Session 4: A Fist Full of Dollars: Utilizing Surety Bonds & - - PowerPoint PPT Presentation

session 4 a fist full of dollars utilizing surety bonds
SMART_READER_LITE
LIVE PREVIEW

Session 4: A Fist Full of Dollars: Utilizing Surety Bonds & - - PowerPoint PPT Presentation

Session 4: A Fist Full of Dollars: Utilizing Surety Bonds & Payment Protection Strategies Brian Clifford Shawna Eikenberry Associate Counsel Surety Bond Basics Obligee = The Protected Party Principal = The


slide-1
SLIDE 1

Session 4: A Fist Full of Dollars: Utilizing Surety Bonds & Payment Protection Strategies

Brian Clifford Associate Shawna Eikenberry Counsel

slide-2
SLIDE 2

Surety Bond Basics

►Obligee = The Protected Party ►Principal = The Contractor/Subcontractor Obtaining the Bond ►Surety = The “Financial Backstop”/Issuer ►Penal Sum = The Surety’s Maximum Liability (with some

exceptions, such as attorneys’ fees for Payment Bonds)

►Forms: AIA A312-2010, statutory forms, and “manuscript” forms

95

slide-3
SLIDE 3

Surety Bond Basics

Payment Bond

►Benefits the subcontractors/sub-subcontractors and suppliers of

the Principal

►Also benefits the Obligee by protecting from mechanic’s liens and

  • ther “non-privity” payment claims

►Owner and unpaid sub-tiered claimants may make a claim on the

bond – often within strict time limits

96

slide-4
SLIDE 4

Surety Bond Basics

Performance Bond

►Benefits the Principal ►Obligates the Surety to complete performance of the Obligee’s

work after a default (or to pay for the excess costs incurred by the Principal to have such work completed by others)

►The remaining balance of the contract price is made available (or

  • ff-set) against the completion costs

97

slide-5
SLIDE 5

Surety Bond Basics

Bid Bond

►Benefits the Principal ►Ensures that a contract (with required Payment and Performance

Bonds) will be executed at the bid price

►Surety’s liability is the difference between the bid price and the

next bid amount that is required to be accepted (up to the Penal Sum)

98

slide-6
SLIDE 6

Surety Bond Basics

Lien Bond

►Benefits the Property Owner ►Ensures that a mechanic’s lien will be either discharged or paid ►Depending on the jurisdiction, such bonds may allow the lien to be

removed as an encumbrance to the Owner’s title to the property

►Other options: title insurance endorsements (often with escrowed

funds), Irrevocable Letters of Credit, Cash Deposits

99

slide-7
SLIDE 7

Surety Bond Basics

Other Common Bonds “Maintenance” Bonds – Ensure performance of warranty, etc. work

►Right-of-Way Bonds – Ensure completion of private work

impacting public right-of-ways (and other similar development requirements)

►License Bonds – Posted with the licensing agencies to protect

consumers from covered risks

►Fidelity “Bonds” – Insurance policies protecting against employee

dishonesty losses

100

slide-8
SLIDE 8

Notice – To The “Nth Degree”

►Safety Signs, LLC v. Niles-Wiese Constr. Co., Inc.,

840 N.W.2d 34 (Minn. 2013)

►Subcontractor is unpaid for Phase I-related traffic-control services

and pavement-marking work on City airport project

►It files a Notice of Claim with the Prime Contractor and the Surety

► Surety served at address listed in Payment Bond ► Prime Contractor served at address listed in subcontract

►Prime Contractor pays full amount due to Subcontractor for

Phase I work

101

slide-9
SLIDE 9

Notice – To The “Nth Degree”

►Subcontractor continues on project and completes Phase II-related

work

►Prime Contractor receives payment from City for such work, but

fails to pay full amount due to Subcontractor

►Subcontractor again files a Notice of Claim with the Prime

Contractor and the Surety

► Surety again served at address listed in Payment Bond ► Prime Contractor again sent Notice at address listed in subcontract

102

slide-10
SLIDE 10

Notice – To The “Nth Degree”

►Notice to Prime Contractor return “Unclaimed – Unable to

Forward”

►Surety responds to Claim by requesting “proof of claim”

information and documentation

► Surety also included a “reservation of rights”

►After submission, Surety notifies Subcontractor that the Prime

Contractor disputed the claim and therefore the Surety was denying payment

► Prime Contractor copied at a P.O. Box address

103

slide-11
SLIDE 11

Notice – To The “Nth Degree”

►Subcontractor files suit against Prime Contractor and Surety for

payment on subcontract and on Payment Bond

►Prime Contractor defaults

► Appears to be insolvent and “judgment proof”

►Surety answers the lawsuit and moves for Summary Judgment

► It claims that although it was served at the address listed in the

bond, the notice to the Contractor was sent to an address different than the one listed in the bond – which is contrary to the applicable public works statute

104

slide-12
SLIDE 12

Notice – To The “Nth Degree”

►Subcontractor challenges that Surety has standing to protest

against the notice sent to a different (and defaulted) party

►Subcontractor also provides evidence that the notice to the Prime

Contractor was sent to the address:

► Listed in the subcontract ► Listed on the Prime Contractor’s website ► Used on all Project invoices ► Used for correspondences between the Prime Contractor and the

Subcontractor

► Used (without objection and with positive results) for the Notice of

Claim for Phase I

105

slide-13
SLIDE 13

Notice – To The “Nth Degree”

►The District Court rejects the Surety’s claims and granted

summary judgment to the Subcontractor on the notice issue

►Subcontractor moves for summary judgment on liability and

damages – and District Court grants the motion

►Surety appeals, and Court of Appeals reverses summary judgment

  • n the notice issue

►Subcontractor appeals to the Minnesota Supreme Court

106

slide-14
SLIDE 14

Notice – To The “Nth Degree”

What do you think is the outcome?

107

slide-15
SLIDE 15

Notice – To The “Nth Degree”

►Minnesota Supreme Court demands strict compliance with statute

► ”Form over Substance?”

►“Substantial Compliance” with statute that required that the Notice

  • f Claim be served at the Prime Contractor’s and Surety’s

“addresses as stated in the bond” (Minn. Stat. § 574.31(2)(a)) was not permitted

►The statute says that “no action shall be maintained…unless” the

pre-suite notice requirements were met

108

slide-16
SLIDE 16

Notice – To The “Nth Degree”

►The Subcontractor could not show waiver based (1) the Phase I-

related claim or (2) the Surety using a similar P.O. Box address for the Prime Contractor as the Subcontractor used for the Phase II Notice of Claim

►The Court also allowed the Surety to challenge the

Subcontractor’s compliance with the statute – even if the violation did not involve notice to the Surety

►Thoughts?

109

slide-17
SLIDE 17

Banks and Bonds – Oil and Water

►U.S. ex rel. BAC Funding Consortium, Inc. v. Winchester Fire Ins.

Co., 998 F.Supp.2d 1330 (S.D.Fla. Nov. 4, 2013)

►U.S. Corps of Engineers’ Project for “Water Conveyance Structure”

in Miami-Dade County

►Prime Contractor obtains financing from Bank, which will act as

disbursing agent

►Bank advances funds to pay Prime Contractors’ subcontractors

and suppliers, and is reimbursed from government’s payments

110

slide-18
SLIDE 18

Banks and Bonds – Oil and Water

►As required by the Miller Act, the Prime Contractor also obtained a

Payment Bond

►Bank pays the subcontractors, but is not reimbursed for more than

$500,000 in payments

►Bank files suit against the Surety, and the Surety moves for

dismissal for “failure to state a claim”

111

slide-19
SLIDE 19

Banks and Bonds – Oil and Water”

What do you think is the outcome?

112

slide-20
SLIDE 20

Banks and Bonds – Oil and Water

►Motion to Dismiss is granted ►Miller Act payment bonds are “to protect subcontractors and

suppliers who provide labor and materials for a federal project,” and not others

►It has long been held that loans for payments to such protected

entities do not, themselves, constitute “labor and materials”

113

slide-21
SLIDE 21

Banks and Bonds – Oil and Water

►Bank tried to claim “equitable subrogation” to the rights of the

subcontractors it paid for the work

►The basic assertion was that, as a matter of fairness, the Bank

could utilize the payment bond rights of the companies it sent money to for the project work

►The Court said no – the Bank was a “volunteer” to the financing

arrangements and could not utilize “equitable” theories

114

slide-22
SLIDE 22

Banks and Bonds – Oil and Water

►Bank also asserted right against the payment bond under an

“equitable assignment” theory

►Again, the basic assertion was that, as a matter of fairness, the

subcontractors should have been deemed to have impliedly assigned their bond rights to the Bank in exchange for the payments advanced

►One problem: since the subcontractors were paid for their work on

the project (albeit by the bank), they had no rights against the payment bond to assign

115

slide-23
SLIDE 23

Banks and Bonds – Oil and Water

►Another problem: there were no assignment documents from the

subcontractors to the Bank

► And the lien waivers that were provided as a part of the

payment process weren’t “assignments in disguise”

►Question: What if the Bank would have obtained assignments of

the subcontractors’ rights against the bond?

► Because the Bank paid for the Project labor and materials, it

probably “extinguished” the payment bond claims

► If it wanted rights to the bond, it should have been a named

Obligee

►Thoughts?

116

slide-24
SLIDE 24

Miller Act and State Laws – What State Laws?

►Technica LLC ex rel. U.S. v. Carolina Cas. Ins. Co., 749 F.3rd 1149

(9th Cir. 2014)

►Sub-subcontractor is unpaid for more than $600,000 of work on a

California-located federal project by a subcontractor

►It asserts a claim against the Miller Act payment bond of the Prime

Contractor

►Prime Contractor and Surety file for summary judgment based on

the undisputed fact that the Sub-subcontractor was not licensed in California, as required by law

117

slide-25
SLIDE 25

Miller Act and State Laws – What State Laws?

►The District Court grants the motion, finding that the unlicensed

status of the Subcontractor was a complete defense to the payment claim

►The California statute “precludes any contractor from maintaining

an action for collection of compensation for services if the contractor was not a licensed contractor during performance of the contract”

►The Sub-subcontractor appealed

118

slide-26
SLIDE 26

Miller Act and State Laws – What State Laws?

What do you think is the outcome?

119

slide-27
SLIDE 27

Miller Act and State Laws – What State Laws?

►The Court of Appeals finds that the California law “restricts the

substance of the rights” afforded under the Miller Act

►Conditioning contractors’ rights under the Miller Act on compliance

with state laws would “wreak havoc on the uniform application of the Miller Act”

►Thoughts?

120

slide-28
SLIDE 28

Notice: Procrastination is opportunity’s assassin.

►Baistar Mech., Inc. v. Cont’l Ins. Co., 2014 WL 2156657 (D.D.C.

May 22, 2014)

►Subcontractor performs work at the Brazilian Embassy ►Prime Contractor’s payment bond required that any lawsuit be

commenced prior to “the expiration of one year from the date…on which the last labor or service was performed by anyone…under the Prime Contract”

► This is substantial similar to the AIA A312-2010 form

►As early as February 2011, the Subcontractor had invoiced the

Prime Contractor the total amount of the subcontract price

121

slide-29
SLIDE 29

Notice: Procrastination is opportunity’s assassin.

►But it provided equipment training at the Project site more than six

months later (by September 30, 2011)

►Due to a $350,000+ payment dispute, the Subcontractor and the

Prime Contractor enter into a 1-year “tolling agreement”

►When no resolution was reached, the Subcontractor filed a lawsuit

against the Surety on July 15, 2013

►The Surety filed a motion for summary judgment based on the

“contractual statute of limitations”

122

slide-30
SLIDE 30

Notice: Procrastination is opportunity’s assassin.

What do you think is the outcome?

123

slide-31
SLIDE 31

Notice: Procrastination is opportunity’s assassin.

►The District Court granted the motion ►The Subcontractor’s allegation that it performed “consulting

services” with respect to the HVAC system it had installed was insufficient to extend the deadline for filing a suit on the bond

► The Court found this was not work that was part of the original

Prime Contract

► Instead, it was “merely for the purpose of correcting defects, or

making repairs” to the previously-completed work

124

slide-32
SLIDE 32

Notice: Procrastination is opportunity’s assassin.

►The fatal blow: the General Contractor’s affidavit that all work

required under the Prime Contract was completed when the Subcontractor finished the on-site HVAC equipment training

►Although the Court accepted a “trigger date” that was months after

the final invoice was sent by the Subcontractor, that was still too early for the Subcontractor’s bond claim to survive

►The Subcontractor’s delay between tendering the claim to the

Surety and actually filing suit on the bond sunk its case

125

slide-33
SLIDE 33

Notice: Procrastination is opportunity’s assassin.

►It is unclear why the Prime Contractor/Subcontractor “tolling

agreement” did not include the Surety

► This was a fatal error for the Subcontractor’s rights on the payment

bond

►Thoughts?

126

slide-34
SLIDE 34

Other Payment Protection Strategies

Parent Guaranty/Indemnities

►Commits the financial resources of another entity (usually a parent

  • r affiliate of the Principal) to support the performance of the

Principal’s contractual obligations

►Often utilized when dealing with Single-Purpose Entities and

common in construction lending transactions (for the benefit of the lenders)

►Wide range of terms, including “covered risks,” length of financial

support, and net worth and liquidity commitments

127

slide-35
SLIDE 35

Other Payment Protection Strategies

Irrevocable Letters of Credit

►A banking instrument that operates similar to a check ►Beneficiary has the right to “cash” the ILoC by endorsing the

instrument and providing a statement in accordance with the document

►Bank and “posting party” have limited abilities to prevent payment,

but may have a claim back against the Beneficiary for recovery of funds and resulting damages

128

slide-36
SLIDE 36

Other Payment Protection Strategies

Construction Escrow and Disbursing Agreement

►A multi-party agreement between the Owner, Lender and Title

Company, usually with the Prime Contractor as a non-party signatory

►Outsources Sworn Statement/Lien Waiver submittal process to

title company, which issues “date-down” endorsements to the Lender’s Mortgage/Trust Deed Policy

►Usually supported by Personal Undertakings from the Owner and

(if a “pay-general” system is used) the Prime Contractor

129

slide-37
SLIDE 37

Other Payment Protection Strategies

“Lockbox Account”

►A multi-party agreement that restricts access to Project proceeds ►Sometimes utilized in conjunction with financing agreements and

ILoC’s to allow the bank to maintain control of distributions

130

slide-38
SLIDE 38

Other Payment Protection Strategies

Pledges of Other Assets

►The protected party is granted rights in other collateral (such liquid

financial instruments, securities, real estate, Accounts Receivable, equipment, etc.)

►May be subject to Uniform Commercial Code requirements for

Security Interests

►Value of assets may fluctuate, and restrictive covenants may be

needed

131

slide-39
SLIDE 39

Session 5: Insurance Risks in Multifamily Residential Construction

Jason Wilsey Willis of Minnesota

slide-40
SLIDE 40

The New Normal

Construction Risk 2.0

Jason Wilsey, Vice President Willis of Minnesota, Inc.

slide-41
SLIDE 41

Today You Will Receive…

  • Clarity in understanding current and future risk issues in

construction

  • How these risks affect you
  • Simple, Effective, Aligned insight, helping you:

– Reduce cost – Improve cash flow & margin – Protect earnings – Make informed decisions – Don’t end up like this guy…

slide-42
SLIDE 42

*Happy Gilmore 9th Green at 9 clip

slide-43
SLIDE 43

Look On The Bright Side…

  • Taxes are reaching and exceeding 50% (depending on

state)

  • OSHA, EPA, DOT and other regulatory institutions are

ramping up oversight and penalties

  • Record rainfall, droughts, wildfires and more intense

seasonal weather (blizzards, hurricanes)

  • Contract language has become more stringent
  • Recommendations and Value Engineering potentially

classify you as a “design professional”

slide-44
SLIDE 44

Guess What?

These are “The Good Old Days”

  • Taxes
  • Politics
  • Climate
  • Regulation
  • Litigation

Unfortunately, we will look back and remember these as when things were easier…

slide-45
SLIDE 45

Welcome To The “New Normal”

slide-46
SLIDE 46

Where’s The Action?

Warming Up

  • Industrial
  • Commercial
  • Retail

Hot!

  • Apartments
  • Senior Living
  • Hotels
  • Student Housing
  • Condominiums
slide-47
SLIDE 47

Condo’s???

*Insert Whatchu Takin Bout Willis video

slide-48
SLIDE 48

Multi-Family

  • New reinvestment initiatives to urbanize downtown areas
  • Example: Minneapolis 2025 Plan – Create space for
  • ver 300,000 new residents in downtown Minneapolis
  • More apartments and mixed use developments,

including condominiums

slide-49
SLIDE 49

So What? Building Is Good!

slide-50
SLIDE 50

We Agree! But In The “New Normal”

  • Insurers are not keen on insuring habitation risk
  • Housing market is showing signs of recovery
  • Potentially “Overbuilt”
  • A proverbial “Bubble”
  • Excluding coverage for Residential Construction
slide-51
SLIDE 51

“But I’m Not Building Single Family Homes, Tow nhomes Or Condos”

slide-52
SLIDE 52

If Apartments Are Covered, Then More Than Likely...

This insurance does not apply to "bodily injury", "property damage" or "personal and advertising injury" arising out of or in any way related to premises if those premises, in whole or in any part, are or were at any time, marketed, sold, occupied,or used as residential premises. Residential premises include, but are not limited to:

  • 1. Condominiums, cooperatives, dwellings,homes, houses, townhomes or townhouses, timeshares and

"mixed- use buildings"; and 2. Appurtenant common areas, structures, facilities and grounds associated with the residential premises. Residential premises also include any conversion of property to or from any of the residential premises described above. Residential premises do not include nursing homes, assisted living facilities, hospitals. dormitories, jails, prisons, military housing, apartment buildings, hotels or motels, provided that any such premises, in whole

  • r in any part, are or were not at any time,marketed, sold, occupied, or used as condominiums,

cooperatives, dwellings,homes, houses, townhomes or townhouses,timeshares or "mixed-use buildings." For the purposes of this endorsement, ''mixed-use buildings" means any structures and improvements thereto which contain both: (i) residential living space and (ii) commercial or industrial space. This exclusion does not apply to "bodily injury", "property damage" or "personal and advertising injury'' arising out of on-going operations performed by you or on your behalf. This insurance is excess over any other valid and collectible insurance (including any deductible portion thereof) availabie to the insured whether primary, excess,contingent or on any other basis.

slide-53
SLIDE 53

Condo Conversion Exclusion

  • High end finishes
  • Rebounding housing market
  • High rents making homeownership more

appealing

  • Market studies showing increased demand for

urban living

– Transit, Green lifestyle, “Lock and walk”

slide-54
SLIDE 54

Uncovered CD Claim – Who Is At Risk?

  • Owner
  • Lender
  • General Contractor
  • Subcontractor
slide-55
SLIDE 55

 Construction Defect Liability – what is this?

Generally speaking, a deficiency in the design or construction of a building or structure resulting from a failure to design or construct in a reasonably workmanlike manner, and/or in accordance with a buyer's reasonable expectation. (IRMI’s Glossary of Insurance and Risk Management terms)

 Statute of Repose – the time period within which a construction defect

action must be brought. In Minnesota, the exposure lasts for 10 years following substantial completion, plus 2 years for late manifestation.

 CD-related lawsuits are common in the construction industry, and

condos/TH’s are even more prone to CD claims when compared with commercial or single family residential.

Construction Defect Liability

148

slide-56
SLIDE 56

Example

Electrical Fire in Apartment Project

  • Claim Triggered
  • Passed via contract from

GC to Electrical Sub

  • Electrical Sub files claim

against their insurance carrier

  • Sub carries “residential

exclusion” in general liability policy

Potential Outcome

  • Job delay
  • Claim trails back up through

the contract path

  • Lawsuit
  • Electrical sub potentially out
  • f business
  • Compromised relationships

– Owner/lender – Owner/GC – GC/Sub

slide-57
SLIDE 57

Traditional Risk Transfer / Insurance

OWNER GENERAL CONTRACTOR SUBCONTRACTORS Indemnification / GL Additional Insured Contractual Risk Transfer Contractual Risk Transfer Indemnification / GL Additional Insured

150

slide-58
SLIDE 58

Utilizing Traditional Insurance For Habitation

  • Beware
  • Very difficult to manage

– Companies move insurance providers – Do you have time to read all sub policies? – How does your policy apply to the new paradigm?

  • Certificates of Insurance do not disclose whether

“residential” exclusion applies

– Or if it has been amended – What if the project converts?

slide-59
SLIDE 59

Don’t Panic!

  • With the right process, you can proactively budget, plan

and deliver your work confidently

  • Multi-Directional Value

– GC to Owner – Owner to Lender – GC to Sub

slide-60
SLIDE 60

What’s Out There?

  • High capacity of available insurance volume
  • 2:1 ratio of available capacity for current volume in

current marketplace

  • Habitation strategies and programs assuring GC and

Subs all carry completed operations coverage (CGL) up to the statute of repose

  • Pricing will continue to soften

– Positive loss performance – Quality risk control procedures

slide-61
SLIDE 61

What Should We Do?

  • *Movie clip – Caddy Shack, Billy Murray “I’d

keep playing, I don’t think the heavy stuff will come down for quite a while”

  • - Consider this slide at the end
slide-62
SLIDE 62

Utilizing These Strategies

  • Balance Sheet – Protected
  • Cash Flow & Margin – Improved
  • Unexpected Expenses – Reduced
  • Time - Saved
  • Decision Making Insight – Increased

– More certainty – Confidence in your delivery – Focus on what you do best

How do I learn more about these strategies?

slide-63
SLIDE 63

Call Me

Jason A. Wilsey – Vice President 763-302-7102 jason.wilsey@willis.com

slide-64
SLIDE 64

Session 6: Critical Legal Developments in CGL and Property Insurance

Patrick O’Connor Partner

slide-65
SLIDE 65

Anatomy of a Construction Contract Insurance Provision

►Required Coverages

► Workers’ Compensation/Employers’ Liability ► Commercial General Liability ► Automobile Liability ► Property/Builder’s Risk Coverage

►Optional Coverages

► Excess/Umbrella Liability Insurance ► Professional Liability Insurance ► Pollution Liability Insurance

158

slide-66
SLIDE 66

►Coverage Limits

► General Liability ►Per Occurrence/Aggregate Limits ► Property Insurance ►General Limits ►Sublimits for Specified Perils or Coverage Extensions ► Excess/Umbrella Insurance ►Limits ►Exhaustion ►Follow Form ►Excess vs. Umbrella

159

slide-67
SLIDE 67

►Additional Insured Coverage

► Primary and Non-Contributory ► Elimination of Cross-Suit Exclusion ► Elimination of Privity Requirements ► Scope of Additional Insured Coverage ► Relationship of Anti-Indemnity Laws to Additional Insured Coverage

►Subrogation Waivers

► Scope of Waiver ► Waiver Triggers

160

slide-68
SLIDE 68

►Certificates of Insurance ►Carrier Financial Thresholds ►Cancellation and Notice ►Miscellaneous Requirements

161

slide-69
SLIDE 69

Real-Life Examples of Contract Language

162

slide-70
SLIDE 70

COVERAGES

163

slide-71
SLIDE 71

Workers’ Compensation

►In the event contractor is not required to provide or elects not to

provide workers’ compensation coverage, the parties hereby agree that contractor, its owners, agents and employees will have no cause of action against, and will not assert a claim against, the State of Louisiana, its departments, agencies, agents and employees as an employer, whether pursuant to the Louisiana Workers’ Compensation Act or otherwise, under any circumstance.

164

slide-72
SLIDE 72

Commercial General Liability

**While the minimum Combined Single Limit of $1,000,000 is required for any renovation, the limit is calculated by taking 10% of the building value and rounding it to the nearest $1,000,000 to get the insurance limit. Example: Renovation on a $33,000,000 building would have a calculated $3,000,000 combined single limit of coverage (33,000,000 times .10 = $3,300,000 and then rounding down to $3,000,000). If the calculated limit is less than the minimum limit listed in the above chart, then the amount needed is the minimum listed in the chart. Maximum per

  • ccurrence limit required is $10,000,000 regardless of building value. The per project aggregate limit is then

calculated as twice the per occurrence limit.

165

COMBINED SINGLE LIMIT (CSL) PER OCCURRENCE Type of Construction Projects up to $1,000,000 Projects over $1,000,000 up to $10,000,000 Projects over $10,000,000 New Buildings: Each Occurrence Minimum Limit $1,000,000 $2,000,000 $4,000,000 Per Project Aggregate $2,000,000 $4,000,000 $8,000,000 Renovations: The building(s) value for the Project is $_______________. Each Occurrence Minimum Limit $1,000,000** $2,000,000** $4,000,000** Per Project Aggregate 2 times per occur limit** 2 times per occur limit** 2 times per occur limit**

slide-73
SLIDE 73

Commercial General Liability

►Products and completed operations coverage. This coverage shall

extend through the contract guarantee period and for at least 6 years from final completion of all work.

►Employees as additional insureds. ►The aggregate must be applicable on a per project basis.

166

slide-74
SLIDE 74

Commercial General Liability

►A policy of commercial general liability insurance, written on an

insurance industry standard occurrence form, including all the usual coverages known as: premises/operations liability; products/completed operations; personal injury; contractual liability; independent contractors liability; and fire damage legal

  • liability. Such policy(ies) must provide the following minimum

► Bodily injury and property damage - $2,000,000 each occurrence ► Products or completed operations - $2,000,000 each occurrence

►Any deductible or self-insured retention must be disclosed and is

subject to approval by the Electric Boat Corporation’s risk

  • manager. The cost of any claim payments falling within the

deductible shall be the responsibility of the contractor.

167

slide-75
SLIDE 75

Commercial General Liability

►Commercial general liability insurance, with limits no less than One

Million Dollars ($1,000,000) combined single limit per occurrence and Two Million Dollars ($2,000,000) annual aggregate limit for bodily injury and property damage, including coverage for contractual liability; personal injury; fire damage legal liability; advertisers’ liability; owners’ and contractors’ protective liability; products and completed operations; broad form property damage; and explosion, collapse and underground (XCU) coverage during any period in which Borrower is conducting any activity on, alteration or improvement to the Site with risk of explosions, collapse, or underground hazards.

168

slide-76
SLIDE 76

Builder’s Risk

►Builder’s Risk Insurance shall be in an amount equal to the greater

  • f the fully-completed project value or the amount of the

construction contract including any amendments and shall be upon the entire work included in the contract. The policy shall provide coverage equivalent to the ISO form number CP 10 20, Broad Form Causes of Loss (extended, if necessary, to include the perils

  • f wind, earthquake, collapse, vandalism/malicious mischief, and

theft, including theft of materials necessary to provide plans, specifications and supervision of work for the repair and/or replacement of property damage caused by a covered peril, not to exceed 10% of the cost of the repair and/or replacement.

169

slide-77
SLIDE 77

Builder’s Risk

►The policy shall provide coverage for “all risks” of direct physical

loss or damage to the portions or elements of the Facility under construction, excluding terrorism but including the perils of earthquake, earth movement, flood, storm, tempest, windstorm, hurricane, and tornado and subsidence; shall contain extensions

  • f coverage that are typical for a project of the nature of the

Facility; and shall contain only those exclusions that are typical for a project of the nature of the Facility.

170

slide-78
SLIDE 78

Builder’s Risk

Section 1: Insurance Coverages Required Prior to Final Completion of the Project Assets

► Builder’s Risk Insurance for physical loss, destruction, or physical damage to the Work. The

Builder’s Risk insurance will cover the Concessionaire, Design-Build Contractor, the Department, and other Contractors of all tiers until Substantial Completion of all of the Project Assets; provided, that the limits of such coverage may be based on a maximum probable loss analysis, subject to the Department’s approval of such maximum probable loss analysis by an independent third party acceptable to the Department. In no event will the limits of such coverage be less than $250

  • million. Further, the policy will include sub-limits for certain specified perils including, but not

limited to: Offsite Storage, Property in Transit, Expediting Expenses, Demolition and Increased Cost of Construction, Debris Removal, Mobile Equipment and Professional Fees/Loss adjustment

  • expenses. The policy also will include replacement cost coverage for materials, supplies,

equipment, machinery, and fixtures that are or will be part of the Project. Coverage will include, but not be limited to, the following: right to partial occupancy; earthquake; earth movement; flood; transit; temporary and permanent works; expediting expenses; debris removal; offsite storage; delayed opening, commissioning; and start-up.

171

slide-79
SLIDE 79

Builder’s Risk

Section 2: Insurance Coverages Required for the Project following the Existing Assets Tolling and O&M Work Commencement Date

► Property and Business Interruption Insurance at replacement cost covering loss, damage, or

destruction to the Project, including improvements and betterments; provided, that the limits of such coverage may be based on a maximum probable loss analysis, subject to the Department’s approval of such maximum probable loss analysis by an independent third party acceptable to the Department. In no event will the limits of such coverage be less than $250

  • million. Coverage will include, but not be limited to, the following: flood, earthquake, earth

movement; collapse; water (including overflow); leakage; utility interruption; debris removal; business ordinance or law for increased costs of construction; extra expenses; valuable papers; and terrorism. Subject to the applicable deductible, such coverage also will insure against interruption or loss of projected Toll Revenues for at least six months from the occurrence of the risk, resulting from physical damage to the Project and any relevant feeder roads. The Department is to be named as an additional insured on a primary, non-contributory basis. The Concessionaire is responsible for all loss or damage to personal property (including but not limited to materials, fixtures/contents, equipment, tools, and supplies of the Concessionaire.

172

slide-80
SLIDE 80

Builder’s Risk

►All Risk Builders Risk Insurance or Installation Floater

► If Permittee is undertaking any construction, including

improvements, betterments and/or repairs, Permittee shall provide All Risk Builder’s Risk Insurance or an Installation Floater covering the materials, equipment, machinery and fixtures that are or will be part of the permanent facility. Extensions of All Risk Builders Risk coverage shall include earthquake, flood, materials in-transit and

  • ff-site, utility interruption, debris removal and delayed opening.

173

slide-81
SLIDE 81

Excess Liability Insurance

► Umbrella and Excess Liability Insurance with the following features:

► Coverage that provides excess coverage for Employers Liability, Commercial General

Liability, and Auto Liability, with the same features as described in sections A, B and D herein with limits not less than $5,000,000. Subcontractor acknowledges that it will provide Umbrella and Excess Liability Insurance on behalf of the Contractor and that the Umbrella and Excess Liability Insurance will be subject to vertical exhaustion before any

  • ther Primary, Umbrella or Excess Policies or any other insurance obtained by the

Contractor will be triggered. The total insurance coverage provided by Subcontractor for any claim will under no circumstances be less than the combined Primary limits as defined in Section A, plus the Umbrella and Excess limits as defined above. Subcontractor (vendor) further acknowledges that the total amount of insurance coverage provided by its insurance carriers, whether primary, excess, umbrella or other, where Contractor, and others, as specified above, are afforded additional insured coverage, shall apply as first tier/following form coverage. Any other insurance maintained by Contractor,

  • r any other additional insured shall be excess of this first tier coverage and shall not be

called upon to contribute to satisfy any loss within the limits specified and required above. Subcontractor shall furnish umbrella/excess policy language evidencing coverage to apply

  • n a primary and non-contributory basis to the Contractor as Additional Insured.

174

slide-82
SLIDE 82

Excess Liability Insurance

►Supplier shall carry Excess Liability Insurance that follows the form

  • f the underlying primary liability insurance required by employer’s

liability only, general liability, and automobile liability in an amount not less than $5,000,000 per occurrence and $5,000,000 in the aggregate.

175

slide-83
SLIDE 83

Professional Liability Insurance

►When any professional services, such as architecture, auditing,

construction design, engineering, mechanical design, or other service which requires professional certification and licensing by a governmental entity, is being provided to the Chicago Park District under the Permit, Professional Liability Insurance with limits of not less than $1,000,000 per occurrence for damages arising from any acts, errors or omissions. Coverage shall include severability of interest and cross-suit liability for consultants/sub-contractors. Claims-Made policies shall be renewed each year for a period of two (2) years after completion of the contract and shall have an extended reporting period of two (2) years. When renewed or replaced, the policy retroactive date must coincide with or precede start of work under the Permit.

176

slide-84
SLIDE 84

Professional Liability Insurance

►Design Service Requirements

► If Subcontractor or its sub-subcontractor performs design services,

Subcontractor will purchase, furnish and maintain or require its sub-subcontractor to purchase, furnish and maintain professional liability insurance with limits of at least $2,000,000 and with the following coverages: basic professional errors and omissions, punitive damages (where not prohibited by law), contractual liability, with a retroactive date that is no later than the date of inception of design services. Such coverage shall be maintained in effect for a period of five (5) years from the Date of Substantial Completion of the Project or the statute of repose, whichever is longer.

177

slide-85
SLIDE 85

Professional Liability Insurance

►Policy of professional liability insurance – appropriate to the

contractor’s operations. Coverages should be for a professional error, act or omission arising out of the scope of services required by this agreement. Such policy(ies) must provide the following limits:

► $5,000,000 per claim

178

slide-86
SLIDE 86

Professional Liability Insurance

►All claims based on acts, omissions, injury or damage occurring or

arising in whole or in part during the policy period must be

  • covered. If any required insurance is provided under a claims-

made policy, coverage must be maintained continuously for a period ending no less than three (3) years after recordation of a notice of completion for builder’s risk or the Compliance Term for general liability and property insurance.

179

slide-87
SLIDE 87

Pollution Liability Insurance

►When any pollution risk exposure is apparent, Pollution Liability

Insurance shall be provided on a blanket basis covering bodily injury, property damage and environmental restoration for claims arising out of performance of services including handling, clean-up and excavation of waste and hazardous materials. Limits required for each shall not be less than $1,000,000 each accident and general aggregate. Claims-Made policies shall provide an inception or retroactive date prior to the date of this agreement and be renewed each year for a period of three (3) years after termination of this agreement or provide an extended claims reporting period of not less than three (3) years after the termination of this agreement.

180

slide-88
SLIDE 88

Coverage Limits

181

slide-89
SLIDE 89

Coverage Limits

►CGL General Aggregate Limits – Per Project:

► We require that your CGL policy’s General Aggregate limit applies

separately to this project. By doing so we eliminate concerns that the limit could be eroded due to claims from other projects that you are working on. The “Project” box in the CGL section of the Certificate should be checked or the words “Per Project” should be typed in this section.

182

slide-90
SLIDE 90

Coverage Limits

►Any policy in a form of coverage that includes a general annual

aggregate limit or provides that claims investigation or legal defense costs are included in the general annual aggregate limit must be in amounts that are double the occurrence or claims limits specified above.

183

slide-91
SLIDE 91

Coverage Limits

►The City reserves the right to require an increase in insurance

coverage in the event the City determines the conditions show cause for an increase, unless Borrower demonstrates to the City’s satisfaction that the increased coverage is commercially unreasonable and unavailable to Borrower.

184

slide-92
SLIDE 92

Coverage Limits

►Limits of Insurance: Subcontractors insurance coverage shall

apply for the full amount of any loss up to each respective policy limit of liability and shall not be limited to the minimum required limits of this subcontract. In specifying minimum requirements herein, neither Contractor nor Owner assert or recommend this insurance as adequate to Subcontractor’s requirements. Subcontractor is solely responsible to inform itself of types of insurance or additional limits it may need beyond these.

185

slide-93
SLIDE 93

Additional Insured Coverage

186

slide-94
SLIDE 94

Additional Insured Coverage

►Acceptable Additional Insured endorsements include ISO Form CG

2010 1185 or the use of both ISO forms 2033 1001 and 2037 1001

  • together. Notwithstanding the foregoing, the use of any form, including

but not limited to ISO form 2010 0704 and/or 2037 0704 or later versions, are subject to review and will not be acceptable if they limit coverage to the Additional Insureds for liability caused by their acts or

  • missions, or those of the named insured (or someone acting on behalf
  • f the named insured). Endorsement wording that states that coverage

will be excess of any other policies for which the parties to be named as additional insureds (per paragraph f above) have additional insured status is likewise unacceptable. A copy of the additional insured endorsement shall be provided to the Contractor for approval prior to commencement of work.

187

slide-95
SLIDE 95

Additional Insured Coverage

►The insurance required by General Liability, Automobile Liability,

and Excess Liability (if required) Sections shall include Company, its direct and indirect subsidiaries and affiliates including Limited Liability Companies, as additional insureds with respect to all

  • perations and work hereunder, as to the full limits of liability

purchased by the Contractor (including limits greater than the minimum limits required herein).

188

slide-96
SLIDE 96

Additional Insured Coverage

►Developer, TxDOT and the Design-Build Contractor shall be the

named insureds on the policy as their respective interests appear. Developer also may, but it not obligated to, include other contractors as named insured as their respective interests appear. The policy shall be written so that no act or omission of any insured shall vitiate coverage of the other named insureds. Developer may name itself or the Collateral Agent as loss payee under the policy.

189

slide-97
SLIDE 97

Additional Insured Coverage

►Subcontractor shall provide the following ISO Endorsements or

their functional equivalents:

a)

CG 20 33 10 01 (Additional Insured – Owners, Lessees or Contractors – Automatic Status when required in Construction Agreement with You)

b)

CG 20 10 10 01 (Additional Insured – Owners, Lessees or Contractors – Scheduled Persons or Organization) if applicable for Owner or other persons or entities

c)

CG 20 37 07 04 (Additional Insured – Owners, Lessees or Contractors – Completed Operations)

d)

CG 24 04 10 93 (Waiver of Transfer of Rights of Recovery Against Others to Us)

190

slide-98
SLIDE 98

Additional Insured Coverage

►All liability policies must provide that the insurance is primary to

any other insurance available to the additional insureds with respect to claims arising out of this Agreement, and that insurance applies separately to each insured against whom claim is made or suit is brought and that an act of [sic] omission of the named insureds that would void or otherwise reduce coverage will not void or reduce coverage as to any other insured, but the inclusion

  • f more than one insured will not operate to increase the insurer’s

limit of liability.

191

slide-99
SLIDE 99

Additional Insured Coverage

►Additional Insured Protection to be “Primary and Non-

Contributory”:

► We require subcontractors to have the additional insured language

structured so that it is “primary and noncontributory” as respect insurance contractor maintains. This means that your policy must respond in defense of contractor first and with no contribution of coverage from contractor’s policies.

192

slide-100
SLIDE 100

Waivers of Subrogation

193

slide-101
SLIDE 101

Waivers of Subrogation

►The insurance policies for all Subcontractor’s insurance shall

include a waiver of subrogation as follows: “It is agreed that in no event shall these insurance companies have any right of recovery against ABC Builders, its parents and affiliates, XYZ Development LLC, 123 Development LLC, East 456 Developers LLC, their parent and affiliates (to the extent applicable) or any other additional insured as required in the Owner/Contractor Agreement.”

194

slide-102
SLIDE 102

Waivers of Subrogation

►The insurance required by workers’ compensation and employers’

liability, general liability, automobile liability, excess liability (if applicable), and professional liability (if applicable) such Sections shall include full waivers of subrogation in favor of Company, including its direct and indirect affiliates, limited liability companies, unless waiver of subrogation is prohibited by law governing such insurance.

195

slide-103
SLIDE 103

Waivers of Subrogation

►Waiver of Subrogation – Rights of subrogation against additional

insureds are waived and Subcontractor will provide Contractor with a copy of ISO Endorsement CG 24 04 10 93 as evidence of coverage.

196

slide-104
SLIDE 104

Certificates of Insurance

197

slide-105
SLIDE 105

Certificates of Insurance

►The reverse side of the certificate must list each of the above

items a through f, and the following statement must precede the listing: “This certificate warrants that:”

198

slide-106
SLIDE 106

Certificates of Insurance

►The certificate of contractor’s general liability insurance shall

certify that any policy restrictions or exclusions (such as “care, custody and control”) have been deleted from the policy and no similar restrictive clauses or exclusions have been included.

199

slide-107
SLIDE 107

Certificates of Insurance

►Prior to commencing Work, Subcontractor shall furnish Contractor

with certificate(s) of insurance executed by a duly authorized representative of each insurer, as evidence of compliance with the insurance requirements set forth above. Such certificates of insurance shall be accompanied by copies of endorsements evidencing coverage afforded to Contractor and Owner as additional insureds, and endorsements reflecting insurer’s concurrence with Subcontractor’s waiver of recovery or subrogation rights.

200

slide-108
SLIDE 108

Notice of Cancellation

201

slide-109
SLIDE 109

Notice of Cancellation

►The above insurances shall each contain the following wording

verbatim:

► Construction Manager is interested in the maintenance of this

insurance and it is agreed that this insurance will not be canceled, materially changed or not renewed without at least a thirty (30) day advance written notice to the Construction Manager sent by certified mail – return receipt requested. Note: If an “Accord” [sic] certificate of insurance is used, it must not include any wording in the cancellation clause, such as “endeavor to” and “but failure to mail such notice shall impose no obligation or liability of any kind upon the company.”

202

slide-110
SLIDE 110

Notice of Cancellation

►All policies required by this Agreement must be endorsed to

provide no less than thirty (30) days’ written notice to the City before cancellation or intended non-renewal is effective.

203

slide-111
SLIDE 111

Miscellaneous Requirements

204

slide-112
SLIDE 112

Miscellaneous Requirements

►Contractor shall not permit any subcontractor to enter upon or

continue performance unless subcontractor is and remains insured in accordance with these requirements.

205

slide-113
SLIDE 113

FAR § 28.302

►When coverage is provided by self-insurance, the contractor shall

not change or decrease the coverage without the Administrative Contracting Officer’s prior approval.

206

slide-114
SLIDE 114

Miscellaneous Requirements

►Self-insurance – should the contractor be self-insured, for any or

all of the above insurance requirements, a letter from the corporate risk manager, or appropriate finance office, is acceptable – stipulating if actuarially funded and fund limits; plus any excess declaration pages to meet the contract requirements. This letter should also advise how the contractor would protect and defend Electric Boat Corporation as an additional insured in its self- insured layer, and include claims handling directions in the event

  • f a claim.

207

slide-115
SLIDE 115

Miscellaneous Requirements

►Contractor shall include all subcontractors as insureds under its

policies or be responsible for verifying and maintaining the certificates provided by each subcontractor.

208

slide-116
SLIDE 116

Miscellaneous Requirements

►Subcontractors – contractor shall include all subcontractors as

insureds under its policies or shall furnish separate certificate of insurance, as stated above, for each subcontractor. All coverages for subcontractors shall be subject to all the requirements stated herein and applicable to their profession.

209

slide-117
SLIDE 117

Miscellaneous Requirements

►Sub-subcontractor Insurance Requirements

► Subcontractor shall obtain insurance coverage from each of its

sub-subcontractors or suppliers that is equal to or greater than that required of Subcontractor.

210

slide-118
SLIDE 118

Miscellaneous Requirements

►Any failure of the Contractor to comply with reporting provisions of

the policy shall not affect coverage provided to the Agency, its

  • fficers, agents, employees and volunteers.

211