Sizewell B

Sizewell Stakeholder Group Meeting

Thursday 19 April 2018

slide-3
SLIDE 3

Safety performance and staffing

During the period of the report there has been:

  • No lost time injuries to staff
  • No nuclear reportable incidents
  • No environmental incidents
  • 545 EDF Energy staff includes 16 Apprentices, 3 trainees, 3 Industrial

Placements

  • 250 year round contracting partners
slide-4
SLIDE 4

Steam Generator work during refuelling outage 15

  • On 31 January 2018 Sizewell B power station returned to service following its

fifteenth planned refuelling and maintenance outage

  • Shutdown was extended to allow repairs to our steam generators.
  • Maintenance inspections, repairs and testing on all four steam generators took

place.

slide-5
SLIDE 5

Turbine Generator 2 pipework repair

  • On 20 February 2018 Turbine Generator 2 was brought offline to complete a repair to a

section of pipework.

  • Monitoring detected a small hydrogen leak, on original components of the turbine and a

conservative decision was made to take the turbine offline to complete the repair.

  • Turbine Generator 1 was not affected and continued to supply power to over 1million

homes and businesses.

  • Turbine Generator 2 was returned to service on 05 March following the repair to a section of

its pipework.

slide-6
SLIDE 6

International review confirms good safety practice at Sizewell B

  • International Atomic Energy Agency (IAEA) has confirmed the successful

completion of its review of Sizewell B.

  • Operational Safety Review Team (OSART) concluded the mission had

been successful after the follow-up mission to Sizewell B nuclear power station in April 2017.

  • The Department for Business, Energy and Industrial Strategy welcomed

the follow-up report from the IAEA and congratulated Sizewell B on the number of good practices identified.

  • A link to the OSART report and Government response can be found here:

https://www.gov.uk/government/publications/operational-safety-osart- mission-to-sizewell-b-nuclear-power-station-follow-up-report

slide-7
SLIDE 7

Sizewell B Sponsorships and Donation fund

£10k per year, summaries of projects awarded to date: £4,450

  • Leiston Football Club - pitchside advertising

£500.00

  • Suffolk Coastal District Council - Workplace games

£250.00

  • Southwold Golf Club - Festival of golf week

£200.00

  • Beccles Royales Gym Club - Portable foam pit safety

£500.00

  • Rotary Club Saxmundham & Framlingham - Heritage coast run

£600.00

  • Sudden Unexpected Death in Epilepsy - Memorial event donation

£50.00

  • Suffolk Singers - Portable choir rise stage

£500.00

  • Yoxford Two Charities - Summer fete donation

£100.00

  • Palliative Care East - Counselling sessions

£500.00

  • Long Shop Museum - Leaflet production

£1,000.00

  • Loft Youth Centre Southwold – Founders Walk

£250.00