company stru


  1. STX FRANCE From Design To Construction of Offshore Wind Projects Pierre-Paul LACAS – Hydrodynamic and Structural Engineer Technical manager for floating offshore wind projects pierre-paul.lacas@stxeurope.com

  2. SUMMARY Co Company stru tructure Ship ip build ilding back ckground Offshore e en ener ergy busin ines ess unit it References R&D programs

  3. ABOUT STX FRANCE…

  4. LOCATION Saint Nazaire, France Loire estuary 60km from Nantes 22 janvier 2018

  5. COMPANY STRUCTURE Fincantieri (~50 + 1%) Naval Group (~14%) 3 Business Units French state (~33%) Others (2%) OFFSHORE SHIPS SERVICES ENERGY

  6. MAIN FIGURES 2,600 employees 6,000 persons on site Th The e lar argest er erectio ion do dock in n Eur Europ ope 1,400 t of hoisting capacities 65,000 tons/year transformed steel Of Offshor ore pr proj ojects ded dedic icated wor orkshop ops 1 sheltered workshop with 2x60t hoisting capacity 6000 m² assembly area 1 sheltered painting workshop

  7. CORE BUSINESS De Desig ign and and build build com omple lex na naval l str tructures  Manage interfaces  Integrate  Industrialize  Assemble  Commission

  8. OFFSHORE ENERGY BUSINESS UNIT

  9. MARKET AND ACTIVITIES Sc Scop ope EP EPCI for: or: • Electrical Offshore Substations • Substructures and Foundations Al All for or on one e and and on one e for or al all ! FEED BASIC DESIGN DETAILED DESIGN INDUSTRIALIZATION General Arrangement CONSTRUCTION Architecture T&I Advanced Workshop drawings Strategy Material 22 janvier 2018 Vessel Control and loop Crane capacity Effi ficie ient desi design by y mul multi-dis iscip iplin inary con onstrain int integr gratio ion

  10. REFERENCES (1/2) Deliv livery: 2014 Site: Westermost Rough – UK: OSS 210MW (1200t) + post-pilled jacket (1500t) Clie ient: DONG Energy Scop ope: EPC Deliv livery: 2011 Site: Onshore jacket prototype for Haliade 6MW Client: Alstom Site: Le Carnet - FRA Scop ope: EPCI 22 janvier 2018

  11. REFERENCES (2/2) Deliv livery: 2018 Site: Arkona – GER: OSS 385MW (4000t) + pre-pilled jacket (1800t) Clie ient: EON, Statoil, 50Hz Scop ope: EPCIM Deliv livery: 2018 Site: Rentel – BEL: OSS 309MW (1200t) + monopile (1600t) Clie ient: Otary Scop ope: EPCI 22 janvier 2018

  12. ENGINEERING AND FABRICATION OF INSTALLATION AIDS • opside  Spreader bar Lift Lifting of of top • driving  Template, follower Pile ile dr • arge Transport  Sea fastening design Bar 22 janvier 2018

  13. COST REDUCTIONS BY INNOVATION AND DEVELOPMENT

  14. R&D • Proj oject Par artnership ip • In n Ho Hous use De Develo lopment

  15. R&D PR PROJECTS Prod oduct Perio iod Subje ubject FONDEOL Jacket 2010-2011 Comparison of various foundation types & tank trials POSEOL Vessel 2010-2011 Installation vessel FONDEOL 2 Jacket 2011-2012 Environmental impact & monitoring AG4 Jacket 2012 DNV certification of jacket concept CHARGEOL Jacket 2012-2016 Complex loading applied on offshore structure SURFEOL Jacket 2013-2015 Measurement and maintenance ADUSCOR Jacket 2013-2015 Corrosion protection HYSMAR Jacket, Tidal 2013-2014 Hydrodynamic modeling APSTRAM Jacket 2013-2016 HLE material WATTEOL 500 OSS 2014-2015 DNV certification of OSS stress skin design ORCA Tidal 2015-2016 Tidal turbine foundation FEOS Floating OSS 2015-2017 Floater benchmarking and FEED JACKCLASS Jacket 2016 Fast track design of OSS jacket OMDYN 1 & 2 Cables 2016-2019 Dynamic cable for floating structure DIME Environmental loads 2017-2019 MetOcean data and extrem loads modeling JIP DNVGL Floating 2016-2018 Coupled analysis of floating wind turbine ROS 3D Pile 2017-2020 Soil FE modeling MONOCLASS Monopile 2017 Fast track design of MP SEEOS OSS 2017-2018 OSS standardization

  16. E.G. JACKET FOUNDATIONS  WTG AG4 AG3 STX Concept certification (DNV) Ship impact Clustering SCF METHODOLOGY AND TOOL DE DEVELOPMENT: -20 20% prim primary ry ste teel  OSS Pile Top M Y F X Fond marin H AFFOUIL L. F Z H ENSEVELIE Fabrication constraints Pile bottom 22 janvier 2018 Pile design (axial + lateral)

  17. E.G. SEEOS CONCEPT (certification 2018) – PATENT PENDING Standardize the “OSS function” and provide customized add -ons T1 T2 T3 -20% % CAP CAPEX, OP OPEX, Co Cons nstruction ti time Semi-submersible concept 22 janvier 2018

  18. This presentation and the information contained herein are STX France’s property, and they cannot be reproduced, used or comm unicate, even partially, without the written consent by STX France SA. THANK YOU FOR YOUR ATTENTION

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.