Starting Soon Arts District Project Area WE ARE RECORDING WE HAVE - - PowerPoint PPT Presentation

starting soon
SMART_READER_LITE
LIVE PREVIEW

Starting Soon Arts District Project Area WE ARE RECORDING WE HAVE - - PowerPoint PPT Presentation

Starting Soon Arts District Project Area WE ARE RECORDING WE HAVE MUTED THIS MEETING. THE AUDIENCE. THE FILE WILL BE PLEASE USE THE EMAILED OUT TO HAND RAISE OUR EMAIL FEATURE TO BE SUBSCRIBERS. CALLED ON. Divisio sion n 20 Portal


slide-1
SLIDE 1

Arts District Project Area

Starting Soon…

WE ARE RECORDING THIS MEETING. THE FILE WILL BE EMAILED OUT TO OUR EMAIL SUBSCRIBERS. WE HAVE MUTED THE AUDIENCE. PLEASE USE THE HAND RAISE FEATURE TO BE CALLED ON.

slide-2
SLIDE 2

August 20, 2020

Divisio sion n 20 Portal l Wi Widening ing and Turnba nback ck Faci cili lity ty One Sa Santa Fe Apa partments nts Reside dents nts Meetin ing

2

slide-3
SLIDE 3

Arts District Project Area

  • Portal Widening and Turnback Facility Overview
  • Project Schedule
  • Construction Look-ahead
  • Current Work
  • Utility Relocation
  • 1st Street Viaduct
  • Nighttime Noise Variance
  • What has happened so far
  • Construction Mitigation
  • Reaching the Project Team
  • Questions

Age gend nda

slide-4
SLIDE 4

Metro Red and Purple le Li Lines: s: 140,0 ,000+ 00+ daily y passenger engers

slide-5
SLIDE 5

Faster Red and Purple Line Service

Arts District Project Area

Faster ter and More Frequent uent Red and Purpl ple e Li Line Se Service ce

slide-6
SLIDE 6

Arts District Project Area  Operational improvements to the Division 20 Rail Yard that aim to accommodate increased service levels on the Metro Red & Purple Lines  Improvements include:

  • Widening of heavy rail

portal

  • New turnback facility
  • Expansion and

reconfiguration of rail storage tracks

Pro roject ject Ove verview rview

One Santa Fe Tunnel Portal Turnback Facility Storage Tracks

slide-7
SLIDE 7

Arts District Project Area

Pro roject ject Timeline eline

Environmental Planning

2017-2018

Pre- Construction

2018-2019

Construction

2020-2023

Operations

2023

We are Here 7

slide-8
SLIDE 8

Look-Ahe Ahead ad Sc Schedu dule le

Arts District Project Area

*Schedule is subject to change

Activity ty Start Date End Date Pre-Construction

  • Abatement and

Demolition activities

  • National Cold Storage
  • Viertel Central Division

Facility

November 2018 Summer 2019 Construction Summer 2019 Fall 2023 ACTIV IVITY ITY AUG SEP OCT NOV DEC JAN

North th of 1st

st St Bridg

dge Excavation Grading South th of 1st

st St Bridge

dge Utility Relocation Work Bridge Modifications Removal and Installation of Tracks

slide-9
SLIDE 9

Construction struction Look k Ahead ad

2020 2020-2024 2024

 Construction of storage tracks  Construction of Portal Widening and Turnback Facility  1st Street Bridge modifications  Sidewalk widening and Center Street Landscaping  Welding and storage of Purple Line rail

*Work is subject to change

slide-10
SLIDE 10

Construction struction Comin ming g So Soon

 Potholing for utilities  Site surveying  1st Street Bridge modifications: partial demolition, milling work, and track removal  Utility Installation and Relocation of underground conduits, sewer and waterlines  Excavation of portal wall

*Work is subject to change

slide-11
SLIDE 11

Cur urrent rent Work rk

National Cold Storage Facility 11

 Potholi ling ng of Comme mercia ial Street: : Required to investigate the actual location of an existing waterline under the street  When: : August 17, 2020 to August 21, 2020  Where: : South side of Commercial Street east of Center St next to Metro’s Division 20 yard  Activitie ies includ ude: e:

  • Saw cutting, trench excavation, backfill and paving
  • The street will be restored after the potholing work is completed

 Anticip ipate ted d work hours: s:

  • Monday through Friday
  • 7am to 5pm
slide-12
SLIDE 12

Cur urrent rent Work rk

National Cold Storage Facility 12

 Track Remova val and Demoliti tion

  • n Underne

neath th the First Street Viaduct

  • Removal of the maintenance of way (MOW) tracks in the South Yard underneath

the First Street Viaduct

  • Demolition of the smoke slab underneath the viaduct will happen in the near

future

  • Work will continue through August and September

First Street Viaduct looking south

slide-13
SLIDE 13

What’s Happened So Far

Utility bridge removed to allow the widening of the portal looking northeast

13

slide-14
SLIDE 14

What’s Happened So Far

Exploratory work on the First Street Viaduct deck looking east

17

slide-15
SLIDE 15

Utility lity Re Relocation

  • cation Activ

ivities ities

 When: : Through Fall 2020  Where: :

  • Within the Division 20 Yard
  • Work to begin just north of 1st St Bridge and

continue south towards Metro’s Division 20 Parking Lot  Activitie ies includ ude: e:

  • Sawcutting, trench excavation, conduit installation,

backfill and paving  Anticip ipated ted work hours: rs:

  • Monday through Friday
  • 7am to 4pm

*Work is subject to change

N

Utilit lity Reloc locat ation ion Work k Area ea

slide-16
SLIDE 16

Ut Util ility ity Inst stallat allation ion

*Work is subject to change

16

 Contractor is removing an abandoned gas line to accommodate the widening of the train portal  The work occurred near the eastern, vacated part of Jackson Street (west of the portal)

Photo was taken looking northeast

slide-17
SLIDE 17

Re Request uest for r Nigh ghttime ttime Noise se Varia riance nce

*Work is subject to change

*Work is subject to change

 Because the work is being performed in an active rail yard, the contractor must wait until after operating hours to perform certain work  Work k hours: urs: 9pm to 3am  An exemption will minimize construction impacts on the surrounding community by accelerating this work:

  • Directional boring
  • Installation of underground conduits and manhole structures
  • Cutovers to existing tracks and systems

17

slide-18
SLIDE 18

Pro roposed

  • sed Exten

tended ded Work rk Ho Hour urs s

*Work is subject to change

*Work is subject to change

 Extended d work hours s will:

  • Minimize overall duration of most

significant construction impacts

  • Maximize efficiency
  • Night

httime me Work: Overnight work within designated noise limits  Propos posed d extended work hours: s: May 2020 through December 2023

  • Monday

ay through ugh Friday ay: 9pm to 7am the next day

  • Friday

ay: 9pm to 11:59pm

  • Saturda

day: : 12am to 8am and 6pm to 11:59pm

  • Sunday

ay: 12am to 11:59pm

Metro Purple Line Extension crew backfilling a trench at night with directed lighting

18

slide-19
SLIDE 19

Pro roposed

  • sed Work

rk

*Work is subject to change

*Work is subject to change

 Pro roposed

  • sed work

rk:

  • Trenching
  • Directional boring
  • Installation of underground conduits and manhole

structures

  • Grading
  • Pavement restoration
  • Soil testing and stockpiling
  • Hauling
  • Mobilization and demobilization of construction services

19

slide-20
SLIDE 20

Construction struction Mi Mitiga gations tions

 Best st pra racti ctices ces on the const struc ructio ion si site:

  • Equipment and staging areas shall be located away

from noise-sensitive receivers

  • Minimize high impact devices such as jackhammers

and hoe rams

  • Utilize lower impact devices such as concrete crushers

and pavement saws

  • Refrain from idling of equipment

20

slide-21
SLIDE 21

Construction struction Mi Mitiga gations tions

 Noise barriers in the Division 20 yard  Constant watering keeps dust down

21

Photos were taken looking south

slide-22
SLIDE 22

Construction struction Mi Mitiga gations tions

Reducing dust by frequent watering

22

Installing sound blankets around equipment

slide-23
SLIDE 23

Pro roject ject Websit bsite e – metro tro.net/ .net/divis division20 ion20

23

slide-24
SLIDE 24

Ho How t w to Re Reac ach h Us

 Call l us on the Proj

  • jec

ect t Hotli line ne: : 21 213-922 922-69 6934 34  For project questions, concerns and complaints  Live during construction work hours  Monday through Friday, 7am-5pm  After 5pm: Leave a voicemail; staff with return call within 24 hours  Proje

  • ject

ct Email: l: purplelineext@metro.net Staff will reply within 24 hours  Stay Connec ecte ted  Construction notices posted online at metro.net/division20  Receive email project updates and construction notices

24