rydal park
play

Rydal Park: Medical Center Addition Architectural Engineering - PowerPoint PPT Presentation

Rydal Park: Medical Center Addition Architectural Engineering Construction Management Senior Thesis April 12 th , 2010 Consultant: Dr. Magent Matthew Dabrowski Aerial View of the Medical Center Addition Architectural Engineering Spring 2010


  1. Rydal Park: Medical Center Addition Architectural Engineering Construction Management Senior Thesis April 12 th , 2010 Consultant: Dr. Magent Matthew Dabrowski Aerial View of the Medical Center Addition Architectural Engineering Spring 2010 – Senior Thesis

  2. Presentation Outline I. Introduction II. Analysis I: Integrated Project Delivery III. Analysis II: Mechanical System Energy Efficiency IV. Analysis III: Photovoltaic Array Feasibility V. Final Conclusions and Recommendations VI. Acknowledgements VII. Questions Matthew Dabrowski – Construction Management Architectural Engineering Spring 2010 – Senior Thesis Architectural Engineering Spring 2010 – Senior Thesis

  3. Project Background Rydal Park CCRC Medical Center Project Title: Facility for the Memory Impaired Function: Presentation Outline: Rydal Park, Jenkintown, PA Location: I. Introduction $26,590,000 A. Project Background Project Cost: II. Analysis I: Integrated Project Delivery Nov 2009 – May 2011 Construction duration: III. Analysis II: Mechanical System Efficiency 142,862 SF / 5 Stories (2 Parking / 3 Living) Building Size: IV. Analysis III: Photovoltaic Array Analysis Design-Bid-Build & Project Delivery Method: Negotiated GMP V. Final Conclusions and Recommendations Figure: Location – Jenkintown, PA 1 Matthew Dabrowski – Construction Management Architectural Engineering Spring 2010 – Senior Thesis

  4. Project Team Presby’s Inspired Life Owner: Architect: Stewart & Conners Architects Presentation Outline: Construction Manager: Whiting- Turner I. Introduction Developer: Greenbrier Development B. Project Team Structural Engineer: WK Dickson & Co. II. Analysis I: Integrated Project Delivery MEP Engineer: Moore Enigneering Co. III. Analysis II: Mechanical System Efficiency IV. Analysis III: Photovoltaic Array Analysis V. Final Conclusions and Recommendations Figure: project delivery org chart 2 Matthew Dabrowski – Construction Management Architectural Engineering Spring 2010 – Senior Thesis

  5. Overview of Analysis Analysis I: Integrated Project Delivery Critical Industry Issue / MAE • Presentation Outline: Pinpoint elements of success to guide future projects • I. Introduction Analysis II: HVAC System energy Efficiency C. Analyses Overview Mechanical Breadth • Decrease energy consumption with an Alt. HVAC system II. Analysis I: Integrated Project Delivery • III. Analysis II: Mechanical System Efficiency Analysis III: Photovoltaic Panel Feasibility IV. Analysis III: Photovoltaic Array Analysis Structural Breadth / MAE • Determine appropriateness with a Life Cycle Cost • V. Final Conclusions and Recommendations Figure: Various analysis Images 2 Matthew Dabrowski – Construction Management Architectural Engineering Spring 2010 – Senior Thesis

  6. Introduction and Background PACE Fall 2009: Participant, “A successful Design-Build Project?” Presentation Outline: Penn State Owner, Architect, Contractor Project Team: I. Introduction Disconnected, Lacking Collaboration PACE • II. Analysis I: Integrated Project Delivery Fragmentized preconstruction period • A. Introduction and Background Research Goal (critical industry issue) III. Analysis II: Mechanical System Efficiency Industry Students pinpoint successful elements within the Integrated Project • Delivery model IV. Analysis III: Photovoltaic Array Analysis Outline IPD characteristics for improving efficiency within • V. Final Conclusions and Recommendations the Rydal Park OAC project team Improve efficiency within the cm industry • Figure: s:pace logo & productivity index 4 Matthew Dabrowski – Construction Management Architectural Engineering Spring 2010 – Senior Thesis

  7. Integrated Project delivery Defining Elements: Presentation Outline: Early involvement of key participants • Shared risk / reward through Multi-party contracting • I. Introduction Collaborative decision making • Liability waivers / indemnification II. Analysis I: Integrated Project Delivery • C. AIA IPD Traditional vs. IPD Reallocation of upfront efforts • III. Analysis II: Mechanical System Efficiency Linear Design Process vs. Radial Inputs • IV. Analysis III: Photovoltaic Array Analysis V. Final Conclusions and Recommendations Figure: Design Process 5 Matthew Dabrowski – Construction Management Architectural Engineering Spring 2010 – Senior Thesis

  8. AIA’s Contract Language AIA’s 195 Family of Documents Presentation Outline: No significant differences to AIA cm @ risk contract • I. Introduction Tom Krajewski, DPR Project Executive: II. Analysis I: Integrated Project Delivery “I Call These AIA 195 Documents CM (@ risk) with a hug. The Contractor becomes the hook to keep the design within C. AIA’s IPD: Contract Language the GMP . The general conditions are supposed to bind everyone but the language still allows people to point III. Analysis II: Mechanical System Efficiency fingers at other parties.” IV. Analysis III: Photovoltaic Array Analysis V. Final Conclusions and Recommendations Figure: aia, ipd and dpr logos 6 Matthew Dabrowski – Construction Management Architectural Engineering Spring 2010 – Senior Thesis

  9. Case Studies Five Case studies Analyzed (2005-2009): Presentation Outline: Autodesk inc. Solutions Headquarters • Sutter Health Fairfield Medical Office Building • I. Introduction St. Clare health Center • Encircle Health Ambulatory Care Center II. Analysis I: Integrated Project Delivery • Cardinal Glennon Children’s Hospital • D. Case Studies Case studies were explored for: III. Analysis II: Mechanical System Efficiency Lessons learned • IV. Analysis III: Photovoltaic Array Analysis Elements of success • V. Final Conclusions and Recommendations Figure: Summary of IPD Case Studies 7 Matthew Dabrowski – Construction Management Architectural Engineering Spring 2010 – Senior Thesis

  10. OAC Project Team AE 572: Project Delivery and Contract Strategies Pinpointed critical project success factors • Design build extremely viable option Presentation Outline: • Owner (Presby’s Inspired Life): I. Introduction Lacking experience, looking to improve • II. Analysis I: Integrated Project Delivery Architect (Stewart-Conners): Young Company, specializing in Lodging • E. Rydal Park OAC Project Team Construction Manager (Whiting-Turner): III. Analysis II: Mechanical System Efficiency Experienced, well established in SE pennsylvania • Developer (Greenbrier): IV. Analysis III: Photovoltaic Array Analysis Experience, Specializes IN CCRC’s, Located in Texas • V. Final Conclusions and Recommendations Figure: Delivery and Contract Strageies 8 Matthew Dabrowski – Construction Management Architectural Engineering Spring 2010 – Senior Thesis

  11. Preconstruction Timeline Timeline developed after a project manager Interview (chip Cinamella) and reviewing precon documents Presentation Outline: Inefficient Elements: I. Introduction CM hired April 2008, not utilized for 7 months • II. Analysis I: Integrated Project Delivery Locations of the Architect and Developer • Owner placed project out to bid 9 months after cm was already • F. Detailed Preconstruction Timeline awarded contract improperly utilized “Value Engineering” session begins • III. Analysis II: Mechanical System Efficiency January-October 2009: Project hanging on 1.5% of total estimate • IV. Analysis III: Photovoltaic Array Analysis V. Final Conclusions and Recommendations Figure: Precon Timeline Jan – July 2009 9 Matthew Dabrowski – Construction Management Architectural Engineering Spring 2010 – Senior Thesis

  12. IPD Strategies Outline 12 Key Elements: 12 Key elements: 8. & 9. Designer / CM Roles (Different during Design & 1 . Owner Involvement: Determine Level and Adhere Constr. Phases): Outline professional boundaries Presentation Outline: 2. Budget Estimate: Determine if project is feasible 10. Meetings: Weekly Face-to-Face collaborative discussions I. Introduction 3. Core Team: Establish early, Utilize all parties 11. Drawings and Specifications: Manage Releases of II. Analysis I: Integrated Project Delivery addenda material properly, don’t hind info from subs 4. Contracting: Indemnification, “No-Sue” and relational G. IPD Strategies Outline 12. Closeout: All parties on excellent business terms by end of 5. Project Team Norms: Transparent / Cooperative Mgmt III. Analysis II: Mechanical System Efficiency project, Owner confident with IPD 6. 100% Open Books : All parties develop GMP , New Fee IV. Analysis III: Photovoltaic Array Analysis Structures required, Potential to create industry standard V. Final Conclusions and Recommendations 7. BIM Execution: Utilized new and effective technology Do not undermine: TRUST 10 Matthew Dabrowski – Construction Management Architectural Engineering Spring 2010 – Senior Thesis

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend