IESOTP 299-3b RT-GCG Cost Recovery Framework Status Update to TP September 13, 2016 Agenda 1. Rationale for Program Change 2. Engagement Timeline 3. Planned Maintenance 4. Market Rules Timeline and Next Steps 2 Rationale for Program


  1. IESOTP 299-3b RT-GCG Cost Recovery Framework Status Update to TP September 13, 2016

  2. Agenda 1. Rationale for Program Change 2. Engagement Timeline 3. Planned Maintenance 4. Market Rules Timeline and Next Steps 2

  3. Rationale for Program Change • Current RT-GCG Program untenable – Results from past GCG audits showed fundamental issues with participants interpreting market rules, cost eligibility and transparency • New cost recovery framework for the Real Time Generation Cost Guarantee (RT-GCG Program) • Will create a better understanding of incremental costs eligible to be submitted for recovery under the program and reduce the scope and frequency of audits • Pre-approved cost values and methodologies reviewed at least every three years 3

  4. Engagement Timeline • Series of regular stakeholder meetings from October 2015 to July 2016 – Consultations will continue until at least end of year • Consultation at each stage of development from a conceptual proposal to determined values – Supported by data – Clear principles and criteria for determination of eligible costs – All details of design, market rules and market manual content have been developed through engagement and presented to Technical Panel 4

  5. Planned Maintenance • Between June 7 and June 28, all Program participants were asked to provide information and appropriate supporting documentation relating to planned maintenance. • Once information provided to the IESO, one-on- one meetings scheduled for the IESO (and technical consultants) to discuss the information provided and ensure a common understanding of the scope, schedule, drivers and costs for planned maintenance activities included in participant’s cost submissions. 5

  6. Planned Maintenance • 5 of 14 participants provided required data by early July, and IESO and consultants met with them in early August • IESO received data from another 4 participants and met with them late August/early September • IESO waiting for data from remaining 5 participants • IESO cannot finalize pre-approved values until after rules are approved 6

  7. Review of Proposed Market Rule Amendment • April 26 TP meeting – Introduced proposed market rule amendment and presented draft rule language • May 31 TP meeting – Incorporate Panel feedback and presented rule amendment proposal – Presented details of proposed market manuals in response to the Panel’s request – Majority of Panel voted in favour to post for stakeholder comment • August 9 TP meeting – Responded to feedback from stakeholders and presented proposed rule changes – TP members raised issues concerning: • Stakeholder interest in providing input on Planned Maintenance • Specific market manual language – Vote to recommend to Board deferred to September 13 TP meeting 7

  8. Next Steps • September 13 TP – Proposed market rule amendment is substantively unchanged since August 9 TP • Minor changes to market rule amendment to ensure it is clear that the rules take precedence over the manuals – Vote to recommend to IESO Board for Approval – IESO will inform Panel once manuals are posted for comment – IESO will review market manual content through RT- GCG stakeholder engagement prior to posting 8

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.