Sefton Council
VIABILITY IN PLANNING Wednesday 23 April 2014
keppie massie
www.keppiemassie.com
Sefton Council VIABILITY IN PLANNING Wednesday 23 April 2014 - - PowerPoint PPT Presentation
Sefton Council VIABILITY IN PLANNING Wednesday 23 April 2014 keppie massie www.keppiemassie.com Overview Introduction What is Viability? Financial Appraisals: Key Variables Worked Example Relevance to Sefton
Sefton Council
VIABILITY IN PLANNING Wednesday 23 April 2014
keppie massie
www.keppiemassie.com
Overview
Introduction
Importance of Viability in Planning
How it is being considered by LPAs
Changing times
Purpose of the Economic Viability Assessments
Borough Wide
development'
deliverable by considering the Viability of development Case by Case
that "Pursuing sustainable development requires careful attention to viability
and costs in plan-making and decision-taking. Plans should be
the plan should not be subject to such a scale of obligations and policy burdens that their ability to be developed viably is threatened. To ensure
viability, the costs of any requirements likely to be applied to
development, such as requirements for affordable housing standards, infrastructure contributions or other requirements should, when taking account of the normal cost of development and mitigation, provide competitive returns to a willing land owner and willing developer to enable the development to be deliverable"
111%,^1011
What is Viability?
04.011■
Guidance
RICS Guidance Note `Financial Viability in Planning'
What is viability? "an objective financial viability test of the ability of a development project to meet its costs including the cost of planning obligations, whilst ensuring an appropriate site value for the land owner and a market risk adjusted return to the developer in delivering that project."
Guidance
'Viability Testing Local Plans' - Local Housing Delivery Group
"The approach to assessing plan viability should recognise that it can only provide high level assurance that the policies within the plan are set in a way that is compatible with the likely economic viability. It cannot guarantee that every development in the plan period will be viable, only that the plan policies will be viable for the sufficient number of sites upon which the plan relies in
OW
What is Viability?
p
i.._,..:,
0%0%0
What is Viability?
A Residual Valuation A Development Appraisal
What is Viability?
Policy Purposes
Gross Development Value (value of the completed development scheme)
,Lii.
Less
Cost of Development (inclusive of build costs, fees, finance, land cost)
Less Other Costs (inclusive of existing planning obligations) Less
Developers Target Profit = Development Surplus or "Headroom"
What is Viability?
Approach to Testing for Policy Purposes
1
140%01
1
1
What is Viability?
Recap
including the cost of planning obligations
development less the development costs
Financial Appraisals: Key Variables
Financial Appraisals
Key Variables include:-
0%0%0
Financial Appraisals: Key Variables
Gross Development Value
Financial Appraisals: Key Variables
Construction Costs
W
Financial Appraisals: Key Variables
Development Programme
W
Lrp
Financial Appraisals: Key Variables
Other Costs
040
1
1i011
Financial Appraisals: Key Variables
Acquisition Costs/Land Value
Financial Appraisals: Key Variables
Developer's Profit
01140■
%0IN
Financial Appraisals: Key Variables
S106 and CIL
0%011,0*
Worked Example
Options if Unviable
What does it show?
below the required level for either the site to be released or for the
developer to proceed Options therefore include:-
Options if Unviable
Worked Example
GDV
—
6x houses @ £200,000 each Less Costs 1,250 sq.ft GIA E1.00psf x 6 houses
£1,200,000
£
750/ 000 Contingency @ 5%
E
37,500 Professional fees @ 10%
E
75,000 Finance on land/build costs (50% over 3 mths)
E
13,125 Agents Fees @ 2%
E
24,000 New road access to site
E
50,000 Community Centre Contribution
E
50/000 Land Value £
60,000
E 1,059,625 Residual Profit
E
140,375
Options if Unviable
Worked Example
instance we would expect a developers profit requirement of 15.0%
profit increases to £190,375 or 15.9% of GDV and the scheme is viable
same impact however the development would not be able to proceed as this is essential infrastructure
°148t16 1
#,
11
121 '
1111
Option if Unviable
What Next
— What planning requirements are needed — When these are to be paid/undertaken — Should the scheme be reappraised
010
1%0
1
1
Relevance to Sefton
Relevance to Sefton
Policy
Relevance to Sefton
Policy
OW
Conclusions
Conclusions
What are we seeking to achieve?
Requirements
W
Conclusions
the implications of Viability
Sefton Council
Any further questions please contact
Ged Massie
Partner
0870 705 0001
keppie massie
www.keppiemassie.com