Status of Table Top Test Katsuya Yonehara Tuesday Meeting - - PowerPoint PPT Presentation

status of table top test
SMART_READER_LITE
LIVE PREVIEW

Status of Table Top Test Katsuya Yonehara Tuesday Meeting - - PowerPoint PPT Presentation

Status of Table Top Test Katsuya Yonehara Tuesday Meeting 9/19/2017 Progress Prepare beam test Bead-pull test Ready for test Carry out this Friday Beam interaction with cavity material 2 9/19/17 HPRF meeting, Yonehara


slide-1
SLIDE 1

Katsuya Yonehara Tuesday Meeting 9/19/2017

Status of Table Top Test

slide-2
SLIDE 2
  • Prepare beam test
  • Bead-pull test

– Ready for test – Carry out this Friday

  • Beam interaction with cavity material

Progress

9/19/17 HPRF meeting, Yonehara 2

slide-3
SLIDE 3

Prepare beam test

9/19/17 HPRF meeting, Yonehara 3

  • 1st Draft Technical Scope of Work

– Run plan

  • Infrastructure

– Signal cable

  • Found two cables
  • Need a few more

– Gas line

  • Order ¼’’ OD 400-ft PFA tube
  • Maximum allowable working pressure < 300 psi
  • Modify cavity

– Propose a beam window

  • Need to re-evaluate the pressure safety assessment
slide-4
SLIDE 4

Interacting beam with cavity material

9/19/17 HPRF meeting, Yonehara 4

20000 40000 60000 80000 100000 120000 1000 2000 3000 4000 5000

Incident 5,000 protons: 120 GeV/c Rms beam size = 5 mm, rms x’ = 0.03 mrad in front of the cavity SS Plate: r = 57 mm, thickness = 8, 4, 1 mm SS Wall: inner r = 46.8 mm, outer r = 57 mm 1 atm air in the cavity

Extract tangential angle (rad) Total p (MeV/c)

No cavity Fragments

0.1 0.2 0.3 0.4 0.5 1000 2000 3000 4000 5000 6000

Fragment at plate thickness Ratio (8mm) = 1.04 Ratio (4 mm) = 0.55 Ratio (1 mm) = 0.17

Tangential angle = pr/pz

slide-5
SLIDE 5

Proposed cavity

9/19/17 HPRF meeting, Yonehara 5

Beam entrance window Radius = 10 mm Thickness = 1 – 1.5 mm

8 mm

Weld ¼’’ SS pipe for gas inlet line

Reduce the amount of material

  • n the beam path
slide-6
SLIDE 6

Run plan

9/19/17 HPRF meeting, Yonehara 6

Beam intensity Lowest 1/10 x I0 1/5 x I0 I0 (full) N2 High Q Low Q Low Q Low Q + 0.01 Dry air High Q Middle Q Middle Q Low Q + 0.05 Dry air High Q Middle Q Middle Q Middle Q + 0.20 Dry air High Q High Q High Q Middle Q Dry air High Q High Q High Q High Q He High Q Low Q Low Q Low Q + 0.01 Dry air High Q Middle Q Low Q Low Q + 0.05 Dry air High Q Middle Q Middle Q Low Q + 0.20 Dry air High Q High Q High Q Middle Q Beam parameter

120 GeV/c protons, I0 = 3e12 ppp, 1.5 µs/pulse, beam delivered every 60 seconds, bunch length = 1 ns, Normalized transverse beam emittance 18 pi mm mrad, rms r = 5 mm, rms x’ = 0.03 mrad

RF parameter

2.45 GHz, E = 333 V/m, Pressure = 1 atm, dE/dx = 3.3 MeV cm2/g = 3,860 eV/cm (N2) Integrate ne = 4.3E14 ion pairs/cm3/pulse P = 10-7 J/p > High Q, 10-5 J > Middle Q > 10-7, Low Q > 10-5 J P = 𝑜" ̇ 𝜐 10-20, High Q ~ 800, Middle Q ~ 500, Low Q ~ 200

slide-7
SLIDE 7
  • Start from dry air at the highest beam intensity and low Q mode
  • 10 beam pulses for each point

– 36 points x 10 pulse = 360 pulses à 360 minutes = 6 hours

  • RF signal is taken for each pulse during the beam is turned off
  • Fix beam intensity and change gas mixing rate
  • Change beam intensity and quality factor

– Need to access to the exp hall to adjust the quality factor – We need to access at least two times – Probably, we wait for a couple of days for cooling – Try to use weekend as a cooling time

  • Apply factor two for time contingency

– 6 hours x 2 = 12 hours

  • We work a day time and week day in two weeks

– 2 weeks x 5 days x 8 hours = 80 hours

  • This does not involve the beam commissioning

Run plan (II)

9/19/17 HPRF meeting, Yonehara 7

slide-8
SLIDE 8

Layout

9/19/17 HPRF meeting, Yonehara 8

Experimental hall Cavity location Data acquisition room RF detector Gas bottle

slide-9
SLIDE 9

Experimental hall

9/19/17 HPRF meeting, Yonehara 9

120 GeV/c protons Uni strut:

Height and horizontal position are adjustable

Ion chamber will be replaced by the test cavity

slide-10
SLIDE 10
  • A pair of 3/8’’ heliax cables
  • More heliax available
  • Need to stretch ¼’’ OD 400-ft PFA gas tube
  • Cavity will be assembled on a uni-strut

– Need to design the support

Setup infrastructure & Design support

9/19/17 HPRF meeting, Yonehara 10

cavity ¼’’ PFA gas line Support G10 plate (exist) 8 inches bolt

slide-11
SLIDE 11
  • Calibrate cable

– Insertion loss by using Network Analyzer – Timing by using a fast scope and pulser (function generator) – Need to bring NA, scope, and pulser to the Switchyard service building

  • Gas line

– Purchase a PFA gas tube – Build a manifold (take from MTA) – Need to stretch the gas line from the SSB to hall

  • Modify cavity

– Beam window – Gas inlet line

  • New pressure safety assessment
  • New TSW

9/19/17 HPRF meeting, Yonehara 11

To-do list in two weeks