ryan lunsford 5 22 18
play

Ryan Lunsford 5/ 22/ 18 1 NYSE: WLL Vapor Collection System: - PowerPoint PPT Presentation

Life after the Thief Hatch Ryan Lunsford 5/ 22/ 18 1 NYSE: WLL Vapor Collection System: Design VCS Design Goals 1. Route tank vapors to combustion device or VRU. 2. Size VCS for adequate capacity to maintain system pressure below relief


  1. Life after the Thief Hatch Ryan Lunsford 5/ 22/ 18 1 NYSE: WLL

  2. Vapor Collection System: Design VCS Design Goals 1. Route tank vapors to combustion device or VRU. 2. Size VCS for adequate capacity to maintain system pressure below relief device setpoints. 2 NYSE: WLL

  3. Vapor Collection System: Normal Operation During Normal Operation, tank vapors are routed through the VCS to a combustion device. 3 NYSE: WLL

  4. Vapor Collection System: Normal Operation The thief hatch can still be a source of fugitive emissions no matter how well designed the rest of the VCS. 4 NYSE: WLL

  5. Spring-Loaded Thief Hatch • Pressure spring relieves at setpoint (typically 8-16 osig setting) • Vacuum spring relieves at setpoint (-0.4 osig setting) • Two ‘leak points’ per device 5 NYSE: WLL

  6. Pilot Project: Lock-Down Hatch Configuration Can we replace spring-loaded thief hatch with lock-down hatch and: • Reduce or eliminate fugitive emissions from tank components • Reduce frequency of and cost associated with maintaining tank components • Maintain adequate levels of pressure & vacuum relief for tank systems • Maintain operability 6 NYSE: WLL

  7. Tank Devices: Relief and Access Device Action Pressure Vacuum Tank Access Relief Relief Yes Yes Yes Thief Hatch Spring-loaded Manually Lock-Down No No Yes Open/ Close; Hatch Screw Tight Pressure- Yes Yes No Vacuum Relief Weighted Pallet Valve (PVRV) 7 NYSE: WLL

  8. Vapor Collection System: Emergency Operation During Emergency Operation, the standard 4” tank connection is too small to accommodate required relief capacity 8 NYSE: WLL

  9. Pilot Project: Tank Modification Order new tanks with 8” vent connection… and pre-installed Lock-Down hatch 9 NYSE: WLL

  10. Pilot Project: Tank Pressure Modeling Modeled the egress of gas during emergency relief scenario to ensure tank pressure stayed within guidelines of API 2000. Determined: -PVRV Size -PVRV Spacing -Vent Pipe Sizing 10 NYSE: WLL

  11. Pilot Project: Access & Winterization • Piping design to allow maintenance access to PVRV from catwalk • All PVRVs were heat traced and insulated to protect from freezing • Tank systems have at least two (2) relief devices 11 NYSE: WLL

  12. Pilot Project: Layout Pilot Project Q1 2017 – installed 30 lock-down hatches and 6 PVRVs. Eliminated 60 springs. Device Legacy Pilot Lock-Down Configuration Configuration 30 0 Thief Hatch 0 30 Lock-Down Hatch 3 6 PVRV 12 NYSE: WLL

  13. Pilot Project: Results Upon commissioning the facility, the following results were found: • Initial inspection – corrected torque on lock-down hatch bolts • Second inspection – no leaks on lock-down hatches • Subsequent inspections – no leaks on lock-down hatches • Winter observation – no freeze-ups on PVRVs Project was deemed a SUCCESS and rolled out to all new installations. Existing Locations: Economics do not support retrofit of existing locations due to extensive tank modifications 13 NYSE: WLL

  14. Summary New batteries with Lock-Down configuration have experienced SIGNIFICANT reduction in work orders written to address fugitive emissions. Whiting Best Practices for New Tank Installations as of Q3’2017 • 100% Lock-Down Hatch Configuration on new tank installations • All tanks ordered or installed with 8” vent connections • All PVRVs heat traced & insulated • No less than two (2) relief devices will be installed. 14 NYSE: WLL

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend