Sounder South Strategic Development & Implementation Plan update & Fleet Procurement
Board of Directors Meeting 04/23/2020
Sounder South Strategic Development & Implementation Plan - - PowerPoint PPT Presentation
Sounder South Strategic Development & Implementation Plan update & Fleet Procurement Board of Directors Meeting 04/23/2020 Why we are here Briefing Final Sounder South Strategic Development & Implementation Plan report
Board of Directors Meeting 04/23/2020
2
3
(to carry up to 40% more people)
signal upgrades and easements; contingent on negotiations with BNSF
more riders on longer trains
4
5
Summary
short survey
advertisements in English, Spanish and Vietnamese
600 completed the survey Key Findings
and more trips
noting crowded conditions
evening, peak commute period, and other times
reliability, parking and bus service to stations
6
Strategy One: Longer Trains
to meet expected demand
Strategy Two: More Trips
by BNSF Targeted Station Access Investments to provide convenient, safe access for riders to platforms
7
Final report published: April 1, 2020
Budget Amendment R2020-07
9
Recommendation to execute a budget amendment that supports an SEC approved car procurement of eight coach-cars in alignment with the ST3 capacity goals and operational needs. Bombardier Bi-Level Cab Car Classic Bi-Level Coach Car
10
procurement of 8 Sounder vehicles
made whole
11
adding 8 coaches
scale and lower price
reasonable
12 Illustrative - Not to Scale
Approved Today’s Action Future Action
$67.20M Agency Admin. & Vehicles
ALLOCATION $ COMMITMENTS
Sounder Fleet Expansion: Authorized Project Allocation $67.2M
13 Illustrative - Not to Scale
Approved Today’s Action Future Action
$110.28M Agency Admin., Final Design & Vehicles
ALLOCATION $ COMMITMENTS
Sounder Fleet Expansion: Board Approves Increase to Authorized Project Allocation $110.28M