Senior Thesis Analysis Topics Alternate Formwork System Evaluation - - PowerPoint PPT Presentation
Senior Thesis Analysis Topics Alternate Formwork System Evaluation - - PowerPoint PPT Presentation
Senior Thesis Analysis Topics Alternate Formwork System Evaluation (Depth Analysis) The Green Building Reference Guide (Depth Analysis) Office Tower Structural Redesign (Breadth Analyses) Introduction Occupants Headquarters of
Senior Thesis Analysis Topics
Alternate Formwork System Evaluation (Depth Analysis) The Green Building Reference Guide (Depth Analysis) Office Tower Structural Redesign (Breadth Analyses)
Introduction
LEED Rating
Arlington’s first LEED rated
- ffice building (Silver Rating)
Occupants
Headquarters of United States Navy League Retail, Offices
Design
Skewed plan 212,947 sq.ft. 7- story office tower 164,561 sq.ft. 4 - story sub-grade parking garage
Structure M.E.P.
VAV system Copper bus duct power risers Office tower: structural steel Parking garage: C.I.P. concrete
Introduction
Project Background
Project Team
Main Subcontractors:
Concrete: Southland Concrete Structural Steel: Strait Steel Electrical: J.E. Richards Mechanical/Plumbing: W.E. Bowers
Owner: U.S. Navy League Architect: Page Southerland Page LLC Owner’s Representatives: The Keech Company LLC, Lincoln Properties General Contractor: James G. Davis Construction Corp.
GMP Contract Lump Sum Contracts
Project Background
Start Date: 5/8/2003 Scheduled Completion Date: 4/26/2005
Project Schedule Project Delivery
Design – Bid - Build
Building Costs
Alternate Formwork System Evaluation
As-built System:
Aluminum framing & plywood sheathing Labor and material intensive
Analysis Overview & Goals
Alternate System:
Accommodate existing design Reusable components
Goals:
Decrease formwork budget & duration Improve sustainability aspects
Alternate Formwork System Evaluation
Mid-State Filigree Systems
Available Formwork Systems
Peri ‘Skydeck’ ‘Tabla’ by Gillespie Practical Technologies, Inc. ‘Titan HV’
Alternate Formwork System Evaluation
Slab Design Factors
Alternate Formwork System Evaluation
Slab Design Factors
First Floor Slab Framing Plan
Alternate Formwork System Evaluation
Design Characteristics
Formwork System Selection
Engineering Material Costs Labor Local Codes Reusability Viable Alternate System: ‘Titan HV’
Accommodates design Potential labor savings FSC plywood compatible
Alternate Formwork System Evaluation
Cost & Production Factors
Alternate Formwork System Evaluation
Conclusion
Reusability
Excellent Satisfactory Poor
Local Codes Labor Material Costs Engineering Design Characteristics
Titan HV System Standard System Selection Criteria
Standard aluminum system is best option for the parking garage
The Green Building Reference Guide
Analysis Overview & Goals
LEED ratings & sustainable design Additional planning and management required Unnecessary costs and possible delays Lack of dedicated construction resources
Issues: Solution:
Easily accessible network of resources Organize online resources through structured website
Goals:
Develop website to aid construction professionals Increase knowledge = better chances of project’s success
Reference Guide Development
Form: Form Function Content
Readily accessible platform: website Free to use & kept current Targeted organization & direct format Database of available online resources Main Topics:
Material Procurement Indoor Environmental Quality Commissioning Waste Management Site Management
The Green Building Reference Guide
Reference Guide Development
Function:
Website demonstration:
The Green Building Reference Guide
Reference Guide Development
Content:
Filtered content Benefits: reduces search time, increases productivity User input for future development & expansion
The Green Building Reference Guide
Conclusions
GBRG created to address needs of building professionals Targeted, organized content in graphical format Positive feedback indicates value and potential
The Green Building Reference Guide
Office Tower Structural Redesign
Analysis Overview & Goals
Issues: Solution:
Design C.I.P. concrete office tower Establish costs & duration of alternate system
Goals:
Reductions in budget and schedule with concrete tower System with least environmental impact Structure transitions from concrete garage to steel tower Inherent difficulties of steel: cost, time M.E.P. coordination Environmental impact of steel production
Images of structural steel erection
Office Tower Structural Redesign
Concrete Structure Design Development
Criteria: Design Consideration:
Given span length, post-tensioning required Develop schematic design Maintain current structural layout and clearances Maintain open plan office spaces
Characteristics of Current Structural Steel System Dimensions
Floor to Floor Height
13’- 4”
Maximum Member Depth
24”
Composite Slab Thickness
6”
Maximum Bay Span
43’
Office Tower Structural Redesign
Concrete Structure Analysis
Slab Type Thickness (in) 12 Width (in) 36 Concrete Columns Beams Slab 5000 5000 5000 Steel Reinforcement Post-Tensioning Cables System Type Unbonded 0.153 in^2 (7/16" Diam.) Loading
- Typ. Floor
Roof Uniform 80 psf 100 psf Columns Size 14" x 14" Two-way, Flat Slab Strength (psi) Ultimate Tendon Strength 270 ksi Design Load 150 (Normal weight) Bar Yield Strength (fy) Modulus of Elasticity Clear Bar Cover Floor to Floor Height 13' - 6"
Post-Tensioning Design Characterisitics
29,000 ksi 1" 60 ksi Type Unit Weight (psf) Area of Tendons Slab Dimensions Drop Panel Dimensions Tributary Width (ft) Span Length (ft) 30 29.5 to 43 Length (in) 36 Depth (in) 8
Office Tower Structural Redesign
Concrete Structure Analysis
Rendering of C.I.P. Concrete Slab, Columns, & Drop Panels
12” Thick Post-Tensioned Slab 36” x 36” x 8” Deep Drop Panel, Typical
Office Tower Structural Redesign
Budget & Schedule Comparison
Cost difference of $863,000 Concrete is 33% more expensive than steel
Office Tower Structural Redesign
Budget & Schedule Comparison
Office Tower Structural Redesign
Additional Topics
Applications of Alternate Formwork System
‘Titan HV’
Structural & M.E.P. Coordination Environmental Impact: Concrete vs. Steel
Benefits of steel = benefits of concrete
Office Tower Structural Redesign
Structural & M.E.P. Coordination
Coordination Plan:
H.V.A.C. Plan with C.I.P. System Overlay
Office Tower Structural Redesign
Conclusions
Most appropriate Equal advantages Least appropriate
Environmental Impact M.E.P. Coordination Total Duration Total Cost
Post-Tensioned Concrete System
Steel System
Analysis Criteria Structural steel provides greater value most appropriate
Conclusions
Alternate Formwork System Evaluation The Green Building Reference Guide Office Tower Structural Redesign
Most viable: Titan HV system Titan HV: greater cost & duration Selected standard aluminum system Logically organized, up-to-date list of resources Positive feedback indicates potential Post-tensioned, C.I.P. concrete structural system
Greater overall cost and duration Equal environmental impact
Existing steel system offers best value
Acknowledgements
I would like to thank the following people for their help and support in the development of this Senior Thesis Project:
Penn State University
- Dr. Michael Horman (Thesis Advisor)
- Dr. David Riley
- Dr. Kevin Parfitt
James G. Davis Construction Corp
Bill Moyer Dave Purdy Hasan Alsayegh Kim Pexton
The Keech Company
Bill Keech Sr. Bill Keech Jr.
Personal Contacts
My fiancé, Diane My family My friends Southland Concrete
Mark Aulabaugh
Titan Formwork Systems, LLC
Paul Tauscher
Arlington County, Virginia
Michael Lewis