Renewable Integration Study Next Steps
Mark Rothleder Director, Market Analysis and Development Working Group Meeting October 7, 2011
Renewable Integration Study Next Steps Mark Rothleder Director, - - PowerPoint PPT Presentation
Renewable Integration Study Next Steps Mark Rothleder Director, Market Analysis and Development Working Group Meeting October 7, 2011 PURPOSE AND PROCESS Mark Rothleder Slide 2 Purpose and Process Identify operational requirements and
Renewable Integration Study Next Steps
Mark Rothleder Director, Market Analysis and Development Working Group Meeting October 7, 2011
Slide 2
PURPOSE AND PROCESS
Mark Rothleder
Purpose and Process
Slide 3
prepared for the changes it the fleet
and needs
and perform final study work in Q1 2012
Current Advisory Team
Slide 4
Next Steps Schedule
Slide 5
Next Step Target Schedule Working group kick-off October 7, 2011 Requests for additional study work October 14, 2011 Triage and prioritize requests October 19, 2011 Perform priority analysis and review results October - December, 2011 Complete LCR/OTC analysis December, 2011 Scope final study work January 2012 Perform final study work January 2012-March 2012 Final results March 2012
Slide 6
REVIEW OF METHODOLOGY AND RESULTS
Mark Rothleder
Electricity is produced, delivered, and consumed at the speed of light while balance must be maintained.
Slide 7
Supply variability and uncertainty will increase while the flexible capability of the fleet is decreases
Slide 8
capacity will approximately double due to increase of variable resources
flexible capability will retire by 2020
Renewable integration study process quantifies
ability to meet operating requirements.
Slide 9
Renewable Portfolios Variable Resource Wind / Solar and Load Profiles Flexibility Requirements (Regulation, Balancing) Develop Profiles Shortages Infrastructure Needs Costs, Emissions Import/Export Capacity Factor Statistical Analysis/ model Production simulation
33% scenarios in 2020 cover range renewable and load conditions.
Slide 10
Case Case Title Description 1 33% Trajectory Based on contracted activity 2 Environmental Constrained High distributed solar 3 Cost Constrained Low cost (wind, out of state) 4 Time Constrained Fast development (out-of-state) 5 20% Trajectory For comparison 6 33% Trajectory High Load Higher load growth and/or energy program under-performance 7 33% Trajectory Low Load Lower load growth and/or energy program over-performance
Potential need for 4,600MW of upward flexible resources observed in the high-load scenario.
Slide 11
Out of approximately 3,500 MW downward balancing requirements, observed some hours of potential shortages.
Note: Downward balancing may be more effectively and efficiently managed using curtailment or storage rather than less economic dispatch
Slide 12
Slide 13
ADDITIONAL ANALYSIS OF RESULTS
Mark Rothleder
Decomposition of the operational requirements (1)
Slide 14
MW Hour
Spring Load Following Contributions by Forecast Error (33%HighLoad )
LFUp(L) LFUp(L+W) LFUp(L+W+1%err) LFUp(L+S) LFUp(L+S+1%err) LFDn(L) LFDn(L+W) LFDn(L+W+1%err) LFDn(L+S) LFDn(L+S+1%err)
Decomposition of the operational requirements (2)
Slide 15
MW Hour
Spring Regulation Contributions by Forecast Error (33%HighLoad )
RegUp(L) RegUp(L+W) RegUp(L+W+1%err) RegUp(L+S) RegUp(L+S+1%err) RegDn(L) RegDn(L+W) RegDn(L+W+1%err) RegDn(L+S) RegDn(L+S+1%err)
Decomposition of the operational requirements (3)
Slide 16
MW Hour
Summer Regulation Contributions by Technology (33%HighLoad )
RegUp(L) RegUp(L+S_DG) RegUp(L+S) RegUp(L+W) RegUp(L+W+S) RegDn(L) RegDn(L+S_DG) RegDn(L+S) RegDn(L+W) RegDn(L+W+S)
Decomposition of the operational requirements (4)
Slide 17
MW Hour
Summer Load Following Contributions by Technology (33%HighLoad )
LFUp(L) LFUp(L+S_DG) LFUp(L+S) LFUp(L+W) LFUp(L+W+S) LFDn(L) LFDn(L+S_DG) LFDn(L+S) LFDn(L+W) LFDn(L+W+S)
Decomposition of the operational requirements (5)
Slide 18
MW Hour
Spring Regulation Contributions by Technology (33%HighLoad )
RegUp(L) RegUp(L+S_DG) RegUp(L+S) RegUp(L+W) RegUp(L+W+S) RegDn(L) RegDn(L+S_DG) RegDn(L+S) RegDn(L+W) RegDn(L+W+S)
Decomposition of the operational requirements (6)
Slide 19
MW Hour
Spring Load Following Contributions by Technology (33%HighLoad )
LFUp(L) LFUp(L+S_DG) LFUp(L+S) LFUp(L+W) LFUp(L+W+S) LFDn(L) LFDn(L+S_DG) LFDn(L+S) LFDn(L+W) LFDn(L+W+S)
Actual Real-Time Upward Energy Dispatch:
Slide 20
1000 2000 3000 4000 5000 6000 7000 8000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MW HourFall RTD Dispatch Upward
1000 2000 3000 4000 5000 6000 7000 8000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MW HourSpring RTD Dispatch Upward
1000 2000 3000 4000 5000 6000 7000 8000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MW HourSummer RTD Dispatch Upward
1000 2000 3000 4000 5000 6000 7000 8000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MW HourWinter RTD Dispatch Upward
Actual Real-Time Downward Energy Dispatch:
Slide 21
Fall RTD Dispatch Dnward
Spring RTD Dispatch Dnward
Summer RTD Dispatch Dnward
Winter RTD Dispatch Dnward
PRM Resources: Assumptions vs. Performance
22
Assumed: deemed (or assumed) NQC value of resource Simulated: average resource performance during 50 constrained hours of PLEXOS simulation
Traj Env Cost Time All Gas LCR DA OTC 10 20 30 40 50 60 70 80 Assumed Simulated Assumed Simulated Assumed Simulated Assumed Simulated Assumed Simulated Assumed Simulated Assumed Simulated Assumed Simulated Total Capacity during Constrained Hours (GW) Imports RPS Gas Hydro Baseload
RPS Resources: Assumptions vs. Performance
23
Assumed: deemed (or assumed) NQC value of resource Simulated: average resource performance during 50 constrained hours of PLEXOS simulation
Traj Env Cost Time All Gas LCR DA OTC 1 2 3 4 5 6 7 8 9 Assumed Simulated Assumed Simulated Assumed Simulated Assumed Simulated Assumed Simulated Assumed Simulated Assumed Simulated Assumed Simulated Total Capacity during Constrained Hours (MW) Wind Solar Thermal Solar PV Geothermal Biomass
CAISO Resources Used During Top 50 Constrained
24
55,511 54,197 56,546 56,065 55,423
20,000 30,000 40,000 50,000 60,000 70,000 Traj Env Cost Time All Gas MW Reserves RU LFU Flex Maint Baseload Maint Imports Flex Gen RPS Gen Baseload Gen
High solar cases cause constraint to occur during hours with less load Gas resources provide more energy in All-Gas Case
Loads/resources balance for July 22, 2020 High Load Scenario
25
5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 45,000 50,000 55,000 60,000 65,000 HE14 HE15 HE16 HE17 HE18 MWISO Load/Resource Balance --- July 22, 2020
Awarded LF_Up Awarded A/S Demand Response Wind Solar GT Imports Hydro Biomass/Biogas Pump Storage CHP CCGT Nuclear Load + A/S Req. Load+A/S+LF_Up Req.Hydro patterns – 2006 High-Hydro Year
26 January February March April May June July August September October November December 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
CAISO Average Hydro Production - 2006
0-2,000 2,000-4,000 4,000-6,000 6,000-8,000
Hydro patterns – 2007 Low Hydro Year
27 January February March April May June July August September October November December 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
CAISO Average Hydro Production - 2007
0-2,000 2,000-4,000 4,000-6,000
Summary of previous requested work
Slide 28
Summary of previous requested work
Slide 29
Slide 30
1. 33% Renewable Integration studies
2. Annual resource adequacy evaluation
3. Frequency/Inertia Study
4. Distributed Energy Resources
Renewable integration related studies in progress at
Slide 31
FRAMEWORK FOR PROBABILISTIC ANALYSIS
Shucheng Liu
A stochastic model is developed to assess the probability of upward ramping capacity shortage.
assumptions
combinations and determine the probability of ramping capacity shortage
production simulation
Page 32
E3 Proposed Approach
33
Step 1: Calculate hourly flexibility reserve requirement
Current Methodology
Step 2: Test for
Loads, gen. profiles, imports, etc. Need
Potential Incorporation of Probabilistic Analysis
Step 1: Calculate hourly flexibility reserve requirement Step 2: Test for flexibility within base portfolio Loads, gen. profiles, imports, etc. Need Step 1.5: Perform probabilistic analysis based on range of conditions
The stochastic model considers uncertainties in some
following-up
Page 34
It is not a chronologic unit commitment simulation model.
etc.)
– Dispatching capacity economically to meet load first – Qualifying remaining capacity for ramping capacity to meet upward ancillary service and load following requirements
implemented
Page 35
Available ramping capacity depends on the balance of supply and load.
Page 36
Supply curve is constructed based on variable cost of each generation unit
Variation in load due to uncertainty affects availability
Page 37
Variation in supply due to uncertainty in renewable generation also affects availability of ramping capacity.
Page 38
Variations in both load and supply may occur at the same time.
Page 39
Available ramping capacity of each generation unit is qualified based on the following factors:
that can provide off-line non-spinning only)
Page 40
Available ramping capacity is used to meet ancillary service and load following requirements.
Page 41
Shortage may occur due to the variations in available ramping capacity and requirement.
Page 42
Variation range Variation range
The model is developed based on input and output data of the Plexos production simulation model.
– Hourly California load forecast – Hourly regulation and load following-up requirement – Hourly wind, solar, and hydro generation – California import limit and hourly import and export – Generator characteristics (capacity, ramp rate, forced and maintenance outage rates, etc.)
– Variable generation cost of each generation unit ($/MWh)
Page 43
These are examples of the input probability distribution functions fitted based on hourly sample data.
Page 44
Input probability distribution functions examples (cont.)
Page 45
Correlations among the stochastic variables are enforced.
Load Import Wind Solar Hydro RegU LFU Load Import Wind Solar Hydro RegU LFU
Page 46
Generation unit forced and maintenance outages are stochastically determined.
independently for each generation unit
function
Page 47
Monte Carlo simulation of the model produces probabilistic results.
stochastic model
distribution format
Page 48
This is an example of the Monte Carlo simulation result - probability distribution of 20-min ramping capacity sufficiency.
Page 49
The model can also be used in other ways for different purposes.
(without co-optimization), such as
– by ramp rates from high to low – least ramping capacity is left to meet upward AS and LF requirements – by ramp rates from low to high – most ramping capacity is left to meet upward AS and LF requirements
the system
Page 50
Commercial software is used to run Monte Carlo simulations of the model
with co-optimization
Frontline Risk Solver Platform for Excel http://solver.com/platform/risk-solver-platform.htm
Page 51
Question?
Page 52