Status of Table Top Test Katsuya Yonehara Tuesday Meeting - - PowerPoint PPT Presentation
Status of Table Top Test Katsuya Yonehara Tuesday Meeting - - PowerPoint PPT Presentation
Status of Table Top Test Katsuya Yonehara Tuesday Meeting 9/19/2017 Progress Prepare beam test Bead-pull test Ready for test Carry out this Friday Beam interaction with cavity material 2 9/19/17 HPRF meeting, Yonehara
- Prepare beam test
- Bead-pull test
– Ready for test – Carry out this Friday
- Beam interaction with cavity material
Progress
9/19/17 HPRF meeting, Yonehara 2
Prepare beam test
9/19/17 HPRF meeting, Yonehara 3
- 1st Draft Technical Scope of Work
– Run plan
- Infrastructure
– Signal cable
- Found two cables
- Need a few more
– Gas line
- Order ¼’’ OD 400-ft PFA tube
- Maximum allowable working pressure < 300 psi
- Modify cavity
– Propose a beam window
- Need to re-evaluate the pressure safety assessment
Interacting beam with cavity material
9/19/17 HPRF meeting, Yonehara 4
20000 40000 60000 80000 100000 120000 1000 2000 3000 4000 5000
Incident 5,000 protons: 120 GeV/c Rms beam size = 5 mm, rms x’ = 0.03 mrad in front of the cavity SS Plate: r = 57 mm, thickness = 8, 4, 1 mm SS Wall: inner r = 46.8 mm, outer r = 57 mm 1 atm air in the cavity
Extract tangential angle (rad) Total p (MeV/c)
No cavity Fragments
0.1 0.2 0.3 0.4 0.5 1000 2000 3000 4000 5000 6000
Fragment at plate thickness Ratio (8mm) = 1.04 Ratio (4 mm) = 0.55 Ratio (1 mm) = 0.17
Tangential angle = pr/pz
Proposed cavity
9/19/17 HPRF meeting, Yonehara 5
Beam entrance window Radius = 10 mm Thickness = 1 – 1.5 mm
8 mm
Weld ¼’’ SS pipe for gas inlet line
Reduce the amount of material
- n the beam path
Run plan
9/19/17 HPRF meeting, Yonehara 6
Beam intensity Lowest 1/10 x I0 1/5 x I0 I0 (full) N2 High Q Low Q Low Q Low Q + 0.01 Dry air High Q Middle Q Middle Q Low Q + 0.05 Dry air High Q Middle Q Middle Q Middle Q + 0.20 Dry air High Q High Q High Q Middle Q Dry air High Q High Q High Q High Q He High Q Low Q Low Q Low Q + 0.01 Dry air High Q Middle Q Low Q Low Q + 0.05 Dry air High Q Middle Q Middle Q Low Q + 0.20 Dry air High Q High Q High Q Middle Q Beam parameter
120 GeV/c protons, I0 = 3e12 ppp, 1.5 µs/pulse, beam delivered every 60 seconds, bunch length = 1 ns, Normalized transverse beam emittance 18 pi mm mrad, rms r = 5 mm, rms x’ = 0.03 mrad
RF parameter
2.45 GHz, E = 333 V/m, Pressure = 1 atm, dE/dx = 3.3 MeV cm2/g = 3,860 eV/cm (N2) Integrate ne = 4.3E14 ion pairs/cm3/pulse P = 10-7 J/p > High Q, 10-5 J > Middle Q > 10-7, Low Q > 10-5 J P = 𝑜" ̇ 𝜐 10-20, High Q ~ 800, Middle Q ~ 500, Low Q ~ 200
- Start from dry air at the highest beam intensity and low Q mode
- 10 beam pulses for each point
– 36 points x 10 pulse = 360 pulses à 360 minutes = 6 hours
- RF signal is taken for each pulse during the beam is turned off
- Fix beam intensity and change gas mixing rate
- Change beam intensity and quality factor
– Need to access to the exp hall to adjust the quality factor – We need to access at least two times – Probably, we wait for a couple of days for cooling – Try to use weekend as a cooling time
- Apply factor two for time contingency
– 6 hours x 2 = 12 hours
- We work a day time and week day in two weeks
– 2 weeks x 5 days x 8 hours = 80 hours
- This does not involve the beam commissioning
Run plan (II)
9/19/17 HPRF meeting, Yonehara 7
Layout
9/19/17 HPRF meeting, Yonehara 8
Experimental hall Cavity location Data acquisition room RF detector Gas bottle
Experimental hall
9/19/17 HPRF meeting, Yonehara 9
120 GeV/c protons Uni strut:
Height and horizontal position are adjustable
Ion chamber will be replaced by the test cavity
- A pair of 3/8’’ heliax cables
- More heliax available
- Need to stretch ¼’’ OD 400-ft PFA gas tube
- Cavity will be assembled on a uni-strut
– Need to design the support
Setup infrastructure & Design support
9/19/17 HPRF meeting, Yonehara 10
cavity ¼’’ PFA gas line Support G10 plate (exist) 8 inches bolt
- Calibrate cable
– Insertion loss by using Network Analyzer – Timing by using a fast scope and pulser (function generator) – Need to bring NA, scope, and pulser to the Switchyard service building
- Gas line
– Purchase a PFA gas tube – Build a manifold (take from MTA) – Need to stretch the gas line from the SSB to hall
- Modify cavity
– Beam window – Gas inlet line
- New pressure safety assessment
- New TSW
9/19/17 HPRF meeting, Yonehara 11