Ryan Lunsford 5/ 22/ 18 1 NYSE: WLL Vapor Collection System: - - PowerPoint PPT Presentation

ryan lunsford 5 22 18
SMART_READER_LITE
LIVE PREVIEW

Ryan Lunsford 5/ 22/ 18 1 NYSE: WLL Vapor Collection System: - - PowerPoint PPT Presentation

Life after the Thief Hatch Ryan Lunsford 5/ 22/ 18 1 NYSE: WLL Vapor Collection System: Design VCS Design Goals 1. Route tank vapors to combustion device or VRU. 2. Size VCS for adequate capacity to maintain system pressure below relief


slide-1
SLIDE 1

1

NYSE: WLL

Life after the Thief Hatch

5/ 22/ 18 Ryan Lunsford

slide-2
SLIDE 2

2

NYSE: WLL

Vapor Collection System: Design

VCS Design Goals

  • 1. Route tank vapors to

combustion device or VRU.

  • 2. Size VCS for adequate capacity

to maintain system pressure below relief device setpoints.

slide-3
SLIDE 3

3

NYSE: WLL

Vapor Collection System: Normal Operation

During Normal Operation, tank vapors are routed through the VCS to a combustion device.

slide-4
SLIDE 4

4

NYSE: WLL

Vapor Collection System: Normal Operation

The thief hatch can still be a source of fugitive emissions no matter how well designed the rest of the VCS.

slide-5
SLIDE 5

5

NYSE: WLL

Spring-Loaded Thief Hatch

  • Pressure spring relieves at setpoint (typically 8-16 osig setting)
  • Vacuum spring relieves at setpoint (-0.4 osig setting)
  • Two ‘leak points’ per device
slide-6
SLIDE 6

6

NYSE: WLL

Pilot Project: Lock-Down Hatch Configuration Can we replace spring-loaded thief hatch with lock-down hatch and:

  • Reduce or eliminate fugitive emissions from tank components
  • Reduce frequency of and cost associated with maintaining tank

components

  • Maintain adequate levels of pressure & vacuum relief for tank

systems

  • Maintain operability
slide-7
SLIDE 7

7

NYSE: WLL

Tank Devices: Relief and Access

Device Action Pressure Relief Vacuum Relief Tank Access

Thief Hatch Spring-loaded

Yes Yes Yes

Lock-Down Hatch Manually Open/ Close; Screw Tight

No No Yes

Pressure- Vacuum Relief Valve (PVRV) Weighted Pallet

Yes Yes No

slide-8
SLIDE 8

8

NYSE: WLL

Vapor Collection System: Emergency Operation

During Emergency Operation, the standard 4” tank connection is too small to accommodate required relief capacity

slide-9
SLIDE 9

9

NYSE: WLL

Pilot Project: Tank Modification

Order new tanks with 8” vent connection… and pre-installed Lock-Down hatch

slide-10
SLIDE 10

10

NYSE: WLL

Pilot Project: Tank Pressure Modeling

Modeled the egress of gas during emergency relief scenario to ensure tank pressure stayed within guidelines of API 2000. Determined:

  • PVRV Size
  • PVRV Spacing
  • Vent Pipe Sizing
slide-11
SLIDE 11

11

NYSE: WLL

Pilot Project: Access & Winterization

  • Piping design to allow

maintenance access to PVRV from catwalk

  • All PVRVs were heat traced

and insulated to protect from freezing

  • Tank systems have at least

two (2) relief devices

slide-12
SLIDE 12

12

NYSE: WLL

Pilot Project: Layout

Device Legacy Configuration Pilot Lock-Down Configuration

Thief Hatch

30

Lock-Down Hatch

30

PVRV

3 6

Pilot Project Q1 2017 – installed 30 lock-down hatches and 6

  • PVRVs. Eliminated 60 springs.
slide-13
SLIDE 13

13

NYSE: WLL

Pilot Project: Results

Upon commissioning the facility, the following results were found:

  • Initial inspection – corrected torque on lock-down hatch bolts
  • Second inspection – no leaks on lock-down hatches
  • Subsequent inspections – no leaks on lock-down hatches
  • Winter observation – no freeze-ups on PVRVs

Project was deemed a SUCCESS and rolled out to all new installations. Existing Locations: Economics do not support retrofit of existing locations due to extensive tank modifications

slide-14
SLIDE 14

14

NYSE: WLL

Summary

New batteries with Lock-Down configuration have experienced SIGNIFICANT reduction in work orders written to address fugitive emissions. Whiting Best Practices for New Tank Installations as of Q3’2017

  • 100% Lock-Down Hatch Configuration on new tank installations
  • All tanks ordered or installed with 8” vent connections
  • All PVRVs heat traced & insulated
  • No less than two (2) relief devices will be installed.